Professional Documents
Culture Documents
Check that the gas pressure is sufficient and record the value (if applicable). MPA
Check that the HV ring main switchgear is de-energised before testing. (Cables disconnected.)
Conduct functional tests of electrical equipment and parts of the installation; verify the settings, circuitry
and programming; verify the operation and configuration by measurement or testing of protective,
monitoring, measuring and control devices.
Verify that the fire ratings for the building and enclosures are correct and that the emergency exits are
operational.
Verify the minimum clearances between the live parts and earth.
This test must be carried out before any cables are Red - white > 5,000 MΩ/5 GΩ Ω
connected.
White - blue > 5,000 MΩ/5 GΩ Ω
Open all earthing switches and close all load carrying
switches. Blue - red > 5,000 MΩ/5 GΩ Ω
Conduct an insulation resistance test of the busbar
with a 5 kV insulation resistance tester for 1 minute Red - earth > 5,000 MΩ/5 GΩ Ω
and record the value.
The value must be greater than 5,000 MΩ/5 GΩ. White - earth > 5,000 MΩ/5 GΩ Ω
3. Continuity Test
The purpose of this test is to verify the connection between the same phases.
Expected
Test Connection Resistance
Values
Connect an insulation resistance tester set at 1
Red - red 0 MΩ Ω
kV and test between all bushings of the same
phase to prove continuity. White - white 0 MΩ Ω Pass/Fail
Blue - blue 0 MΩ Ω
Close all earthing switches and open all load Red - earth 0 MΩ Ω
carrying switches. Connect an insulation Pass/Fail
White - earth 0 MΩ Ω
resistance tester between all bushings of the
same phase and earth bar to prove continuity. Blue - earth 0 MΩ Ω
9. Handover of Responsibility
I hereby certify that item 8 has been completed with satisfactory results and transfer control to the network
operating authority.
Commissioned by NAC
Signature Date & Time
1. Ensure the work area is left tidy with no hazards to the public.
2. Hand over responsibility to the operating authority.
3. Return this form to the project file as a record of the commissioning/handover certificate.
4. After the on-site project officer signs off on the DCF, a scanned copy of the DCF must be attached to the
relevant project documentation.