Kingdom of Saudi Arabia

Saudi Telecom Company

Project Name: 5G 2022 - 5G4 - Access


Region: Central District: Riyadh

Preliminary Acceptance Test

Technology: LTE700 Collocated (30Mhz) with IoT

SITE ID: ZRH229

MOPNO.:
M-ERI-0168720

Job Numbers:
J-ZRH229-0000081
J-ZRH229-0000082
J-ZRH229-0000083
J-ZRH229-0000084
J-ZRH229-0000085

NRT-V-March2021
LTE SITE CHANGE ORDER
Wireless Network Design

Ref No 208613 Site Id ZRH229


Revision of SCO Dept. RF Design
Region Central Site 900 ZRH229
District Riyadh City Site LTE 2100 FRH229
Area Riyadh City Site LTE 700 XRH229
Site Address Al Rabwah Site Type Macro
Location Name Al Rabwah Vendor Ericsson
Location Type City Project 5G4
Latitude 24.6856 Phase .
Longitude 46.76164
Existing Configuration LTE 700 LTE 2100
Cell Id FRH229A FRH229B FRH229C
Antenna Type 80010892 80010892 80010892
No. of Antennas 0 0 0
Antenna Orientation 30 150 270
Mechanical Tilt 0 0 0
Electrical Tilt 4 4 4
Antenna Height 25.6 25.6 25.6
No. of Carriers 1 1 1
No. of Combiners
Combiner Types
Remote Elect Tilt Yes Yes Yes
TMA No No No
Carrier Band Width 20 Mhz 20 Mhz 20 Mhz
Type of MIMO 4x4 4x4 4x4
Shared Feeder less Shared NO Feeder less Y
E NodeB Model No No. of Node B RBS6102 No. of Node B 0
System Module No of SysMod BB6630 No of SysMod 1
RRU/RU Type 2212/2219
No. of RRU's IOT N 6

Proposed Configuration LTE 700 LTE 2100


Cell Id XRH229A XRH229B XRH229C FRH229A FRH229B FRH229C
Antenna Type 80010892 80010892 80010892 80010892 80010892 80010892
No. of Antennas 0 0 0 0 0 0
Antenna Orientation 30 150 270 30 150 270
Mechanical Tilt 0 0 0 0 0 0
Electrical Tilt 2 2 2 4 4 4
Antenna Height 25.6 25.6 25.6 25.6 25.6 25.6
No. of Carriers 2 2 2 1 1 1
No. of Combiners
Combiner Types
Remote Elect Tilt YES YES YES Yes Yes Yes
TMA NO NO NO No No No
Carrier Band Width 30 Mhz 30 Mhz 30 Mhz 20 Mhz 20 Mhz 20 Mhz
Type of MIMO 2x2 2x2 2x2 4x4 4x4 4x4

Shared NO Feeder less Y Shared NO Feeder less Y


E NodeB Model No. RBS6102 No. of Node B 0 RBS6102 No. of Node B 0
System Module BB6630 No of SysMod 0 BB6630 No of SysMod 0
RRU/RU Type 2219 2212/2219
No. of RRU's 3 IOT Y 6
Quality P Capacity P Coverage P
Comments Please rever to the comments page for the updated Remarks

Approval
ASIF T. MUHAMAD Ahmed Mohammed Elokr Ahmed Mohammed Elokr
Requested by Team Leader Manager
Date 17-JUL-22 Date 20-JUL-22 Date 20-JUL-22
LTE SITE CHANGE ORDER
Wireless Network Design

