Professional Documents
Culture Documents
net/publication/270887453
CITATIONS READS
0 2,411
1 author:
Hussein Elarabi
University of Khartoum
88 PUBLICATIONS 151 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Engineering properties of laterites in Muglad basin, western Kordofan, Sudan View project
All content following this page was uploaded by Hussein Elarabi on 15 January 2015.
TO
LAHMEYER INTERNATIONAL
FOR
FEASIBILITY STUDY
VOLUME I
MAIN REPORT
MARCH 2005
(864)
Table of Contents
(865)
II
(866)
III
List of Tables
Table (1) Mobilized Equipments 18
Table (2) Excavation Route And Duration Of The Test Pits 23
Table (3) The Performed Field Tests 24
Table (4) Location of Test Pits (Leftt Bank) 26
Table (5) Location of Test Pits (Right Bank) 29
Table (6) Soil Profiles and Classification Tests for Left Bank Test Pits 36
Table (7) Soil Profiles and Classification Tests for Right Bank Test Pits 43
Table (8) Locations of Boreholes (Leftt Bank) 51
Table (9) Locations of Boreholes (Right Bank) 52
Table (10) Locations of Lugeon Tests 62
Table (11) Standard Penetration Test Results 66
Table (12) The Performed Laboratory Tests 70
Table (13) Laboratory Permeability Test Results for Left Bank 74
Table (14) Laboratory Permeability Test Results for Right Bank 75
Table (15) UCS and Unit Weight of Samples From Left Bank 77
Table (16) Water Absorption Test Results 89
Table (17) Sodium Sulphate Soundness Test Results 90
Table (18) Dispersivity Test Results (Left Bank) 92
Table (19) Dispersivity Test Results (Right Bank) 93
(867)
IV
List of Figures
Fig. (1) Map of the Sudan 4
Fig. (2) Location of the Project Site 5
Fig. (3) Schematic Arrangement of the Contractor Employees 20
Fig. (4) Lugeon Test Equipments 59
List of Plates
Plate (1) Samples of Topography of the Project Area 7
Plate (2) Sand Dunes 8
Plate (3) Nubian Sandstone Formation 10
Plate (4) Location of Test Points 15
Sample of Photograph of Test Pits on Left and Right Bank
Plate (5) 33
(Remaining of Photos are in the attached (CD)
Plate (6) The DCP Test Equipment 35
Plate (7) Core Samples (rest of photos in the attached (CD) 54
Plate (8) Drilling Process 56
Plate (9) Lugeon Test Equipments 60
Plate (10) In situ Permeability Test (Falling Head Test) 64
(868)
V
Appendix Subject
A Geological Description of Left Bank Test Pits
B Dynamic Cone Penetration Tests of Left Bank
Geological Description of Boreholes and Core Photographs of
C
Left Bank
D Lugeon Test Results of Left Bank
E In-Situ Permeability Test Results (Falling Head Test) of Left Bank
F Sieve Analysis Test Results of Left Bank
G Sieve and Hydrometer Analysis Results of Left Bank
H Compaction Test Results of Left Bank
Consolidated Undrained Triaxial Compression Test Results of Left
I
Bank
J Swelling Pressure Test Results of Left Bank
K Double Hydrometer Test Results of Left Bank
L Pinhole Test Results of Left Bank
Appendix Subject
M Geological Description of Right Bank Test Pits
N Dynamic Cone Penetration Tests of Right Bank
Geological Description of Boreholes and Core Photographs of
O
Right Bank
P Lugeon Test Results of Right Bank
Q In-Situ Permeability Test (Falling Head Test) of Right Bank
R Sieve Analysis Test Results of Right Bank
S Sieve and Hydrometer Analysis Results of Right Bank
T Compaction Test Results of Right Bank
Consolidated Undrained Triaxial Ccompression Test Results of Right
U
Bank
V Swelling Pressure Test Results of Right Bank
W Double Hydrometer Test Results of Right Bank
X Pin hole Test Results of Right Bank
(869)
VI
Pre-feasibility Appendices
Appendix
Geological Description of Test bits in Pre-feasibility study phase
Y
of Left Bank
Geological Description of Test Pits in pre-feasibility study phase
Z
of Right Bank
(870)
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT
1. Introduction
1.1 Preamble
The Ministry of Irrigation and Water Resources, Merowe Dam Project
Implementation Unit (MDPIU) entrusted the German consulting engineering
firm Lahmeyer International GmbH of Bad Vilbel, Germany (LI) with the
engineering services for the Geotechnical Investigations of the Feasibility
Study of Merowe Irrigation Project extending over the Nile valley from the
Merowe dam down to the third Cataract.
