You are on page 1of 19

Tunnelling and Underground Space Technology 25 (2010) 139–157

Contents lists available at ScienceDirect

Tunnelling and Underground Space Technology


journal homepage: www.elsevier.com/locate/tust

Tunnel boring machines under squeezing conditions


M. Ramoni *, G. Anagnostou
ETH Zurich, Switzerland

a r t i c l e i n f o a b s t r a c t

Article history: Squeezing ground represents a challenging operating environment as it may slow down or obstruct TBM
Received 5 May 2009 operation. Due to the geometrical constraints of the equipment, relatively small convergences of one or
Received in revised form 19 October 2009 two decimetres may lead to considerable difficulties in the machine area (sticking of the cutter head, jam-
Accepted 22 October 2009
ming of the shield) or in the back-up area (e.g., jamming of the back-up equipment, inadmissible conver-
Available online 2 December 2009
gences of the bored profile, damage to the tunnel support). Depending on the number and the length of
the critical stretches, squeezing conditions may even call into question the feasibility of a TBM drive. This
Keywords:
paper sets out firstly to give an overview of the specific problems of TBM tunnelling under squeezing con-
Tunnel boring machine
Mechanized tunnelling
ditions; secondly to analyse the factors governing TBM performance by means of a structured examina-
Squeezing ground tion of the multiple interfaces and interactions between ground, tunnelling equipment and support; and
TBM jamming thirdly to provide a critical review of the technical options existing or proposed for coping with squeezing
Shield ground in mechanized tunnelling.
Tunnel support Ó 2009 Elsevier Ltd. All rights reserved.
Yielding support
Segmental lining

1. Introduction are not particularly risky for the economic success of a TBM drive
provided that adequate countermeasures are planned in advance
In recent years, the need for new infrastructure to handle the (Kovári, 1986a).
intercity transportation of people and goods has steadily increased. TBM performance can be affected by geological conditions in a
The construction of such facilities often requires the excavation of great variety of ways (Barla and Pelizza, 2000). For example, bore-
long, deep tunnels such as the two base tunnels of the Alptransit ability problems in hard rock, steering difficulties or severe vibra-
Project in Switzerland (Kovári, 1995), the Brenner Base Tunnel be- tion of the cutter head due to mixed face or blocky rock conditions,
tween Austria and Italy (Bergmeister, 2007), the Lyon-Turin Tunnel major water inflows, cave-ins ahead of the tunnel face or unstable
between France and Italy (Nasri and Fauvel, 2005) or the Gibraltar excavation walls in highly fractured or weathered rock as well as
Strait Tunnel between Spain and Morocco (Pliego, 2005). In many crossing fault zones may represent difficult tunnelling conditions.
cases the cost of such projects can be reduced to a justifiable level Squeezing ground conditions may also slow down or obstruct
only by utilizing tunnel boring machines (TBMs), because they al- TBM operation (ITA, 2003) and sometimes even call into question
low significant savings in construction time and costs. the feasibility of a TBM drive. In fact, there have occasionally been
Due to alignment constraints and the uncertainties of geological some very negative experiences (including complete loss of the
exploration (which may be large, particularly for long, deep tun- TBM) in the past and this has often lead to TBM drives in squeezing
nels), it is not always possible to find a route that will avoid the ground being classified as generally too risky and therefore not fea-
problem of excavating in difficult geological zones with a sufficient sible. However, between the borderline cases of a heavily squeez-
degree of certainty (Robbins, 1992). The extent and frequency of ing ground and a non-problematic competent rock, a wide range of
the difficulties encountered can be decisive in terms of economical conditions exist which neither exclude a priori mechanized tunnel-
viability or even in terms of the technical feasibility of a TBM drive. ling nor allow it without careful consideration. These cases call for
In some cases of very great potential damage, a single event can a well-founded, thorough investigation of the risks, the technical
cast the entire project into doubt. Minor setbacks may also become feasibility and the cost of TBM application. So it is not surprising
relevant if occurring frequently. The length and the number of crit- that the question of TBM applicability in squeezing conditions
ical stretches are very important in this respect. Short tunnel has kept engineers busy for more than 30 years. First remarks
stretches with unfavourable but well-known geological conditions can be found already in Prader (1972), while more detailed concep-
tual considerations have been provided later by Lombardi (1981)
* Corresponding author. and Robbins (1982). Other related works are, e.g., those of Kovári
E-mail address: marco.ramoni@igt.baug.ethz.ch (M. Ramoni). (1986a,b), Amberg (1992), Gehring (1996), McCusker (1996) and

0886-7798/$ - see front matter Ó 2009 Elsevier Ltd. All rights reserved.
doi:10.1016/j.tust.2009.10.003
140 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

Nomenclature

dl lining thickness S1, S2 tunnel support (type, quantity, parameters, distance be-
ds shield thickness hind face) in the machine area and in the back-up area,
D boring diameter respectively
e extrusion rate of the core t1 operational standstill time
E Young’s modulus of the ground t2 standstill time due to jamming of the TBM
Ek entity of N2 chart (the subscript k refers to the entity t3 standstill time due to other problems
numbering) T torque
El Young’s modulus of the lining Tf required torque for overcoming friction
Es Young’s modulus of the shield Tg torque that can be reacted by the grippers
fc uniaxial compressive strength of the ground or of the Ti installed torque
lining Tr rolling resistance of the cutter head
Fb boring thrust force vg gross advance rate
Fb,max maximum possible boring thrust force vn net advance rate
Ff thrust force needed for overcoming friction {x–y} interactions between the entities Ex and Ey of a N2 chart
Fg thrust force that can be reacted by the grippers DD overboring (facility, amount of the increase of the bor-
Fi installed thrust force ing diameter D)
G ground c unit weight of the ground
H depth of cover u internal friction angle of the ground
L shield length m Poisson’s ratio of the ground
n cutter head rotational speed l shield skin friction coefficient
nmax maximum possible cutter head rotational speed (TBM r ground pressure acting upon the tunnel support
design) rmax maximum possible ground pressure acting upon the
nmax  maximum possible cutter head rotational speed (opera- tunnel support (bearing capacity)
tional conditions) rTBM ground pressure acting upon the TBM (cutter head or
N number of physical and functional entities of a N2 chart shield)
p penetration sTBM shear stress acting upon the TBM (cutter head or shield)
PA, PB problems in the back-up area (zone A and zone B, w dilatancy angle of the ground
respectively) # number