Ref No 208613 Site Id ZRH229


Revision of SCO Dept. RF Design
Region Central Site 900 ZRH229
District Riyadh City Site LTE 1800 ERH229
Area Riyadh City Site LTE 2300 TRH229
Site Address Al Rabwah Tech LTE 2300
Location Name Al Rabwah Site Type Macro
Location Type City Vendor Ericsson
Latitude 24.6856 Project 5G4
Longitude 46.76164 Phase .
Existing Configuration LTE 1800 LTE 2300
Cell Id ERH229A ERH229B ERH229C TRH229A TRH229B TRH229C
Antenna Type 80010892 80010892 80010892 EGZV5-65D-R6EGZV5-65D-R6EGZV5-65D-R6
No. of Antennas 1 1 1 0 0 0
Antenna Orientation 30 150 270 30 150 270
Mechanical Tilt 0 0 0 0 0 0
Electrical Tilt 4 4 4 4 4 4
Antenna Height 25.6 25.6 25.6 25.6 25.6 25.6
No. of Carriers 2 2 2 4 4 4
No. of Combiners
Combiner Types
Remote Elect Tilt YES YES YES Yes Yes Yes
TMA NO NO NO No No No
Carrier Band Width 35 Mhz 35 Mhz 35 Mhz 80 Mhz 80 Mhz 80 Mhz
Type of MIMO 4x4 4x4 4x4 2x2 2x2 2x2

IOT Y Shared NO Feeder less Y Shared NO Feeder less Y


E NodeB Model No RBS6102 No. of Node B 0 RBS6102 No. of Node B 0
System Module BB6630 No of SysMod 1 BB6630 No of SysMod 1
RRU/RU Type 2219 RRUS72/4418
No. of RRU's 6 6 DL UL Ratio 3:1

Proposed Configuration LTE 1800 LTE 2300


Cell Id ERH229A ERH229B ERH229C TRH229A TRH229B TRH229C
Antenna Type 80010892 80010892 80010892 EGZV5-65D-R6EGZV5-65D-R6EGZV5-65D-R6
No. of Antennas 1 1 1 0 0 0
Antenna Orientation 30 150 270 30 150 270
Mechanical Tilt 0 0 0 0 0 0
Electrical Tilt 4 4 4 4 4 4
Antenna Height 25.6 25.6 25.6 25.6 25.6 25.6
No. of Carriers 2 2 2 2 2 2
No. of Combiners
Combiner Types
Carrier Band Width 35 Mhz 35 Mhz 35 Mhz 35 Mhz 35 Mhz 35 Mhz
Type of MIMO 4x4 4x4 4x4 2x2 2x2 2x2
Remote Elect Tilt YES YES YES Yes Yes Yes
TMA NO NO NO No No No

IOT N Shared NO Feeder less Y Shared NO Feeder less Y


E NodeB Model No. RBS6102 No. of Node B 0 RBS6102 No. of Node B 0
System Module BB6630 No of SysMod 1 BB6630 No of SysMod 1
RRU/RU Type 2219 RRUS72
No. of RRU's 6 3 DL UL Ratio 3:1
Quality P Capacity P Coverage P Other Purpose
Comments Please rever to the comments page for the updated Remarks

Approval
ASIF T. MUHAMAD Ahmed Mohammed Elokr Ahmed Mohammed Elokr
Requested by Team Leader Manager
Date 17-JUL-22 Date 20-JUL-22 Date 20-JUL-22
3G SITE CHANGE ORDER
Wireless Network Design
Ref No 208613 Site Id ZRH229
Revision of SCO No Dept. RF Design
Region Central Site 900 ZRH229
District Riyadh City Site 3G 900 HRH229
Area Riyadh City Site 3G 2100 GRH229
Site Address Al Rabwah Frequence Band 900MHz & 3G
Location Name Al Rabwah Site Type Macro
Location Type City Vendor Ericsson
Latitude 24.6856 Project 5G4
Longitude 46.76164 Phase .
UMTS 900 Existing Configuration UMTS 2100
Cell Id HRH229A HRH229B HRH229C
Antenna Type EGZV5-65D-R6EGZV5-65D-R6EGZV5-65D-R6
No. of Antennas 0 0 0
Antenna Azimuth 30 150 270
Mechanical Tilt 0 0 0
Electrical Tilt 4 4 4
Antenna Height 25.6 25.6 25.6
No. of Carriers 2 2 2
No. of Combiners
Combiner Types
MCPA NO NO NO
RET Yes Yes Yes
TMA No No No