The Building and Road Research Institute (BRRI), University of Khartoum has
been contracted by Lahmeyer to undertake field and laboratory geotechnical
work for the proposed canals of Merowe Irrigation Project, Sudan. These
geotechnical investigations are needed to perform the feasibility study of the
mentioned project.
Fieldworks were started on 15th August 2004 and the laboratory testing
followed after a 2 week time. The reports for both left and right bank canal
were completed in March 2005.
(871)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 2
Numerous soil and rock material samples have been collected from boreholes
and test pits according to the required specifications and under the supervision
of the consultant engineers representatives on site. Such samples were intended
to be used later for running certain specified number of laboratory testing.
(872)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 3
The project site is located on both banks of the River Nile from approximately
Merowe on the left bank and Kareima on the right bank downstream to the
town of Kerma as shown in Fig. (2).
(873)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 6
The Merowe Irrigation Project located at the area between the dam site till
Dongola and Argo area parallel to the River Nile at both sides, left and right
bank. There is an asphaltic road on the left bank from Khartoum through El
Multaga and from Merowe town to Merowe dam site. Also till Dongola most
of the road is not asphaltic. On the right bank, there is no asphaltic road except
the distance between Karima and the dam site.
The climate of the area is hot and dry during summer and cold and dry during
winter. Closer to the River Nile banks the area is covered by extensive plants
and vegetations and far from the River it is characterized by scattered desert
trees.
Topographically the area generally varies from tough mountain ridges near the
dam site to undulated to flat in the other areas, Plate (1). Near the dam site the
area is covered by basement ridges, while the other areas are covered by low
scattered hills, sand cover, and dunes, Plate (2). The types of deposits are the
sand dunes and ripple marks. The sand dunes cover a big area of the right bank
such as Argi, Gadar and Hau. The sand was transported by wind forming thick
cover of aeolian deposits of recent age. There are two types of sand dunes:
barchans, and longitudinal sand dunes. These two types of sand dunes and
ripple marks can indicate directly the direction of deposition and source of
sand. The most significant drainage system features are the River Nile, Wadi
Howar, Wadi El Muggadam, and Wadi El Malik. Seleim area is a flat area
(874)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 9
The basement formations that cover the dam site area, are part of the Bayuda
basement rocks which are of Proterozoic age. It comprises granitic gneiss
intruded by younger granite Palaezoic age) and intruded by many felsites dyke
and pegmatitic veins. The granitic gneiss is formed mainly of quartz and potash
feldspar as felsic or light minerals, biotite, muscovite micas and iron oxide ores
as dark minerals. The rock generally is foliated.The pegmatite is formed of
very big crystals of quartz and pink potash feldspar whereas the felsite is
formed mainly of fine-grained felsic minerals (possibly quartz and potash
feldspar). The younger granite is generally suitable as a material source for
aggregates. The granitic gneiss was affected by the metamorphic processes and
weathering and therefore is not suitable for aggregate materials. The basement
rocks from the field investigations are hard in the unweathered state, so
blasting and explosives is important for excavation.
The Nubian formations (Plate (3)) include all the consolidated sedimentary
rocks covering most of the area as low scattered outcrops. These formations
include mudstone, sandstone and conglomerates (gravels beds). They are part
of the Nubian formation of Sudan which is of Cretaceous age. This is clear
from the plant fossils found in the formations. The sandstones mainly are
argillaceous fine-coarse grained. All the formations in this area are
characterized by the presence of groundwater, especially the formations near
the River Nile since it represents the main feeding agent for the groundwater.