Schubert (2000). As can be seen from recent publications (Downing back-up area (e.g., jamming of the back-up equipment, inadmissi-
et al., 2007; John and Schneider, 2007), the topic is particularly rel- ble convergences of the bored profile, damage to the tunnel sup-
evant today due to the increased economic importance of mecha- port). In addition to the difficulties that are directly caused by
nized tunnelling associated with the demand for long deep tunnels. squeezing behaviour, adverse events such as clogging of the cutter
The present paper presents a qualitative discussion of the com- head, insufficient bracing of the grippers or instabilities of the face
plex interactions between ground, tunnelling equipment and sup- or the tunnel wall may also occur when boring through weak
port based upon both tunnelling experience (Section 2) and ground. Often it is difficult or even impossible to distinguish the
theoretical considerations. Reference will be made to the peculiar- different phenomena from each other. For example, when driving
ities of the different TBM types and emphasis will be placed on the through poor quality ground it may remain uncertain if the ground
interfaces between the three essential system components: pressure acting upon the TBM is due to squeezing or ravelling
ground, tunnelling equipment and support (Section 3). Over the behaviour. Furthermore, in several cases a feedback between the
last decade, considerable research and development efforts have different problems may be observed (Kovári, 1986a).
been made with the goal of widening the range of applicability Concerning the magnitude of the potentially problematic defor-
for TBMs in squeezing ground either by improving established mations, a marked difference exists between conventional and
TBM types (i.e., gripper, single or double shielded TBM) or by mechanized tunnelling. Due to the geometrical constraints im-
developing new construction methods involving alternative ma- posed by the equipment, even convergences as small as one or
chine designs or deformable lining systems. Reference to these two decimetres may lead to difficulties in the machine or in the
works will be made in Section 4, which – starting from the basic back-up area of a TBM drive Kovári (1986b). It should be noted that
interactions discussed in Section 3 – deals with possible measures relatively moderate deformations, which may be problematic for a
for coping with large rock deformations or high ground pressures TBM (but could be easily dealt with by conventional tunnelling),
in mechanized tunnelling. are in no way limited to the typical squeezing formations of weak
rocks such as phyllites, schists, serpentinites and claystones. Expe-
2. Practical experience and specific problems rience in some stretches of the Gotthard Base Tunnel has shown
that hard but highly fractured rocks may also exhibit relevant
A comprehensive literature search on case histories involving deformations and challenge TBM tunnelling, particularly if
TBMs under squeezing conditions has been carried out in order encountered at great depths.
to identify the specific problems. An extended presentation of Tunnelling experience also indicates that interruptions of the
the results of this search as well as all related references can be TBM drive may be unfavourable in squeezing ground, i.e., that
found in Ramoni and Anagnostou (2009). the ‘‘time” factor may play an important role. In several cases,
According to tunnelling experience, squeezing behaviour may the TBM did not become jammed until there was a slowdown or
become problematic at different distances behind the tunnel face. standstill in the TBM drive, which suggests that maintaining a high
Therefore, the specific potential hazards concern both the machine gross advance rate and reducing standstill times may have a
area (sticking of the cutter head, jamming of the shield) and the positive effect. For example, in the Tunnel 38 of the Yindaruqin
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 141

Irrigation Project (China, double shielded TBM, D = 5.54 m), the by precast segments) forms part of the thrusting system. There
TBM was trapped during a maintenance stop, while in the Ya- have been negative experiences in cases where a proper backfilling
cambú – Quibor Tunnel (Venezuela, gripper TBM, D = 4.80 m) and of the segmental lining was not achieved. For example, the double
in the Nuovo Canale Val Viola (Italy, double shielded TBM, shielded TBM (D = 2.91 m) that excavated a part of the Stillwater
D = 3.60 m) TBM jamming occurred during holiday stops. Tunnel (USA) probably became trapped in squeezing ground be-
Standstills are unfavourable also with respect to cutter head cause of the impossibility of fully utilizing its installed thrust force.
operation. Depending on the rheological behaviour of the ground, Firstly, it was not possible to drive the double shielded TBM in the
high ground pressures acting upon the cutter head or an extremely ‘‘gripper mode” and secondly, the improperly backfilled segmental
high extrusion rate of the core may develop. In this respect, the Gil- lining was not able to withstand the combined loading of ground
gel Gibe II Tunnel (Ethiopia, double shielded TBM, D = 6.98 m) may pressure and thrust force generated in the ‘‘auxiliary mode”. In this
be mentioned. In this project, in one case the core extruded with a case there was a further difficulty in relation to the telescopic part
rate of 40–60 mm/h and pushed the TBM back (with a lateral dis- of the shield, which had a smaller diameter than the front and the
placement of more than 40 cm). As a consequence, the shield and rear shield, favouring the accumulation of loose material in this
the segmental lining were damaged. However, if the TBM is boring, area and thus leading to an increase in the friction that had to be
the excavation speed is normally high enough to avoid problems overcome when moving the double shield. Similar problems also
(Barla, 2001; Gehring, 1996; Hoek, 2001). The development of arose with gripper bracing, the backfilling of the segmental lining
the ground pressure upon the cutter head is, as a rule, not fast en- and the telescopic part of the shield during the excavation of the
ough to lead to an immobilization of the TBM. However, this may Los Rosales Tunnel (Colombia, double shielded TBM, D = 3.54 m).
occur during a standstill (depending on the duration of the stand- Possible problems in the back-up area include inadmissible con-
still and the deformation rate of the ground), if the installed thrust vergences of the bored profile or damage to the tunnel support.
force and torque are not sufficiently high to restart TBM operation. Such problems are basically the same as in conventional tunnelling,
In the case of a gripper TBM, the ground plays an additional impor- the main differences being that in conventional tunnelling (i) there
tant role, as it must provide a sufficient reaction force to the grip- is the option of excavating a considerably larger profile in the crit-
pers. This was also a problem, e.g., in the Yacambú – Quibor Tunnel ical stretches (in order to accommodate the deformations) and (ii)
(the TBMs were also immobilized several times because of insuffi- there is also more flexibility concerning the location of support
cient bracing of the grippers in very weak squeezing ground). installation (stabilization measures can be taken practically wher-
Maintaining a high advance rate is of course a major goal for ever and whenever required). In TBM tunnelling, the space avail-
any TBM drive. When tunnelling through squeezing ground it able for ground deformations and tunnel support is largely pre-
may also help to prevent the machine becoming trapped. Never- determined by the fixed geometry of the excavated cross-section.
theless, high gross advance rates should not be seen as a panacea The possibility of enlarging the boring diameter locally is very lim-
for coping with squeezing. First of all, tunnelling experience shows ited (up to 30 cm, if at all possible, cf. Section 4.2.2), while the de-
that the ground deformations may develop very rapidly and very sign of the back-up equipment fixes the locations of the support
close to the working face. In such a situation, the achieved gross installation and limits the scope for intervention in the back-up
advance rate would play a secondary role (the TBM would become area. Besides the typical problems mentioned above, jamming of
jammed even if operated at the highest feasible speed). Further- the back-up equipment is an additional hazard scenario to be con-
more, standstills of TBM operation cannot be completely avoided sidered, particularly for gripper TBMs. This has been experienced,
(Gehring, 1996; Lombardi, 1981). Besides adverse ground condi- for example, during the excavation of the Strada Section of the Tav-
tions, unpredictable stops due to technical problems (e.g., electric anasa – Ilanz Tunnel (Switzerland, gripper TBM, D = 5.20 m), in the
power stoppages, mechanical breakdowns of the TBM, problems Northern Section of the Vereina Tunnel (Switzerland, gripper-TBM,
in the back-up system) have to be considered. For example, during D = 7.64 m) and, recently, in the Faido Section of the Gotthard Base
the excavation of the Evinos – Mornos Tunnel (Greece) the cutter Tunnel (Switzerland, gripper-TBM, D = 9.43 m).
head of one of the gripper TBMs (D = 4.20 m) became jammed dur-
ing an excavation standstill which was caused by an interruption
3. Ground–equipment–support interactions
of the electric power supply. The need to carry out regular mainte-
nance work is also an important factor. This causes halts in excava-
Identifying the relevant interfaces between the main system
tion but it is at the same time important for reducing the risk of
components and understanding their interactions is essential to
mechanical breakdown. Finally, it has also to be considered that
an assessment of the critical situations, which might affect the per-
a certain time is needed for support installation (a practically con-
formance, or even the feasibility of a TBM drive. The following sec-
tinuous excavation is possible only with double shielded TBMs
tions shall discuss the interactions between ground, tunnelling
advancing in gripper mode).
equipment and support, taking into account the peculiarities of
In the case of time-dependent ground behaviour (which is char-
existing TBM types with respect to thrusting systems, tunnel sup-
acteristic for squeezing formations), the need for interruptions to
port, the presence or absence of a shield (‘‘gripper TBMs” are often
allow support installation introduces important feedback effects
also equipped with a canopy or a short cutter head shield with a
and conflicting requirements. The maintenance of a sufficiently
length of about a half boring diameter) and the achievable gross
high gross advance rate is advantageous but difficult to achieve,
advance rate, which is an influencing factor as well. The discussion
especially in the case of poor quality ground. For example, if the
starts with the case of gripper TBMs (Section 3.1) because their
tunnel is excavated with a gripper TBM, it becomes necessary to in-
greater flexibility concerning tunnel support increases system
stall a higher quantity of support and this lengthens standstill
complexity. The case of single or double shielded TBMs thrusting
times. In extreme cases, the TBM becomes trapped and has to be
against a segmental lining will be discussed later in Section 3.2.
freed with special measures that mostly require hand-mining. On
the other hand, installing a lighter support for the sake of a higher
advance rate may lead to inadmissible convergences in the back- 3.1. Gripper TBM
up area. These aspects will be discussed in more detail in
Section 3.1.3. 3.1.1. Overview of interactions
When tunnelling by a single shielded TBM (or a double shielded The large number of interfaces between ground, tunnelling
TBM in the so-called ‘‘auxiliary mode”), the tunnel support (lining equipment and support in combination with the possibility of con-
142 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