Node BType RBS6102 No. of Cabinet 0 Shared No. of NodeB Shared


RRU/RU Type RRUS12 No. of RRU's 0 GSM No. of RRU's
System Module DUW31 No. SysMod 2 No. SysMod Feeder less
Feeder less
CE DL 512 HSDPA 42 Mbps CE DL HSDPA
Y N
CE UL 512 HSUPA 2x5.6 Mbp CE UL HSUPA
UMTS 900 Proposed Configuration UMTS 2100

Cell Id HRH229A HRH229B HRH229C


Antenna Type EGZV5-65D-R6EGZV5-65D-R6EGZV5-65D-R6
No. of Antennas 0 0 0
Antenna Azimuth 30 150 270
Mechanical Tilt 0 0 0
Electrical Tilt 4 4 4
Antenna Height 25.6 25.6 25.6
No. of Carriers 2 2 2
No. of Combiners
Combiner Types
MCPA NO NO NO
RET Yes Yes Yes
TMA No No No

Node BType RBS6102 No. of Cabinet 0 Shared No. of Node B Shared


RRU/RU Type RRUS12 No. of RRU's 0 GSM No. of RRU's
System Module DUW31 No. SysMod 2 Feeder less No. SysMod Feederless
CE DL 512 HSDPA 42 Mbps Y CE DL HSDPA N
CE UL 512 HSUPA 2x5.6 Mbps CE UL HSUPA
Quality P Capacity P Coverage P Other Purpose
Comments Please rever to the comments page for the updated Remarks

Approval
ASIF T. MUHAMAD Ahmed Mohammed Elokr Ahmed Mohammed Elokr
Requested by Team Leader Manager
Date 17-JUL-22 Date 20-JUL-22 Date 20-JUL-22
SITE CHANGE ORDER
Wireless Network Design

Ref No 208613 Site Id ZRH229


Revision of SCO N Dept. RF Design
Region Central Site 900 ZRH229
District Riyadh City Site 1800
Area Riyadh City Site 3G GRH229
Site Address Al Rabwah Site Type Macro
Location Name Al Rabwah Vendor Ericsson
Location Type City Project 5G4
Latitude 24.6856 Phase .
Longitude 46.76164 Festival STC Share Zain site
Type of Change 900 MHZ 1800 MHZ
BTS Swap Antenna, Configuration Changes Combiner Changes BTS Type Changes

Decomissioning Add/Delete RTS Other Specify

900 Mh Existing Configuration 1800 Mhz


Cell Id ZRH229A ZRH229B ZRH229C
Antenna Type EGZV5-65D-R6 EGZV5-65D-R6 EGZV5-65D-R6

No. of Antennas 1 1 1
Antenna Orientation 30 150 270
Mechnical Tilt 0 0 0
Electircal Tilt 4 4 4
Antenna Height 25.6 25.6 25.6
No. RTs 4 4 4
No. Combiners
Combiner Types
MCPA NO NO NO

BTS Type RBS6102 Shared Shared


No. of Cabinets 1 UMTS
RRU/RU Type RRUS12 No of RRU's 3 Feeder less No of RRU's Feeder less
System Module DUG20 No SysMod 1 Y No SysMod

900 Mh Proposed Configuration 1800 Mhz


Cell Id ZRH229A ZRH229B ZRH229C
Antenna Type EGZV5-65D-R6 EGZV5-65D-R6 EGZV5-65D-R6

No. of Antennas 1 1 1
Antenna Orientation 30 150 270
Mechnical Tilt 0 0 0
Electircal Tilt 4 4 4
Antenna Height 25.6 25.6 25.6
No. RTs 4 4 4
No. Combiners
Combiner Types
MCPA NO NO NO