(875)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 11
The Nubian formations in this area are bedded and laminated and often easy for
excavation. The Tertiary volcanic, represent part of Bayuda Tertiary
Pleistocene volcanic which are of basic composition (dolerite). The dolerite is
formed mainly of dark minerals (Fe-Mg-minerals) possibly pyroxenes. It is
characterized by three sets of closer jointing systems as a result of the cooling
of the magma. Dykes and sills characterize this formation. Generally these
dykes and sills can be used as source of aggregates such as in quarry areas
LQ2, LQ3, RQ3 and north west of Dongola.
The Recent or Quaternary sediments represent the surface of the residual and
transported soils. The residual soils were formed due to the complete
weathering of the pre-existing rock (basement or Nubian formation). The
transported soils were formed due to the transportation and deposition of the
soil by the different weathering agents. Such as Aeolian soil, alluvial soil and
the Lacustrine soil. The most flat area in this project is Seleim area which is
mainly clayey silty soil. It is the most suitable area for agriculture and it is one
of the significant target areas for irrigation in this project.
(876)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 12
Work-front 2: Right Bank Canal from Merowe Dam to km 216 and Khawi
Main Canal from km 0 to km 153 and ancillary structures.
(877)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 13
BS: Shallow Boreholes for the investigation of potential quarry areas for
rock material, maximum theoretical depth 10 m, average depth 6m. No
in-situ testing.
(878)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 14
PB: Test pits, depths down to 4m or refusal for investigation of sand and
gravel borrow areas.
DCP tests were performed either in test pits or at other positions.
The boreholes BD and BL and the test pits P are located on the canal
alignment. The boreholes BS and the test pits PB may be located up to a few
kilometers off the canal alignment.
The positions of boreholes, test pits and DPL are given to BRRI by the
Consultant during the progress of the works, either by setting appropriate
coordinates or by direct marking in the field.
After completion of each drill hole from which soil samples and rock cores
have been taken, and its plugging, the boreholes are filled and indicated by a
concrete plate with the borehole index engraved and with a projected vertical
bar of at least 1m in height.
In general, the drilling depth is related to the invert elevation of the canals or
the foundation elevation of structures and the Consultant specified the final
drilling depth in accordance with the local conditions for each borehole.
The cores were appropriately placed in core boxes and photographed, and the
core boxes transported to the site core box storage area at the Employer’s
premises at Merowe.
(879)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 15
(880)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 16
A lot of preparation works have been done in Khartoum by BRRI staff before
mobilization. This work consisted of collection of relevant information and
suggestion of the best procedure to be applied for carrying out the field-testing.
The previous experience gained from the previous investigation carried out by
BRRI in the pre-feasibility phase of this project was of great assistance in
making a good plan for the implementation of works.
The fieldworks were assigned to four different teams all under the management
of a site manager and a senior geologist. Each team was headed by a geologist.
Three of these teams were combined in one camp with three drilling machines
to perform the drilling work in soil and coring in rock and were called the
drilling group. Each team consisted of a geologist, technical engineer, drilling
operator and five skilled drilling labours. The fourth team or test pits group was
responsible for executing and controlling the excavation and sampling test pits.
The field geological description was carried out also by the latter team which
was consisting of two geologists, two technical engineers and two laboratory
assistants. In addition, thirty-five labours were employed by the team from
local inhabitants at the site for the manual excavation of test pits.
Three trucks and twelve 4-wheel drive vehicles were used at site for the
transportation and movement of the various work groups. Three drilling rigs
mounted on truck were used for drilling boreholes. Two ZY-tanker trucks were
(881)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 17
used for transporting water for drilling and human use. Table (1) lists the
equipments mobilized by BRRI to the site for carrying out the work program.
(882)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 18
6. Execution of Fieldwork
The field works were undertaken in accordance with the terms of reference
outlined in contract documents and instructions of the Geotechnical
Consultancy Engineer of Lahmeyer International.