Fig. 1. Principle and mapping rules of N2 diagramming technique.

flicting requirements and feedback effects introduces a high level between the desired resolution of the partial processes and the
of complexity, which necessitates an efficient mapping of the sys- space available on the paper. As can be seen in Fig. 2, the chosen
tem and of its interfaces in order to identify and analyze the rele- entities include the physical components of the system (such as
vant interactions. The so-called ‘‘N2 chart” offers the possibility of a the ground or the TBM) as well as operational parameters (such
systematic approach and a neat analysis. This method was intro- as the cutter head rotational speed), the results of the boring pro-
duced by Lano (1990) and is a well-known diagramming technique cess (such as the net advance rate) or events (such as problems in
in system engineering practice. the back-up area or standstills due to TBM jamming). The interac-
Following the description given by NASA (2007), an N2 chart is tions depicted have been classified as ‘‘relevant” based upon prac-
an N-by-N square matrix (also called an ‘‘interaction matrix”) con- tical experience (cf. Section 2) and theoretical factors. In spite of
taining the N physical or functional entities of a system (also called their limitations, the latter are indispensable as there are hardly
‘‘system elements”, ‘‘system components” or ‘‘functions”) on the any systematic field investigations available.
main diagonal, and the interfaces between them in the remaining The main inputs of the N2 chart of Fig. 2 are the ground (denoted
off-diagonal cells, while a blank off-diagonal cell means that there by G), the TBM itself, the back-up equipment and the tunnel sup-
is no interaction between the respective system elements. As illus- port (denoted by the entities S1 and S2 that will be explained later),
trated by the schematic example of Fig. 1, the interactions have to while the gross advance rate (vg) can be seen as the main output
be read directionally between the elements, i.e., first horizontally since it best represents TBM performance (construction cost could
in the row and then clockwise in the column. For example, the fact also have been considered as an output entity, of course). The gross
that the cell at the intersection of row x with column y is non- advance rate depends on the net advance rate (vn) achieved during
empty indicates that entity Ex has an effect on entity Ey (the num- the boring process and on the duration of the standstills (denoted
bers x–y within the cell represent the parameters involved as well by t1, t2 and t3 depending on their cause). In this respect a distinc-
as the ‘‘direction” of the interaction). The non-empty cells in row y tion is made here between the regular operational standstills
show all of the entities that are influenced by entity Ey (i.e., the needed for the installation of the tunnel support or for the execu-
‘‘outputs” of Ey), while the non-empty cells in column x show tion of maintenance works, etc. (t1); standstills due to TBM jam-
which entities influence entity Ex (i.e., the ‘‘inputs” to Ex). The use- ming, where the TBM has to be freed and possibly repaired (t2);
fulness of this representation technique is illustrated by the inter- and standstills due to other problems such as damage to the tunnel
action loop {2–x–y–2} which indicates a feedback effect. support or mechanical breakdown (t3).
In order to condense more information into one N2 chart, the The dense population of the first two rows of the N2 chart
diagrammatic language has been enhanced adding two mapping (Fig. 2) reflects the paramount importance and the manifold effect
rules that exploit the shape and color of the cells: rhombuses of the ground and of the TBM (cutter head, shield, thrusting sys-
(e.g., cell y–N in Fig. 1) indicate that an interaction exists only un- tem). These entities summarize a large number of properties and
der certain conditions (for example, rock deformations may lead to features, which become relevant only for one or two interactions.
TBM jamming only if a threshold value is exceeded), while circles Resolving the entities ‘‘ground” and ‘‘TBM” into their individual
(e.g., cell x–y in Fig. 1) denote unconditional interactions (for properties and features (strength, stiffness, permeability, ground
example, standstills always reduce the gross advance rate). As for heterogeneity, shield length, installed thrust force, etc.) is basically
the colors, green1 is used for interactions of the type ‘‘an increase possible, but would increase the chart size beyond the limit that
of Ex leads to an increase of Ey”, red for interactions of the type ‘‘an can be managed on paper. The alternative possibility of including
increase of Ex leads to a decrease of Ey” and black for interactions the lower-level entities, but grouping them into blocks – creating
where the effect of Ex on Ey may be either positive or negative. thus a hierarchy of N2 charts, that considers the major subsystems
Fig. 2 shows the N2 chart elaborated for the subject of the pres- with appropriate resolution (cf. Lano, 1990) – was abandoned for
ent paper. The number of physical and functional entities repre- reasons of complexity and because it would not add anything sub-
sents the result of a trade-off, which has had to be made stantial. Instead, remarks concerning some of the relevant param-
eters under the headings ‘‘ground” or ‘‘TBM” are given in Table 1,
1
which supplements the N2 chart with comments, as well as in
For interpretation of color in Figs. 1 and 2, the reader is referred to the web
version of this article. the remainder of this section, which addresses questions of boring,
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 143