BTS Type RBS6102 Shared Shared


No. of cabinet 1 UMTS
RRU/RU Type RRUS12 No of RRU's 3 Feeder less No of RRU's Feeder less
System Module DUG20 No SysMod 1 Y No SysMod

Quality P Capacity P Coverage P Other Purpose Address To


Comments Please rever to the comments page for the updated Remarks

Approval
ASIF T. MUHAMAD Ahmed Mohammed Elokr Ahmed Mohammed Elokr
Requested by Team Leader Manager
Date 17-JUL-22 Date 20-JUL-22 Date 20-JUL-22
SITE CHANGE ORDER
Comments
Wireless Network Design

Ref_no # 208613 SiteId # ZRH229 Project # 5G4 Phase # .

Last Comments
SCO Issued under 5G-Phase4 Project for N40 4T4R Collocation,
* TDD downgrade to 2/2/2 Carrier 35MHz.
* 3x4418 and BB6630 reconfigure from TDD to N40 4T4R.
* LTE-700 Collocation 30Mhz with 3x2219
* NB-IoT transfer from L-1800 to L-700
Please view details in relevant technology part of SCO.
Old Comments

Reviewer Comment
VENDOR LOGO
Site Installation Inspection Checklist
Project Name: 5G 2022 - 5G4 - Access

Site No.: ZRH229 M-ERI-0168720

Job No.: J-ZRH229-0000081,J-ZRH229-0000082,J-ZRH229-0000083,J-ZRH229-0000084,J-ZRH229-0000085

1. Mechanical Installation
1.01 gNodeB BBU/AirScale / System Module / FSMF / DCDU Cabinet √ OK □ NOK □ N/A

1.02 RRU/AAU / AEQD √ OK □ NOK □ N/A

1.03 GPS system □ OK □ NOK √ N/A


1.04 Antenna /RET system/Jumpers √ OK □ NOK □ N/A

1.05 RRU/AAU Power cable/Fiber(CPRI) cable √ OK □ NOK □ N/A


2. Environment
Check the environment temperature Alarm indicator, Check if the air
2.01 √ OK □ NOK □ N/A
conditioners in the equipment room are running normally.
The normal running temperature range is from -5°C to +50°C, The temperature
2.02 of the environment where air conditioners are equipped is within the range of √ OK □ NOK □ N/A
+15°C to +35°C.
2.03 Check the environment humidity alarm indicator. √ OK □ NOK □ N/A
2.04 Check if the equipment room environment meets the dustproof requirement. √ OK □ NOK □ N/A
Check if the dust filters on the cabinet doors does not fall off or accumulate too
2.05 √ OK □ NOK □ N/A
much dust.

2.06 There are no fingerprints or other smears on the surface of the cabinet. √ OK □ NOK □ N/A

2.07 There are no excessive straps or adhesive tape on the cables. √ OK □ NOK □ N/A

2.08 No tapes, tails of cable ties, paper, or packing bags are left around the cabinet. √ OK □ NOK □ N/A

3. Mechanics:

3.01 The cabinet is placed according to design drawings. √ OK □ NOK □ N/A

3.02 The space for maintenance is enough. √ OK □ NOK □ N/A

3.03 The cabinet is not distorted. Paint on the cabinet surface is in good condition. √ OK □ NOK □ N/A

No parts on the cabinet are damaged or detached. No wires or cables are


3.04 √ OK □ NOK □ N/A
scratched or broken.

Connection between the cabinet and the base is secure. The cabinet stands still
3.05 √ OK □ NOK □ N/A
after installation.

No cable ties, cables, or desiccants are left in the cabling frame, under or inside
3.06 √ OK □ NOK □ N/A
the cabinet.
The cabinet is clean and neat with external paint in good condition. All labels,
3.07 √ OK □ NOK □ N/A
tags, and nameplates are correct, legible, and complete.