The parties participated in accomplishment of the field activities from the side
of the Employer Lahmeyer International were:
Mr. Evert J.P. de Nooy, - Project Manager
Dr. Yannick Scheid - Chief Geotechnical Specialist
Mr. Reijer van der Vlugt, - Chief Engineering Geologist
Dr. A. Yassin, - Geologist
A. Emaduddin , - Geologist
(883)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 19
(884)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 21
The total depths of drilling in all boreholes on the left bank were 53 m in soil,
154 m in gneiss and 192 m in weathered sandstones and other cemented
formations.
The total depths of drilling in all boreholes on the right bank were 64 m in soil,
66 m in gneiss and 316 m in weathered sandstones and other cemented
formations.
All test pits on both left and right banks were excavated to maximum depth of
4.0 m or wherever manual excavation becomes impossible.
In the following sections the field works executed by the two main work
groups, i.e. boreholes group and test pit group on both left and right bank
canals are presented.
(885)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 22
The fly camp technique was adopted for execution of these field activities.
Table (2) shows the excavation route and duration of the test pits. The field
tests performed are presented in Table (3).
(886)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 23
(887)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 25
During excavation every layer was placed separately for the purpose of
description and sampling. The field description was done to report the depth
of the test pit, the profile of the soil, topography, surface cover and
elevation of the point. The soil profile describes the consistency of the soil,
moisture content, colour, structure, soil type and soil origin. In case of
existence of rock the profile describes the hardness, weathering, colour,
discontinuity spacing, rock name and straight graphic horizon. Disturbed
soil samples were collected at each change of soil strata or at one-meter
depth intervals where soil conditions did not change. These samples were
kept in plastic bags, labeled and transported to BRRI geotechnical
laboratory for testing.
Dynamic cone penetration (DCP) tests were carried out at the surface or at
the bottom of each pit as described in the following sections. Also, the
natural moisture content was determined during the execution of the
excavation.
(888)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 32
stratum close to the ground surface in many locations may give sufficient
information for design purposes.
The same observations mentioned above in the test pits on left bank
were also noted. The geological description of the excavated test pits on
the right bank are presented in Appendix (M). Also natural moisture
content tests were carried out as specified by the consultant engineer.
All photos of these test pits were presented in the attached CD. Plate (5)
shows a sample of one photograph of a test pit on the right bank.
(889)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 34
The maximum penetration depth for the equipment used in this project is
1m. The test was performed on ground surface and at the bottom of a few
test pits and whenever the soil conditions allowed. Since this equipment has
many advantages including simplicity, portability, and cheapness besides
giving continuous rough record of soil consistency over the depth tested,
many tests have been carried out for this project. The collected data from
field and the curves of penetration values against the number of blows for
this test are presented in Appendix (B) for the left bank canal and Appendix
(N) for the right bank canal. Plate (6) shows the equipment of the DCP test,
used in this investigation.
The natural moisture content tests were carried out on representative soil
samples specified by the consultant engineer. These tests were performed
inside a small mobile laboratory at the site. The results of the tests carried
out for the left bank canal are shown in Table (6), and those carried out for
the right bank canal are presented in Table (7).
(890)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 50
The fly camp technique was used for execution of the field activities. The
drilling teams camped on the left bank at Merowe, Tangasi, Wadi Arees,
Elghaba and on the right bank at Selaim, Gadar, Ezzuma and Karima
respectively.
(891)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 53
In general, the drilling depth is related to the invert elevation of the canals
or the foundation elevation of structures and the Consultant specified the
final drilling depth in accordance with the local conditions for each
borehole.
For the rocks (Gneiss, Granite, Dolerite and Sandstone) core drilling
technique was used with core pits diamond and diamond-carbide with
diameter 47.6 mm. Casing of 3 inches diameter was used at the upper depth
of the borehole (0-3 mm). The core drilling technique involved the use of
water pumps for cooling and clearing the cuttings. No bentonite slurry was
used during work. The core samples were extracted and labelled in the core
boxes, then were prepared for this purpose. Field description was done to
report the depth of samples, geological description (colour, hardness,
weathering, discontinuity spacing, grain size, rock name, straight graphic
horizon etc.), percentage of core recovery, percentage of RQD, drilling rate
and water loss. The soil samples were kept in plastic bags, described by the
same system. Core boxes were photographed and then transported to the
core box storage site at the Employer’s premises at Merowe. A sample of
core box photos is shown in Plate (7). All other Core boxes photos were
copied in the CD attached with this report. The N-value of SPT tests were
reported besides any other field and drilling observations.