thrusting and support, including their interactions. For the sake of tance of the cutter head should be lower than during the boring pro-
simplicity, pairs of numbers within curly brackets will be used for cess, as no (or only a low) thrust force is applied to the cutter head
making reference to Fig. 2 and denoting the interfaces of the when restarting its rotation {9–12}. Under squeezing conditions,
respective entities (e.g., {9–15} denotes the effect of entity 9 on en- however, the ground at the tunnel face may deform axially and
tity 15). around the cutters. The core extrusion thus leads to an increase of
the depth of cut and, therefore, of the rolling resistance of the cutter
3.1.2. Boring and thrusting head {1–12}. Furthermore, since the cutter head hinders ground
The jamming of the TBM represents a major hazard as it may deformations, an axial pressure develops upon it (Fig. 3). It is obvi-
lead to serious damage, necessitating lengthy standstills for free- ous that in this case the demand both for thrust force and for torque
ing or repairing the machine (standstill t2, Fig. 2). Besides being increases. The increased thrust demand is not so problematic, be-
important from a practical point of view, this potential problem cause a thrust force reserve is available at this stage since the
is also theoretically very interesting and has attracted several re- TBM is not engaged in boring. The torque demand may, neverthe-
search efforts over recent years – recent works are, e.g., those by less, be critical to the resumption of operations.
Graziani et al. (2007), Ramoni and Anagnostou (2007a,b) and Ster- If the ground pressure acting upon the TBM reaches its bearing
pi and Gioda (2007). The present paper limits itself to a qualita- capacity, damage will occur and repair work will be needed {2–18,
tive discussion of the basic interactions and mechanisms 10–18}. This is particularly true if the TBM is already immobilized
underlying (i) the inability to resume TBM operation after a and the ground pressure increases further. During a standstill, the
standstill (which may be necessary, e.g., for support installation, possibility of the TBM being pushed back by the axial ground pres-
re-gripping, etc.) and (ii) the immobilization of a TBM during sure acting on the cutter head has also to be considered. Finally,
ongoing excavation. when restarting TBM operation (or during ongoing excavation)
over-stressing due to combined loading (thrust force, torque and
ground pressure) is also possible.
3.1.2.1. Restart after standstill. If the ground behaviour is time-
dependent, which is very common for squeezing conditions, a ra-
3.1.2.2. Immobilization during ongoing excavation. TBM immobiliza-
dial ground pressure may develop upon the machine during a
tion during the boring process can be seen as equivalent to the bor-
standstill. In order to resume TBM operation, i.e., to move the
derline case of a zero net advance rate vn {16–18} (Fig. 2). Usually
TBM forwards and to rotate the cutter head, the thrusting system
the net advance rate vn is expressed as the product of the achieved
must be able to cope with the frictional forces acting upon the cut-
penetration p {15–16} with the chosen cutter head rotational
ter head and the shield (Fig. 3).
speed n {7–16}. In the case of intensively squeezing ground, how-
In order to move the TBM forwards, both the installed thrust
ever, one should bear in mind that before the machine moves for-
force Fi and the bearing capacity of the thrusting system Fg must
wards the extrusion of the core has first to be compensated and,
be higher than the frictional resistance Ff (static friction):
consequently, the net advance rate
minðF i ; F g Þ > F f : ð1Þ v n ¼ maxð0; pn  eÞ; ð3Þ
The frictional resistance Ff increases with the radial pressure where e denotes the extrusion rate of the core {11–16}. Under nor-
acting upon the machine {10–18} (which may be high in the case mal conditions (characterized by the usual values for penetration
of squeezing ground) and with the size of the loaded area (i.e., with and rotational speed), the effect of the core extrusion is small, but
the diameter and length of the cutter head and of the shield {2– it may become relevant in the case of a low penetration rate p or
18}). Furthermore, it depends on the type of the ground {1–18} a low rotational speed n. In extreme cases, the cutter head pene-
and on the surface roughness of the cutter head and of the shield trates and rotates without moving forward (the penetration is
{2–18} as they are relevant with respect to the skin friction coeffi- used-up just for removing the axially deforming ground at the
cient. The installed thrust force Fi is a matter of TBM design {2–18}, working face). The circumstances leading to reduced values of pen-
while the bearing capacity Fg of the thrusting system depends both etration or rotational speed are outlined below.
on the TBM design (the number, dimensions and surface roughness The penetration rate depends on the rock mass characteristics
of the grippers and the installed gripper force) {2–18} and on the (strength, discontinuities, etc.) {1–15}, on the cutter head design
stiffness and the strength of the ground {1–18}. If the ground is (form and stiffness, cutter spacing, size, etc.) {2–15} and on the
weak and offers only insufficient resistance to the grippers, the boring thrust force Fb {9–15}, i.e., on the force with which the cut-
effectively available thrust force will be lower than the installed ter head is pushed against the working face. The boring thrust force
one. represents an operational parameter which can be chosen within
In order to restart the rotation of the cutter head, the effectively certain limits that are imposed by the installed thrust force Fi {2–
available torque must be high enough to overcome the frictional 9}, by the bearing capacity Fg of the thrusting system {1–9, 2–9}
resistance Tf at the circumference of the cutter head (Fig. 3) as well and by the frictional resistance of the cutter head and the shield
as its rolling resistance Tr: Ff (in this case sliding instead of static friction has to be considered)
minðT i ; T g Þ > T f þ T r ; ð2Þ {2–9, 10–9}. The maximum possible boring thrust force
F b;max ¼ maxð0; minðF i ; F g Þ  F f Þ: ð4Þ
where Ti denotes the installed breakout torque (Fig. 4) and Tg is the
maximum torque that can be applied when taking into account the The analysis of TBM operational data and of field measure-
limited bearing capacity of the ground next to the grippers. Con- ments, as done, e.g., from Farrokh and Rostami (2009) for the
cerning the installed torque {2–18} and the bearing capacity of Ghomroud Tunnel (Iran, double shielded TBM, D = 4.50 m), con-
the thrusting system {1–18, 2–18} the factors are similar to those firmed that an increase of the frictional resistance Ff can lead to a
for the thrust force. The frictional resistance depends in this case limitation of the net cutter load and, consequently, of the penetra-
on the geometry of the cutter head and on the ground pressure act- tion p {9–15}. Of course, a further reduction of the boring thrust
ing upon it {2–18, 10–18} as well as on the type of ground {1–18} force may also be necessary for reasons not related to squeezing
and on the characteristics of the cutter head surface {2–18}, while (for example, in order to limit vibrations that could damage the
the rolling resistance increases with the depth of cut at the moment equipment or in the case of blocky ground or mixed face
when the cutter head rotation restarts. Normally the rolling resis- conditions).
144 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