3.08 No tapes, tails of cable ties, paper, or packing bags are left around the cabinet. √ OK □ NOK □ N/A

NRT-V-March 2021
4. BBU / AirScale

4.01 The BBU / AirScale is placed according to design drawings. √ OK □ NOK □ N/A

4.02 The Labeling is placed according to standard. √ OK □ NOK □ N/A

4.03 The Grounding location is right. Use 6mm grounding cable. √ OK □ NOK □ N/A

4.04 The routing of the fiber is correct. √ OK □ NOK □ N/A

4.05 Transmission cable is connected to SFP 0 or FE/GE 0 of UMPT/UMPT √ OK □ NOK □ N/A

RRU/AAU / AEQD fiber of Section A is connected to CPRI0 of UBBP / LBBP / QSFP ,


4.06 √ OK □ NOK □ N/A
Another RRU/AAU fiber is connected to CPRI1 of UBBP / LBBP/QSFP

4.07 Power cable of BBU / Air Scale is connected to Load of DCDU / FPFH √ OK □ NOK □ N/A

5. DCDU / FPFH

5.01 The DCDU / FPFH is placed according to design drawings. √ OK □ NOK □ N/A

5.02 The breaker or the fuse is placed according to design drawings. √ OK □ NOK □ N/A

5.03 The Labeling is placed according to standard. √ OK □ NOK □ N/A

5.04 The Grounding location is right. Use 6mm grounding cable. √ OK □ NOK □ N/A

6. AAU / AEQD

6.01 The RRU/AAUs/ AEQD are placed according to design drawings. √ OK □ NOK □ N/A

6.02 The Labeling is placed according to standard. √ OK □ NOK □ N/A

6.03 The RRU/AAU/ AEQD Grounding location is right. Use 16mm grounding cable. √ OK □ NOK □ N/A

6.04 Fiber are connected to CPRI 0 of RRU/AAU/AEQD √ OK □ NOK □ N/A

6.05 The OCB Grounding location is right. Use 25mm grounding cable. □ OK □ NOK √ N/A

6.06 The metal shield of the power cable is grounded inside the OCB. □ OK □ NOK √ N/A

6.07 OCB is waterproofed. □ OK □ NOK √ N/A

Power cable is grounded (RRU/AAU/AEQD end): Grounded with metal shield inside the
6.08 √ OK □ NOK □ N/A
RRU/AAU cabling cavity.

6.09 Power cable is grounded (Grounding bat of Roxtec): Grounding with lightning proof clip. √ OK □ NOK □ N/A

6.1 The cover plate for the cabling cavity is securely installed. √ OK □ NOK □ N/A

6.11 Waterproof blocks are securely installed in vacant troughs of the RRU/AAU/AEQD √ OK □ NOK □ N/A

The vacant RF ports of RRU/AAU / AEQD are covered with waterproof caps and
6.12 √ OK □ NOK □ N/A
waterproofed.

6.13 The power cable is not circled. √ OK □ NOK □ N/A

6.14 7/8, 13/8 feeders are fitted with feeder clip. □ OK □ NOK √ N/A

6.15 7/8, 13/8 feeders are grounded. □ OK □ NOK √ N/A

6.16 The sharing sectors for RRU/AAU/AEQD: □ OK □ NOK √ N/A

6.17 Feeder installation for site operating with CPRI Optic Fiber should be marked as N/A □ OK □ NOK √ N/A

NRT-V-March 2021
7. GPS

7.01 The GPS are placed according to design drawings. □ OK □ NOK √ N/A

7.02 The Labeling is placed according to standard. □ OK □ NOK √ N/A

The arrester is grounded with the same grounded with the same ports of BBU. Use 6mm
7.03 □ OK □ NOK √ N/A
grounding cable.

