Dee au)
Diversion Headworks Questions
CEE ABU Re lila)
Start Complete Exam Preparation
aC Da a eer
eee pected (oa) Mock Tests
ere ars
Download App
Exot
Question 1:
View this Question Online >
The main function of a diversion head work of a canal from a river is:
1. Toremove silt
2. Tocontrol floods
3. To store water
4. To raise water level
5. Toinereasedischarge
.
‘Answer (Detailed Solution Below)
Option 4: To raise water levelcoaching
India’s Super Teachers for all
govt. exams Under One Roof
or
Diversion Headworks Question 1 Detailed Solution
Explanation
Diversion head works like Weir or barrage is con! dacrossa perennial river to raise water
level and to divert the water to canal. ersion head work Flow of water in the
canal iscontrolled by canal head requiatofmt controls the entry of silt into canals and provides
some poundage by creating small pond, However, the most appropriate will be option ‘4’.
India’s #1 Learning Platform CRC ost
Start Complete Exam Preparation
A) Dally Live ood Peace
MasterClasses resin xtc)
| - 4
D> Download App \ .
—____i
Question 2:FSLof a canalat its head with respectto parent ‘CO
1. At the samelevel ot
2. 1S emhigher Noe
3. 15cm ae S
igher
5. 10 cm lower
Answer (Detailed Solution Below)
Option 3: 15 cm lower
Diversion Headworks Question 2 Detailed Solution
Explanation:
Canal Regulators Q
a structure
A canal obtains Its share of water from the pool behind the barrage throu the
canalhead regulator.
Acanal head regulator is located just upstream of the barrage.
FSL (Full supply level) of the canal at its head wit!
em lower and should be above the sill of the
For effective control of the silt entry into xe* s above the head regulator.
je Channel
arent channel is kept 15
Offtake Chanel
Parent Channel
<eRe anc partial
Start Complete Exam Preparation
cree Cte Crees
CCL ke ott
jownload App
Question 3:
View this Question Online >
For design purposes, the sill level of a canalhead regulator is generally kept higher by a
minimum of about 1 to 1.2m, above the
1. crestlevel of under-sluices
2. breast wall
3. bed level of berrage
4. crestlevel of barrage bays
Answer (Detailed’Solution Below)
a 1: crestlevel of under-sluices
Diversion Headworks Question 3 Detailed Solution
Explanation:
Fundamental design parameters of the following hydraulic structures :
+ Canal head regulators
+ Distributary head regulators
+ Crossregulators.
Marainal(oe = |
Guide bank |
Divide wall
Scouring sluices
Head regulator
Canal head regulators
‘ae
+ A canal head regulator which is loc: ME Jof a barrage (or placed appropriately
near areservoir)is provided to hel
(a) Regulate the discharge flowing into the off-taking channel
(b) Control the entry of sediment into the channel
+ Ahead regulator is generally aligned at an angle of 90' to 110’ to the axisof the barrage in
order to minimize the entry of sediment entering into the channel
+ besides preventing backflow and stagnant pools in the under sluicepocket that lies in the
vicinity of the regulator.
+ Steel gates of spansusually in the range of 6 to 8 m, for manual operation, are provided in the
regulator to control the discharge.
+ Larger spanscan be adopted for gates that are operated by electricwinches.
+ To the designed full supply level of the canal, a working head of 1.0 to 1.2 mis added to
obtain the pond level in the under sluice pocket, upstream of the canalhead regulator.
+ To prevent the entry of sediment into the canal, the crest of the head regulator is always
kept higher than the sill level of the under sluices.
+ Wherever a sediment excluder is provided in the under sluiceportion of the barrage, the crest
level of the head regulator is decided considering the design requirements of the sediment
excluder besides the requirements of the waterway of the regulator, and the working head that
is available.Start Complete Exam Preparation
Pea acs Mock Tests
aad Ce hod Crresieuccg Ga ete
Download App
Question 4:
View this Question Online >
Which of the following is NOT a function of a crossegulator?
1. Effectively controls the entire canalirrigation system
2. Helps in heading up water on the upstream
~ Absorbs fluctuationsin various sectionsof the canal
4, Servesas a meter for measuring discharge
Answer (Detailed Solution Below)
Option 4: Servesasa meter for measuring discharge
Diversion Headworks Question 4 Detailed Solution
Explanation:
Canal- regulator:
+ Canal Regulators are required orcaannel to regulate tlsapply of water.
+ For effecting control of flow on the irrigation systemsome structuresare required to be
constructed at the berrage and alsoon the off-taking distributary canalsand these structures
are: 1.Canal Head Regulator 2. Canal CrossRegulator
Canal Cross Regulator:
+ Itis acontrol structure constructed across a canal to regulate the level of the water
upstream of the cross regulator.