Fig. 2. N2 chart for a gripper TBM drive through squeezing ground (see Fig. 1 for the mapping rules).

Squeezing behaviour – particularly if encountered in combina- interrelated and determined by the TBM design {2–7} (Fig. 4).
tion with gripper bracing problems – may limit the boring thrust Additionally, the effectively available torque may be smaller than
force to such an extent that penetration is no longer possible {9– the installed one as the torque Tg that can be reacted by the grip-
15}. Special problems may arise if squeezing weak ground alter- pers may be low in poor quality ground {1–7, 2–7}. In general,
nates with hard rock. More specifically, when the TBM is exiting the following condition must be satisfied in order to rotate the cut-
a weak zone and entering hard rock (Fig. 5), a so-called ‘‘under- ter head with a speed n:
thrust situation” may occur (McCusker, 1996), which is character-
minðT i ðnÞ; T g Þ > T f þ T r : ð5Þ
ized by the combination of several adverse factors: (i) low bearing
capacity of the ground in the gripper area {1–9}; (ii) the need to Under given operational conditions it may be necessary to reduce
overcome high frictional resistance {2–9, 10–9}; and (iii) high the cutter head rotational speed to a value n < nmax  (Fig. 4) in order
resistance of the hard rock to the boring process {9–15}. for sufficient torque to be available for overcoming the frictional
The cutter head rotational speed is another operational param- and rolling resistances. Sticking of the cutter head will occur if
eter directly affecting the net advance rate {7–16} (Eq. (3)) and is the torque is insufficient in spite of the reduction of the rotational
chosen on the basis of several limiting factors such as the diameter speed of the cutter head up to n = 0 ({1–7}, {2–7}, {10–7}, {12–7},
and the robustness of the cutter head {2–7}, the capacity of the {7–16–18}; please note, that the notation {7–6–18} summarizes
mucking system and the torque demand Tr + Tf, where Tr denotes the sequence of the interactions {7–16} and {16–18}).
the rolling resistance of the cutter head {12–7} and Tf is the torque Penetration p and rotational speed n determine the net advance
needed to overcome the frictional resistance (sliding friction) rate vn (Eq. (3)). It should be noted, however, that the latter is not
caused by the ground pressure acting axially and radially upon only the main output of the boring process but may also be an
the cutter head {2–7, 10–7}. The rolling resistance of the cutter important influencing factor. In the case of pronounced time-
head depends on the ground {1–12} as well as on the characteris- dependent ground behaviour, a slower advance leads to a higher
tics of the cutters (e.g., number, spacing, arrangement, shape, loading of the machine {16–10}, and this reduces both the achiev-
diameter, wear) {2–12}. In weak ground, the torque demand may able penetration {10–9–16} and the maximum possible rotational
be very high and reduce the achievable rotational speed consider- speed of the cutter head {10–7}, thereby causing a further reduc-
ably, because rotational speed n and installed torque Ti(n) are tion in the net advance rate {7–16, 15–16}, i.e., the system re-
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 145

Table 1
Comments on the interactions shown in Fig. 2.