7.04 The arrester is not touched with the cable tray. □ OK □ NOK √ N/A

7.05 The connectors of the feeders and jumpers are waterproof. □ OK □ NOK √ N/A

7.06 Feeders are not circled. □ OK □ NOK √ N/A

8. Antenna

8.01 The antennas are placed according to design drawings. √ OK □ NOK □ N/A

8.02 The Labeling is placed according to standard. √ OK □ NOK □ N/A

8.03 SBT, RCU are installed as design and cables are connected correct. □ OK □ NOK √ N/A

8.04 Jumpers, SBT, and RCU are well waterproofed. √ OK □ NOK □ N/A

8.05 The vacant RCU ports are securely covered. □ OK □ NOK √ N/A

The vacant RF ports of antenna are waterproofed. The vacant RET ports are securely
8.06 √ OK □ NOK □ N/A
covered.

The confirm of the antenna parameters:

8.07 Height: √ OK □ NOK □ N/A


Azimuth: √ OK □ NOK □ N/A
Mechanical Tilt: √ OK □ NOK □ N/A
9. Labels

9.01 Power Cable & Circuit Breaker √ OK □ NOK □ N/A

9.02 Transmission Cable ( Fiber and FE cable) √ OK □ NOK □ N/A

9.03 Fibers between BBU /FSMF /System Module AirScale and RRU/AAU/AEQD √ OK □ NOK □ N/A

9.04 Jumpers Cables √ OK □ NOK □ N/A

9.05 GPS Cables □ OK □ NOK √ N/A

9.06 Grounding Cables √ OK □ NOK □ N/A

Remarks:
Vendor Representative: STC \ O&M Representative:

Name: Ashfaq Name:

Signature: Ashfaq Signature:

Date: Date:

NRT-V-March 2021
VENDOR LOGO
Acceptance Test

Project Name: 5G 2022 - 5G4 - Access Vendor: Ericsson


JOB No.:
J-ZRH229-0000081,J-ZRH229-0000082,J-ZRH229-0000083,J-ZRH229-0000084,J-ZRH229-0000085

Work Type:
LTE700 Collocated (30Mhz)
Site No.: ZRH229 with IoT

Acceptance Tests
A. Site completion checklists

a. eNodeB (H/W specific) OK NOK Remarks


1 Power up Test √

2 Installation Verification √

3 Antenna System Test √

4 Site Integration Test √

UpLink RSSI Result ranges for different technologies
- 3G U900 Less than -95 Db minimum requirement
4
- 3G U2100 Less than -102 Db
- LTE 700 MHz Less than -100 Db.
√ □
- LTE 1800,2100, 2300 MHz Less than -105 Db.
- 5G Less than -110 Db.
b. Operation Verification Test. OK NOK Remarks
1 Power Failure Test
1.a. Description: Switch off DC input for the Telecom node
(Expected Result: Telecom Node is down) √

1.b. Description: Wait 15sec then switch on the power
{Expected Result: Telecom node comes up automatically and can
handle traffic. The O&M connection recovers correctly (Recovery time √
for eNodeB is about 10 minutes)} □
2 Restore after transmission interruption (Recovery time for eNodeB is
about 10 minutes) √

c. External Alarm check as per normal STC standard √ □
Remarks:

Vendor Representative: STC\ O&M Representative:

Name: Ashfaq Name:

Signature: Ashfaq Signature:

Date: Date:

PAGE 1

NRT-V-March 2021
VENDOR LOGO
ACCEPTANCE TEST

Project Name: 5G 2022 - 5G4 - Access SITE No.: ZRH229

J-ZRH229-0000081,J-ZRH229-0000082,J-ZRH229-0000083,J-ZRH229-0000084,J-ZRH229-
JOB No:
0000085

Work Type: LTE700 Collocated (30Mhz) with IoT


Remarks:____________________________
i. Visual Test: √ OK □ NOK ___

ii. Antenna System Test:


