Track slab

North Strathfield tunnel


- Project info
- Include picture here • Due for construction in June 14
• Australia, Sydney
• John Holland
• NSW Transport Authority

- Technical solution
• Dramix 5D 65/60BG
• 35kg/m3
• 400mm thick track slab
• 12mm bars at 120mm c/c, top
• Dramix 5D used for strength and crack
control

- Benefits
• Conventional design used 20 - 24mm bars at
150mm c/c, top and bottom
• Dramix 5D solution reduced this steel by
more than 50pc, and in most cases only
required one layer

Project Reference