Entities Remarks Entities Remarks Entities Remarks

1–5 The tunnel support to be installed in the machine area 2–10 Furthermore, the conicity of the cutter head and of the 2–13 The design of the back-up equipment (more
1–6 {1–5} or in the back-up area {1–6} is chosen on the shield as well as the overcut (i.e., the difference 2–14 specifically, its sensitivity to ground deformations)
basis of the ground conditions (although work safety between the cutter head diameter and the shield 3–13 may also be decisive for other problems such as
must always be ensured). diameter) play an important role as regards steering 3–14 damage to pipes or heave of the tracks.
the TBM and allowing ground deformations without 8–13
loading the TBM. During a standstill, the ground 8–14
pressure acting axially upon the cutter head can be
reduced, if the TBM design allows it to be pulled back.
In order to overcome the friction caused by the ground
pressure acting upon the cutter head and the shield, a
sufficient pull force must have been installed and the
ground must offer sufficient resistance to the grippers.
2–5 The location of the first tunnel support installation 5–10 The tunnel support immediately behind the shield 5–13 Besides stiffness and bearing capacity of the tunnel
depends on the length of the cutter head and of the 5–12 facilitates arch action in the longitudinal direction, 5–14 support, its thickness is also relevant, as it reduces the
shield. Furthermore, the design of the equipment thus leading to lower loading of the shield {5–10} 6–14 space available to ground deformations.
installed on the TBM is relevant with respect to the (Section 4.6, Fig. 8). During a standstill, the ground
type of tunnel support that can be installed and to the pressure acting axially upon the cutter head as well as
place available for the installation work. its rolling resistance when its rotation has to be
restarted can be reduced by pulling it back. This
presupposes that the tunnel support in the machine
area does not impede the movement of the TBM
backwards {5–10, 5–12}.
16–5 The stiffness and the bearing capacity of the tunnel 8–10 A larger overboring allows more ground deformation 16–13 In the case of a pronounced time-dependent ground
17–5 support may be time-dependent (shotcrete, grouted to take place and thus leads to a lower loading of the 17–13 behaviour, a reduction in the net advance rate or a
18–5 bolts). During a standstill, they increase with the TBM. 18–13 standstill will lead to higher ground deformations or
19–5 elapsed time {17–5, 18–5, 19–5, 17–6, 18–6, 19–6}. 19–13 higher ground pressures at a given distance behind
16–6 During ongoing excavation, the more rapid the TBM 16–14 the tunnel face.
17–6 advance, the lower will be the stiffness and the 17–14
18–6 bearing capacity of the tunnel support at a given 18–14
19–6 distance from the tunnel face {16–5, 16–6}. 19–14
3–6 The location of the second tunnel support installation, 16–10 In the case of pronounced time-dependent ground 1–15 The relevant influencing factors are the cutter head
the type of tunnel support and the space available for 17–10 behaviour, an increase in the net advance rate leads to 2–15 design (e.g., its form as well as number, spacing,
support installation all depend on the design of the 18–10 a reduction of the ground pressure acting upon the shape, diameter and wear of the cutters) and the
back-up equipment. 19–10 TBM {16–10} and of the extrusion rate of the core {16– characteristics of the rock mass (intact rock and
16–11 11}. During a standstill, ground pressure increases discontinuities).
with time {17–10, 19–10}. If the TBM is already
jammed, the ground pressure acting upon it may
increase further {18–10}. Furthermore, as shown by
numerical investigations (Ramoni and Anagnostou,
2007b), the conditions prevailing at the beginning of a
standstill, depend on the ‘‘history” of the TBM advance
up to the time of the standstill (i.e., on the achieved
gross advance rate).
1–7 See Section 3.1.2 and Eq. (3). 2–11 The size of the face (boring diameter) represents a 9–15 See Section 3.1.2.
2–7 ‘‘span” and influences therefore core extrusion.
10–7
12–7
8–7 During overboring, the cutter head rotational speed 9–11 During the boring process, the boring thrust force 7–16 See Eq. (3).
may have to be reduced (Section 4.2.2). acting upon the face reduces core extrusion. 11–16
15–16
1–8 The choice of the overboring facility to be applied and 1–12 See Section 3.1.2. 1–17 The ground conditions are relevant with respect to
the feasible increase in the boring diameter in 2–12 cutter wear (e.g., abrasivity of the rock) and more
particular will depend on the ground conditions 10–12 generally to the required maintenance work (as, e.g.,
(Section 4.2.2). in the case of cutter head clogging). Difficult ground
conditions (e.g., major water inflows) may also slow
down the installation of the tunnel support.
2–8 Overboring is only possible if this option has been 9–12 The rolling force of each cutter increases with 2–17 The complexity of the TBM influences the frequency
catered for in the design of the cutter head and of the increasing normal cutter force (the boring thrust force and duration of maintenance work.
shield (Section 4.2.2). acting upon a single cutter), because of the deeper
cuts and of the higher rolling friction.
1–9 See Section 3.1.2 and Eq. (4). 11–12 A faster core extrusion leads to a greater depth of cut. 8–17 Depending on the type of overboring equipment, the
2–9 This leads to an increase in the rolling force of each commencement of overboring operations may require
10–9 cutter and, therefore, in the rolling resistance of the a standstill (Section 4.2.2).
cutter head.
8–9 During overboring, the boring thrust force may have 2–13 Large deformations may impede passage of the back- 1–18 See Section 3.1.2 and Eqs. (1) and (2).
to be reduced (Section 4.2.2). 2–14 up equipment. The magnitude of problematic 2–18
3–13 deformations depends on the dimensions of the bored 10–18
3–14 profile (and, therefore, on the cutter head diameter 12–18
8–13 and on the amount of overboring) as well as on the
8–14 design of the back-up equipment (the more compact,
the better).
1–10 The ground pressure acting upon the TBM {1–10} and 16–18 If during ongoing excavation the net advance rate
1–11 the extrusion rate of the core during the boring becomes equal to zero, the TBM is jammed and has to
process {1–11} depend on the strength, stiffness and be freed.
permeability of the ground as well as on the initial
stress and the initial hydraulic head (Ramoni and
Anagnostou, 2007a). Depending on the strength and
stiffness of the ground, the reaction forces provided by
the grippers may be insufficient for pulling back the
cutter head during a standstill in order to reduce the
ground pressure acting on it axially {1–10}.
2–10 Firstly, the dimensions (diameter, length) of the cutter 1–19 The frequency of standstills associated with
head and the shield represent a ‘‘span” and therefore 2–19 mechanical breakdowns depends on the ground
influence the amount of ground pressure acting upon 3–19 conditions (e.g., damage to the cutters or to the
the TBM. The ground pressure also depends on the 8–19 conveyor belt in blocky ground), on the robustness of
stiffness of the different TBM components. The ground 17–19 the TBM (including the overboring equipment) and
pressure acting upon the shield may be reduced, if the the back-up equipment as well as on the maintenance
shield is shrinkable (Section 4.3). work carried out on a regular basis.
16–20 By definition.
17–20
18–20
19–20
146 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