Sector 0 Sector 1 Sector 2
Check items
Design Actual Design Actual Design Actual

Antenna Numbers 0 0 0 0 0 0

Antenna Directions (Degrees) 30 30 150 150 270 270

Antenna Heights (Meters) 25.6 25.6 25.6 25.6 25.6 25.6

Antenna Models ( Provide screen shot


80010892 80010892 80010892 80010892 80010892 80010892
)

Antenna MDT 0 0 0 0 0 0

Antenna Electrical tilt / Digital Tilt 2 2 2 2 2 2

Fiber Length (Meters) 50 50 50

Vendor Representative : STC \ O&M Representative

NAME: Ashfaq NAME:

Signature: Ashfaq Signature:

DATE: DATE:

PAGE 2

NRT-V-March 2021
VENDOR LOGO
ACCEPTANCE TEST
Project Name: 5G 2022 - 5G4 - Access Site Number: ZRH229

J-ZRH229-0000081,J-ZRH229-0000082,J-
Job Number : ZRH229-0000083,J-ZRH229-0000084,J-ZRH229- Work Type: LTE700 Collocated (30Mhz) with IoT
0000085

1 CPRI Port for RBS ; 3 CPRI Ports for RRUS ;up to 6 CPRI ports for
RBS Radio Type:
RUS

Optical Parameter check of Optical Modules on CPRI interfaces (test via logs on OSS)

Optical Interface Parameters CPRI 0 (TX1) CPRI 1(TX2) CPRI 2(TX3) CPRI 3(TX4) CPRI 4(TX5) CPRI 5(TX6)

Optical Transmission Bit


SFP Module 10G 10G 10G
rate (2.5 Gbps or 10Gbps)
Optical Transmit Power
31.2(44.9) 21.1(43.2) 11.8(40.7)
(watts/dbm)
BB 1
Optical Receive Loss (dbm) 19.4 26.5 19.4

CPRI SFP Type SM SM SM


Remarks:

Vendor Representative: STC/O&M Representative:


NAME: Ashfaq NAME:

Signature : Ashfaq Signature :

DATE : DATE :
PAGE 3

NRT-V-March 2021
ALT

ASHFAQ
ASHFAQ
ANTENNA MODEL

ASHFAQ
ASHFAQ
RSSI

ASHFAQ
ASHFAQ
SLOTE LAYOUT / RRU LAYOUT / VSWR

ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
SFP INFO

ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
PING TEST

ASHFAQ
ASHFAQ
ASHFAQ
ASHFAQ
5G PHASE 4 PROJECT

DOCUMENT APPROVAL REQUEST


Civil Structural Architectural Mechanical Electrical

ERICSSON
Submittal No. : ERI-C22-ZRH229
MOP No. : M-ERI-0166794
Date : 28-Sep-2022
Project Title : 5G PHASE 4 PROJECT
Package Name : FINAL DETAILED ENGINEERING DESIGN (FDED) REV. B
Job No.1 : J-ZRH229-0000080
Site No. / Name : ZRH229 / EXISTING ZAIN SITE ID (2093) / RIYADH
No. of Copies :1
Vendor : ERICSSON
Description :
Final Detailed Engineering Design (FDED) for Site No. ZRH229 (ZAIN ID: 2093) Rev. B
Site Information:
Site Model: GF Tower Height: 30.0M Tower Supply: ZAIN Tower Type : ZAIN MOSAIC
TOWER
Shared with : ZAIN+ Shelter: ODU (RBS6102) Power Sup.:. SCECO HVAC: BUILT IN
MOBILY
Site Dimensions: 7X7 Recitifer: PSU/ 8X52A (EXISTING) Battery: 4X180AH (MISSING)

Area of used antenna or MW (EPA)/m2 : Top : 21.651M2 Middle : 0M2 Lower: 0M2

SAF no. N/A TCC No. N/A SCO no. 208613 NSCO no.
Attention : Design Manager
Wireless Network Implementation
For ERICSSON
Date : Name : Hassan Zobie Signature :

Jawal no.: 00966-504174409


For Saudi Telecom Company
Approval Codes :

ACCEPTED Accepted with comments REJECTED

Comments :

Signature
Wireless Network Implementation Design Manager
Name :

Date :
Signature :
REV DATE DESCRIPTION
REVISIONS

5G PHASE-4 PROJECT
SCO REF NO. 205586.