+ It is general practiceto provide a crossregulator in the main canal downstream of the off-
taking canal.
+ The functions of cross regulator :
(a) To allow the desired discharge in the off-taking canal that is situated upstream of thecross regulator,
(b) To release water from the canals by operating along with escapes,
(c)To maintain the water surface slopes in appropriate conjunction with the
flow control over falls so the canals may attain their regime slopes and cross sections,
(d) To control the discharge released by one canal into another canal or lake.
Canal Head Regulator:
neat about a reservoir) is provided 10
(a) regulate the discharge flowing into the
+ A canalhead regulator which oi of @ barrage (or placed eppropriately
(b) control the entry of sediment into the canal.
taking canal and
+ Ahead regulator is generally aligned at an angle of 90° to 110° to the axis of the barrage
order to minimize the entry of sediment entering into the channel, besides
preventing backflow and stagnantpools In the under- sluice pocket that lies in the vicinitgt
the regulator.
rake Chane _/f/ /
comake Channel COftake Channet _/f
Si /
Head Reguiator ff / /
\ Bo/
———
rod
Pe eect
ere Oat cet:
Pela mew chime elie)
erresienccag
Ce el Brie
Download App
ices (@ pee eis
Question 5:
View this Question Online >
Water head upstream is increased when the main canalis running with low supplies by
means of
1. bed banks2 ~~"
3), gates
4. sluices
Answer (Detailed Solution Below)
Option 2: crossregulators
Diversion Headworks Question 5 Detailed Solution
Concept:
Cross Regulator:
+ It is provided to control the supplies passing down the parent channel
+ Across regulator is provided on the parent channel at the d/s of the offtake to head up
the parent channel at the channel to draw the required supply.
The function of cross regulators: z
+ Cross regulators eni -ctive regulation of the entire canal system.
+ They help to raise the level in the parent channel is low.
+ They help in closingthe supply to the d/s of the parent channel for the purposes of repairs
and construction works.
+ In conjunction with escapes, theyhelp water to escape from the channels.
+ They facilitate communication since 2 road canbe taken over them with a little extra cost.
+ They help to absorb fluctuations in the various sectionsof the canal systemand hence to
prevent possibilitiesof breaches in the tail reaches.
+ They help to control discharge at an outfall of the canal into another canalor lake.
+ They help to control the water surfaceslope for bringing the canalsto regime slope and
section,
Pd
India’s #1 Learning Platform @ Trusted by 1,06,00,449+ Student
Start Complete Exam Preparationees foie ese
MasterCl resend
Download App
Px tzr
Question 6 View this Question Online >
The most suitable location of canal head work is:
1. Rock stageof theriver.
2. Boulder stageof the river
Bios stage of the river
4, Delta stage of the river
Answer (Detailed Solution Below)
Option 3: Trough stage of the river
Diversion Headworks Question 6 Detailed Solution
Explanation:
Canal head work
+ Any hydraulic structure constructed et the head of the canal to regulate the flow of water is
called canal head work.
Functions
+ Itregulates the supply of water into the canal
+ It controls the entry of the silt.
* It prevents the river flood from entering the canal
Depending upon the stages reaches)of the river, the location of head work is: se
+ Trough stage or alluvial stage
+ Boulder stage
+ Rocky stage
+ Detta stage
|___- Meandering length (M, }Trough stage or alluvial stage
In this stage, the cross-section of the river is made up of alluvial sand and silt. Thebed slope and
velocity are small. |i is Most suitable because
+ The demand for irrigation water is high.
+ Seepage losses are less.
Both rocky and delta stage is not suitable for cenalhead work
India's #1 Learning Platform
ORD cast
Start Complete Exam Preparation
Doeciaprny
ets (Ce ee Cine
Download App
Question 7 \Viewthis Question Online >
Which of the following is not a canal diversion head-work?
1. Fishladder
2. Canal fall
3. Under- sluices
4 z. regulator
Answer (Detailed Solution Below)Option 2: Canal fall
Diversion Headworks Question 7 Detailed Solution
Explanation:
Components of Head Works
Following are the parts/components of headworks
> Weir
+ Under Sluices
+ Canal Head Regulators
+ Fish Ladder.
+ Divide Wall.
+ River Control Works
| Marginal —
Qe !
/
Fish ladder
ary he a
Start Complete Exam Preparation
CCC otc
if Slee one) Tas
ot
co resend xtc r)
Question & View this Question Online >
Which of the following structuresis constructed to separate under sluicesfrom the main
weir?1. Marginal bund
2. Divide wall
3. Head regulator
4. None of the aN
ow (Detailed Solution Below)
0
jption 2: Divide wall
Diversion Headworks Question 8 Detailed Solution
Explanation:
Divide wall:
Thisis much like a pier and is provided between the sets of under sluice or river sluice or spill
bays. It separate under sluices from the main weir. The main functionsof a divide wall:
+ It separatesthe turbulent floodwaters from the pocket in front of the canalhead.