After finishing drilling of the boreholes, the falling head permeability tests
were carried out in case the rock formations were highly weathered and the
walls were not hard enough to support the Lugeon Packers. In the hard
formations where the walls were hard enough to support the Lugeon
Packers, the Lugeon tests were carried out. These two tests were carried out
to estimate the field permeability for the rock formations.
(892)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 55
The Lugeon test apparatus used was comprised of single and double
packers, steady flow pump, flowmeter, pressure gauge water level indicator
and other accessories.
After the completion of drilling of the borehole and the field tests, the
drilling machine was shifted to another borehole to continue with the same
drilling procedure. All boreholes, after completion of drilling, testing and
measurement were covered with a concrete block with steel rod placed on
top of each borehole. The borehole name and number was clearly marked
on the concrete blocks.
8.3 Boreholes
The boreholes in this Project were drilled using the rotary drilling technique
(Plate 8): in most of the boreholes rotary core drilling was used to recover
representative samples from rock strata. A core barrel fitted with a 55 mm
diamond tipped or impregnated drill crown was used.
Drilling water was pumped through the core barrel to cool the drill bit and
flush the cuttings to the surface. The core barrel used can recover a 1.5 m
length of core at a time. Once the core barrel was full the drill stem with
core barrel was withdrawn from the hole and the core sample was recovered
and stored in core boxes. Core boxes were marked with the depths drilled
so that a visual inspection of the core box indicates the degree of core
recovery relative to the total depth drilled. The core boxes were transported
later to Merowe for assigning the laboratory testing program to be carried
out at BRRI laboratory.
(893)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 57
(894)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 58
(895)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 61
length of soil or rock to be tested. The single packer method was used to
carryout the test at the bottom of the hole.
The test consists of pumping water into the isolated zone of the borehole at
three different pressures, in the following typical sequence:
0.5-1-2-1-0.5 bar for depth less than 10 m below ground) and
1-2-3-2-1 bar for depth of 10 to 20 m below ground .
(896)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 63
through the interstitial voids. Water movement through soil and rock
significantly affects the ability to control water during construction.
There are many different types of field tests that can be used to estimate the
permeability of the in situ soil. Such field tests are used because the
coefficient of permeability determined from laboratory tests on small soil
specimens may not be representative of the overall field conditions.
Another common method of determining the field coefficient of
permeability is through the measurements of the change in water levels in
open standpipes.
The apparatus used for carrying out the in-situ permeability test is shown in
Plate (10). This apparatus was designed to give a general idea of the
seepage characteristics of the material at the bottom of the tested boreholes.
The following assumptions were adopted for this test:
• The soil is not subject to disturbance, segregation, swelling and
consolidation.
• There is no sedimentation or leakage during testing.
• No air or gas are entrapped in soil or pipe used for testing.
• The hydraulic losses in pipes or filter are negligible.
The results of the field permeability for some of the boreholes on the left
bank are presented in Appendix (E) and those on the right bank are
presented in Appendix (Q)
(897)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 65
recorded. The blow count for the first 150 mm increment is discarded and
the sum of the blow counts for the remaining 300 mm penetration is known
as the SPT ‘N’ value. The SPT tests were carried in this project as requested
by the Consultant Engineer in all boreholes performed at proposed
structures locations. Thirty-four SPT tests were performed on left bank and
Forty-eight on the right bank, Table (11).
The N values with their locations for left bank canal are presented in
Appendix (C) while those for the right bank canal are presented in
Appendix (O).
(898)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 69
9. Laboratory Testing
Laboratory testing was conducted to evaluate the geotechnical properties of the
soils encountered during the excavation of the test pits.