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
FAX. (01) 2301777 / 2302777

ZRH229 (ZAIN ID # 2093)


EXISTING GREENFIELD SITE / RIYADH
CIVIL SITE LAYOUT AND ELEVATION

ZRH229-ERI-Dc-0001
REV DATE DESCRIPTION
REVISIONS

5G PHASE-4 PROJECT
SCO REF NO. 205586.

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
FAX. (01) 2301777 / 2302777

ZRH229 (ZAIN ID # 2093)


EXISTING GREENFIELD SITE / RIYADH
CIVIL SITE LAYOUT AND ELEVATION

ZRH229-ERI-Dc-0001
REV DATE DESCRIPTION
REVISIONS

5G PHASE-4 PROJECT

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
SCALE NTS FAX. (01) 2301777 / 2302777

AZMI ABDUL HADI - LICENSE No. 13 - AL-KHOBAR, KSA

ZRH229 (ZAIN ID # 2093)

EXISTING GREENFIELD SITE / RIYADH


EXISTING FUSE ALLOCATION DIAGRAM

ZRH229-ERI-Fd-0001 A
REV DATE DESCRIPTION
REVISIONS

5G PHASE-4 PROJECT

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
SCALE NTS FAX. (01) 2301777 / 2302777

AZMI ABDUL HADI - LICENSE No. 13 - AL-KHOBAR, KSA

ZRH229 (ZAIN ID # 2093)

EXISTING GREENFIELD SITE / RIYADH


FINAL FUSE ALLOCATION DIAGRAM

ZRH229-ERI-Fd-0002 A
REV. DATE DESCRIPTIONS

REVISIONS
CONFIDENTIALITY:

5G PHASE-4 PROJECT

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
FAX. (01) 2301777 / 2302777

AZMI ABDUL HADI - LICENSE No. 13 - AL-KHOBAR, KSA

TITLE: ZRH229 (ZAIN ID # 2093)

EXISTING GREENFIELD SITE / RIYADH


EXISTING EQUIPMENT SHELTER FLOOR PLAN LAYOUT
DRAWN: DESIGNED: SCALE: DATE:

CHECKED CADD: DRAWING NO: REV.

CHECKED QUALITY:
ZRH229-ERI-FP-0001 A
APPROVED:
REV. DATE DESCRIPTIONS

REVISIONS
CONFIDENTIALITY:

5G PHASE-4 PROJECT

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
FAX. (01) 2301777 / 2302777

AZMI ABDUL HADI - LICENSE No. 13 - AL-KHOBAR, KSA

TITLE: ZRH229 (ZAIN ID # 2093)

EXISTING GREENFIELD SITE / RIYADH


FINAL EQUIPMENT SHELTER FLOOR PLAN LAYOUT
DRAWN: DESIGNED: SCALE: DATE:

CHECKED CADD: DRAWING NO: REV.

CHECKED QUALITY:
ZRH229-ERI-FP-0002 A
APPROVED:
REV DATE DESCRIPTION
REVISIONS
CONFIDENTIALITY:

5G PHASE-4 PROJECT

P.O. BOX 6121 MAKKAH 11442


SAUDI ARABIA
TEL. (01) 2303111
FAX. (01) 2301777 / 2302777

AZMI ABDUL HADI - LICENSE No. 13 - AL-KHOBAR, KSA

ZRH229 (ZAIN ID # 2093)

EXISTING GREENFIELD SITE / RIYADH


EXISTING & FINAL ACDU SINGLE LINE DIAGRAM

ZRH229-ERI-De-0001 A