Interventions outside the two sectors mentioned above are, as a


rule, not possible. According to Schneider et al. (2007), particularly
critical in this respect is the zone between the first and the second
tunnel support installation points (zone A in Fig. 6). In order to re-
duce the risk of problems in this area (e.g., jamming of the back-up
equipment, inadmissible convergences of the bored profile, dam-
age to the tunnel support) the installation of a higher quantity of
tunnel support may be needed in the machine area, and this, as
said before, will affect general TBM performance.
For these reasons, the N2 chart (Fig. 2) was refined in order to
Fig. 3. Loads acting on the TBM at restart (the shear and normal stresses at the face take into account the specifics of the two locations for support
apply only in the case of a significant core extrusion).
installation. The two entities S1 and S2 denote the tunnel support
applied in the TBM area and in the back-up area, respectively
(Fig. 6), and summarize all the relevant features of the support:
the type (steel meshes, rock bolts, steel sets or shotcrete), the
quantity (e.g., number of rock bolts per linear metre), the parame-
ters (thickness, strength and stiffness) as well as the distance of the
support installation point from the working face. (With respect to
the resolution of these two entities, the same remarks apply as the
ones made in Section 3.1.1 for the entities ‘‘ground” and ‘‘TBM”.)
Due to the impossibility of stabilizing interventions in given
sectors of the back-up area, the two entities PA and PB have been
introduced in order to summarize the problems that may occur
in these zones (zones A and B, respectively, Fig. 6). Similar prob-
lems may also occur, of course, behind the back-up area, i.e., after
the passage of the tunnelling equipment. For example, in one of the
drives of the Yacambú – Quibor Tunnel (Venezuela, gripper TBM,
D = 4.80 m) major heave of the tunnel floor was observed starting
Fig. 4. Relationship between cutter head rotational speed n and torque T. 50–100 m behind the TBM. Such cases have not been included in
Fig. 2 although such situations may also have an impact on TBM
operation (for example, major heave or twisting of the tracks as
well as the execution of repair works may impair rail operations
and, thus, the supply of construction materials or the mucking).
The selection of the type, quantity and location of support appli-
cation represents an important operational decision for a gripper
TBM drive. As long as tunnel stability and working safety are not
endangered, a trade-off between excavation progress and the
quantity of support in the machine area is thoroughly conceivable.
Deciding to apply as little as possible tunnel support in the ma-
chine area (in order to proceed more rapidly {5–17–20}) results,
as a rule, in a lower support stiffness and bearing capacity and this
may lead to problems in zone A (Fig. 6), which may also reduce the
gross advance rate {5–13–19–20}. Decision-making has to take
into account the potential consequences of problems in the back-
up area. A jamming of the equipment leads anyway to a standstill
in TBM operation, while repair works after the passage of the
Fig. 5. Gripper TBM leaving squeezing weak ground and entering hard rock. equipment may often be carried out without slowing down the
TBM drive very much.
A standstill may lead to an additional and longer standstill. Dur-
sponse to the given ‘‘perturbation” is amplified. This so-called ‘‘po- ing support installation, for example, the ground pressure acting
sitive feedback” is more pronounced where there is a high extru- upon the machine will increase {17–10} and, if the duration of
sion rate of the core {16–11–16 or 16–11–12–7–16}. the standstill t1 is long or the development of the ground pressure
fast, the available thrust force or torque (Eqs. (1) and (2)) may be-
3.1.3. Tunnel support come so low that an excavation restart is no longer possible {1–18,
The application of tunnel support usually takes place at two 2–18, 10–18} with the consequence that costly, time-consuming
locations: in the machine area and later in the back-up area at a and sometimes also dangerous work is needed in order to free
distance of 30–60 m behind the tunnel face (Maidl et al., 2001). the TBM (t2). Problems in the above-mentioned zones A and B
The locations of the support installation are determined by the de- may also cause a TBM standstill, during which the TBM may be-
sign of the tunnelling equipment. In the back-up area it is generally come trapped {e.g., 14–19–10–18}.
possible to install the tunnel support without slowing down the
rate of TBM progress. Support application in the machine area,
however, interferes considerably with TBM operation because, as 3.2. Single and double shielded TBMs
a rule, it necessitates a halt of the machine. Furthermore, the sup-
port in the machine area may influence the ground pressure acting A similar N2 chart to the one shown in Fig. 2 could also be drawn
upon the shield (cf. Section 4.6) or may limit the possibility of for the case of single shielded TBMs. For the sake of economy, how-
retracting the cutter head if necessary (cf. Section 4.2). ever, only the main differences between the two machine types
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 147

Fig. 6. Layout of a gripper TBM.

will be discussed here. These differences include the TBM length, gle shields and necessitate a particularly careful and robust design
the thrusting system, the tunnel support and the advance rate. in order to reduce maintenance times or breakdown times.
Single shielded TBMs are longer than gripper machines. As the In weak ground, bracing by the grippers may become impossi-
area exposed to the squeezing pressure is larger, a higher frictional ble. In this case, the machine operates in so-called ‘‘auxiliary
resistance has to be overcome and, consequently, all other param- mode” jacking against the segmental lining with the consequence
eters being equal, the risk of shield jamming is higher (cf. Sec- that it is no longer possible to install the segments simultaneously
tion 3.1.2). The disadvantage of a longer shield is, nevertheless, with the boring (unless a hexagonal segmental lining is applied).
not of absolute significance because single shielded TBMs usually Depending on the machine design, unstable ground may also
have a higher installed thrust force than gripper TBMs. impair the extension and closure of the telescopic joint, thus neces-
Instead of being thrusted via grippers, single shielded TBMs are sitating machine operation in single shield mode. In both cases
jacked against segmental linings. The shield as well as the segmen- (auxiliary mode and single shield mode) the same remarks apply
tal lining have to be designed of course for the combined action of as for the single shielded TBM and the potential advantages of dou-
maximum jacking forces and ground pressure, in order to avoid ble shielded TBMs mentioned above are lost.
over-stressing or inadmissible ovalization. The structural design
of the segmental lining plays an important role, as its bearing 4. Countermeasures
capacity limits the thrust force and torque that can be applied. This
effect can be represented in the N2 chart of Fig. 2 by adding three 4.1. Introduction
interactions ({5–7, 5–9, 5–18}). Although the effect of the ground
on the available thrust force and torque is not as important as in The basic interactions discussed in the last section suggest not
the case of gripper TBMs, in this regard the interactions {1–7, 1–
only how a given parameter is involved in the performance of
9, 1–18} do not disappear completely because the quality of the the entire system, but also where it is possible to intervene, i.e.,
annulus grouting depends also on the ground and an improper to apply measures in order to influence system behaviour. Section 4
backfilling of the segments may reduce the capacity of the segmen- will review possible countermeasures to deal with the problems
tal lining to handle the jacking loads. associated with squeezing. As in the last section, reference will
As described in Section 3.1.3, the type, quantity and installation be made to the interactions of Fig. 2, reporting the corresponding
points of tunnel support represent important operational parame- numbers within curled brackets.
ters for a gripper TBM drive. For shielded TBMs, however, these Over the years, technological improvements in various compo-
parameters are pre-determined (a segmental lining of given thick- nents of the TBMs have extended their range of applicability. The
ness is installed in the rear part of the shield). Therefore, the N2 next sections aim to evaluate not only the well-established meth-
chart can be simplified by eliminating the differentiations made ods but also alternative lining and machine concepts, which have
with respect to the tunnel support (S1 and S2) and to the locations been proposed specifically for coping with squeezing ground. The
of problems in the back-up area (PA and PB). Furthermore, due to order of this discussion reflects the location of the system compo-
pre-fabrication, the stiffness and the strength of the tunnel support nents and, therefore, of the possible intervention points along the
do not change over time and, therefore, do not depend on the gross tunnel axis: the discussion starts with the TBM (cutter head, shield,
advance rate (i.e., the interactions {16–5, 17–5, 18–5, 19–5, 16–6,
thrusting system), continues with the back-up equipment and fin-
17–6, 18–6, 19–6} do not exist). ishes with the tunnel support. Before doing so, however, some
Single shielded TBMs offer the advantage of a higher advance
higher-level aspects, such as alignment, construction method,
rate in poor quality ground (Pelizza and Peila, 2005), although operational measures and pre-treatment of the ground will be
feedback effects are possible for these machines as well. For exam-
briefly addressed below.
ple, high water inflows or unstable tunnel walls may make lining The technical feasibility and the cost of a given measure (or
installation or annulus grouting difficult and, therefore, may slow
package of measures) for dealing with the problems associated
down the advance rate. with squeezing depend on the number and the length of the tunnel
Double shielded TBMs operating in ‘‘gripper mode” install the
stretches affected. If the geometry and the behaviour of critical
lining simultaneously with the boring process and, all other geological zones are well-known, one would try first to reduce
parameters being equal, therefore achieve a higher performance
the length of the affected tunnel stretches by selecting another
than single shielded machines. In the case of time-dependent alignment in the planning phase. Such a route optimization pre-
ground behaviour, a higher advance rate is also advantageous with
supposes knowledge of the geology with a degree of resolution
respect to the amount of shield skin friction to be overcome. Com- that may be difficult to achieve particularly for long deep tunnels.
parative studies should, nevertheless, take account of the fact that
Furthermore, it may lead to an unacceptably long tunnel or it may
double shielded TBMs are in general longer than single shielded be impossible due to project constraints such as the location of the
TBMs. Potential differences may exist, furthermore, concerning
portals, access galleries or shafts, the minimum curve radiuses or
machine availability as double shields are more complex than sin- the longitudinal gradients.
148 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