As the moisture content increases a clayey or silty soil will become softer and
stickier until it cannot retain its shape when it is described as being in a liquid
state. If the moisture content is increased further then there is less and less
interaction between the soil particles and a slurry, and a suspension is formed.
If the moisture content is decreased the soil becomes stiffer until there is
insufficient moisture to particle cohesiveness when the soil becomes friable and
cracks or breaks up easily if remoulded. This state is described as semi-plastic
solid or semi-solid. If the moisture content is decreased further there is a stage
when the physico-chemical forces between the soil particles will not permit
them to move any closer together and the soil is then described as a solid.
The limits between the different states of the soil are originated by the Swedish
soil scientist, Albert Atterberg (1911). The Atterberg Limits are the so-called
consistency limits. Determining Atterberg Limits is very useful for the
classification of cohesive soils. The concept is based on the fact that the
consistency depends largely on its water content. The Atterberg Limits
(899)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 71
comprise the liquid limit, the plastic limit and the shrinkage limit. These define
the boundaries between four stages of a consistency. The Atterberg Limits tests
were carried out on 113 samples from the left bank and 159 from the right
bank. The results are shown in Table (6) for the left bank and in Table (7) for
the right bank.
(900)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 72
The grain size curves for 110 and 136 samples are plotted in Appendix (G) and
(S) for the left and right bank respectively. For sieve analysis, the percent finer
was plotted for a corresponding sieve size opening. For hydrometer analysis,
the percent finer was plotted for a corresponding soil grain size.
Proctor test is used to determine the dry density moisture content relationship.
The test is described in BS 1377:1990, Part 4. The results of these tests carried
out on 94 and 102 soil samples are presented in Appendix (H) for left bank and
(T) for right bank.
(901)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 73
Several factors may influence the reliability of the permeability test in the
laboratory. Air bubbles may be trapped in the test specimen, or air may come
out of solution from the water. The degree of saturation could thus be less than
100%, which would affect the test result significantly. Migration of fines in
testing sands and silts also affects the measured values. Temperature variation,
especially in tests of long duration, may affect the measurements.
(902)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 76
presented in Appendix (I) and two taken from the right bank are presented in
Appendix (U).
The results of the swelling pressure of 23 samples from left bank are presented
in Appendix (J) and 45 samples from right bank are presented in Appendix (V).
(903)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 88
Dispersive soils are those in which the clay content has a high percentage of
sodium. This clay fraction readily breaks down to form a suspension in water.
The results of a double hydrometer on 61 soil samples collected from left bank
are presented in Appendix (K) and for 67 samples collected from right bank are
presented in Appendix (W).
(904)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 91
The chemical tests were performed on fourteen samples from the left bank and
thirty one from the right bank. The results of these samples are presented in
Table (18) and Table (19) respectively.
(905)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 94
Laboratory tests were performed on representative soil samples taken from the
test pits and boreholes to obtain the important data needed for the feasibility
study of the project.
(906)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 95
(907)
Geotechnical Division - Building and Road Research Institute – University of Khartoum
GEOTECHNICAL INVESTIGATION REPORT FOR
MEROWE IRRIGATION PROJECT 96
References
[1] Barnes, G. : Soil Mechanics: Principles and Practice, Palgrave, New York.
[2] Holtz, R.D.and Kavacs, W.D. : An Introduction to Geotechnical
Engineering, Prentice-Hall, New Tersey, 1981.
[3] Budhu, M. : Soil Mechanics and Foundations.
[4] Day, R. W., Soil Testing Manual, Mc Graw- Hill, New York, 2001.
[5] Weltman , A. J. and Head J.M. : Site Investigation Manual, CIRIA,
London, 1981.
[6] Byrne G. et.al. : A Guide to Practical Geotechnical Engineering, FRANKI,
Southern Africa, 1995.
[7] Whiteman A.J. : The Geology of the Sudan Republic, William Clowers and
Sons Limited, London 1971.
[8] Graig, R.F: Soil Mechanics, Fifth Edition, (HAPMAN & Hall), London, 1993.
(908)
Geotechnical Division - Building and Road Research Institute – University of Khartoum