+ It helps in checking parallel flow (to the axisof the barrage) which would be caused by the
formation of deep channels leading from the river to the pocket in front of the sluices.
Head regulator:
Ahead sluicesor canal head regulator (CHR) Is provided at the head of the off-taking canal, and
servesthe following functions:
+ It controls the entry of silt into the canal
+ It regulates the supply of water entering the canal.
+ It prevents river floods from entering the canal. of
; \A @
Components of Diversion headwork are as follows:fe wall
Approach
Fish ladder
RL a Lea CREA as
Start Complete Exam Preparation
yeaa eae waa
Pres
MasteClasses LIB J Question Rank
Download App
Question 9 "View this Question Online >
Silt excluders are constructed while silt ejectors are constructed.
1. on the river bed, on the diversion headworks
2. on the river bed, on the bed of the off taken canal
3. on .d of the off taken canal, on the bed of the river
4. on the bed of the off taken canal, on the river bed
Answer (Detailed Solution Below)
Option 2: on the river bed, on the bed of the off taken canal
Diversion Headworks Question 9 Detailed Solution
Concept:
‘lb Biter Tinie “Phin ceteyaik etit itr ene aie tele alt tee icra sak waiira: Kenbe reduced by constructing certain specialworks which are called silt control Works or silt control
devices. These works may be classifiedinto the following two types:
Silt Excluders:
+ Silt excludersare those works which are constructed on the bed of the river at upstream of
the head regulator. »
+ The clearer water enter
excluder. in this type of
the canal.
head regulator and consequently the silted water enters the silt
the silt is, therefore, removed from the water before it enters
Silt Ejectors:
* Silt ejectors, also called silt extractors, are those devices that extractthe silt from the canal
water after the silted water has travelled a certain distance in the off-take canel.
+ Theseworks are, therefore, constructed on the bed of the canal, end a little distance
downstream from the head regulator.
India’s #1 Learning Platform Cae etter
Start Complete Exam Preparation
ees =) Practice Epes
DOs coery Cresco Exeter)
Download App
Question 10 View this Question Online >
Which of the following is not the part of diversion headworks?
1. Barrage
2. Divide wall
3. Head regulator
Answer (Detailed Solution Below)
Option 4: DistributaryDiversion Headworks Question 10 Detailed Solution
Explanation:
Components of Head Works
Following are the parts/components of headworks
Weir
Under Sluices
Canal Head Regulators
Fish Ladder.
Divide Wall.
River Control Works
ioe - .
Nae i, i
KX | | L
Fish ladder
eS
OPES aL elec aes
Start Complete Exam Pri
Deo rote
Gees Practice Dag
Question Bank EY ho
Question 11 View this Question Online >
Aqueducts are designed to carry of full supply.
1, 10% - 25%
2. 25% - 50%3. 50% - 75%
4. 100%
Answer (Detailed Solution Below)
Option 3: 50% - 75%&
iP RE ABA Rec ial CC RR reo
Start Complete Exam PreparationDownload App
Question 12 View this Question Online >
Which of the following is provided to prevent the river flood from entering the canal and
regulating the supply of water entering the canal?
1. Artificial cut-offs
2. Divide wall
3. Head Siuices
4, FishLadder
Answer (Detailed Solution Below)
Option 3: Head SluiceseRe aL aise CRC cect
Start Complete Exam Preparation
ia ene ond Dar
Ds cieloy researc Ext r
Jownload App
Question 13 View this Question Online >
Minimum Angle between axis of weir and canal head regulator is.
1.0°
2. 90°
3. 60°
4. 120°
Answer (Detailed Solution Below)
Option 2: 90°ee ge hacia aoe ar eon
PS eTameouie)(CM ecu medal L aed)
iG ene Dao
Tera
Download App
Question 14 View this Question Online >
Which of the following work is not performed by canal headwork
1. Tocontrol the silting in canal
2. Toraise the water level of river water
3. To control the flow in the existing canal
4. To generate the electricity power from water
Answer (Detailed Solution Below)
Option 4 : To generate the electricity power from watereee accu) SSS
Start Complete Exam Preparation
Pan oie Praca
toes Ps saree Ga ecoQuestion 15 View this Question Online >
Acanal head work has nothing to do with a:
1. Weir
2. Guide bank
3. Head regulator
4, Safety ladder
Answer (Detailed Solution Below)
Option 4: Safety ladder