The conventional excavation of a critical section may lead to a operation) but necessitates in nearly all cases the construction of
reduction of the project schedule risks if it can be done in advance. an intermediate access tunnel or a pilot tunnel, which may also
However, this is only possible if the critical zone is well-known be technically demanding, costly and time-consuming. The pre-
(position and length) and can be accessed via an auxiliary tunnel treatment of the ground from the TBM itself does not require aux-
or a shaft. Switching to conventional excavation during a TBM iliary structures, but slows down the TBM drive considerably. The
drive is, as a rule, very difficult. Nevertheless, it represents an applicability of grouting or drainage depends strongly on the
indispensable measure if the TBM is trapped and has to be freed. ground characteristics. Squeezing rocks are unfavourable in this re-
As a rule, this requires hand-mining over the shield or the con- spect as they often have a high fraction of fines and, therefore, a
struction of a by-pass tunnel – demanding operations, particularly low permeability. In addition, it has to be borne in mind that the
for small boring diameters due to the very limited space available. cutter head and the shield, as well as the limited space available
Special measures have to be planned in advance, in order to reduce for the drilling equipment, impose geometric constraints on the
standstill time as much as possible. The potential delays and addi- layout of the boreholes. Pore-pressure relief by advance drainage
tional costs also have to be analyzed before construction and taken is a highly effective measure for reducing deformations (Anagnos-
into account in the construction schedule and in the contractual tou, 2009) but investigations have to be performed in order to
regulations. This is particularly true in the case of a long drive determine whether the technically feasible spacing and length of
through predominately competent rock, where the possibility of the boreholes are sufficient to achieve the necessary consolidation
the TBM jamming in individual short fault zones may even be re- within an acceptable time period (Floria et al., 2008). In this re-
garded as an acceptable risk. spect, the heterogeneity of the ground permeability has also to
A larger boring diameter offers more space for ground deforma- be considered.
tions, thus reducing the risk of a violation of the minimum clear- Finally yet importantly, in addition to the technological and lo-
ance profile and, when combined with a yielding support (cf. gistic aspects, the importance of the experience of the crew (the
Section 4.6.2), will lead to lower ground pressures, thus reducing human factor) should not be overlooked. This general truth is par-
the risk of support over-stressing as well {2–13, 2–14}. The choice ticularly relevant for dealing with adverse geotechnical conditions
of a larger boring diameter also reduces the risk of shield jamming such as squeezing ground.
– this will be the case, however, only if it is combined with a larger
overcut, i.e., with a larger gap between the tunnel wall and the
4.2. Cutter head
extrados of the shield {2–10}. Local enlargements of the boring
diameter are often very problematic (cf. Section 4.2.2), but select-
The sticking of the cutter head during a standstill may be
ing a larger boring diameter for the entire tunnel may be a viable
avoided by rotating it at regular time intervals. This should be re-
option particularly if squeezing conditions are expected to persist
garded as an operational measure, which must be applied during
over a big percentage of the route. The financial viability of such
longer standstills such as, e.g., holiday stops. In order to facilitate
a solution should be assessed case by case, since it will result in
unlocking, the cutter head should be rotatable in both directions
an unnecessarily large boring diameter in the tunnel stretches
{2–12} (Gütter, 2007).
crossing competent rock (Amberg, 1992).
Another measure for avoiding sticking of the cutter head where
As mentioned in Sections 2 and 3, tunnelling practice as well as
there is a major extrusion of ground at the face is to pull back the
theoretical considerations indicate that maintaining a high overall
cutter head or the TBM. For gripper TBMs this presupposes that the
advance rate may help with the problem of the TBM jamming due
applied support does not impede a movement of the machine
to squeezing ground. Operational measures and an appropriate
backwards {5–10, 5–12}. Single or double shielded TBMs have to
construction site organisation are important for keeping the fre-
be designed so that the cutter head can be moved independently
quency and the duration of standstills low and thus the overall ad-
from the shield. Of course, a movement of the cutter head back-
vance rate high {4–17, 4–18, 4–19}. For example, if an identified
wards is possible only if the friction caused by the radial ground
critical zone has to be crossed, thorough maintenance work should
pressure can be overcome, if the machine possesses a sufficient
be carried out in advance in order to reduce the risk of mechanical
pull force and if the ground is able to provide a sufficient reaction
breakdowns {17–19} and the necessary logistical precautions
force to the grippers {1–10, 2–10, 1–12, 2–12, 10–12, 10–18}. Fur-
should be taken to allow operations within the critical zone to be
thermore, during a standstill the cutter head may support the tun-
as continuous as possible {4–17}. Such operational measures have
nel face. A careful evaluation of the face conditions is important, as
been applied systematically, e.g., during the construction of the
moving back the cutter head may cause instability of the face (Bar-
Wienerwald Tunnel (Austria, single shielded TBM, D = 10.67 m) in
la and Pelizza, 2000).
order to reduce the risks in known fault zones. Holiday periods
The cutter head must also be stiff enough to guarantee an effi-
(and, depending on local conditions, even perhaps the possibility
cient boring process (Toolanen et al., 1993) and to allow for a full
and frequency of strikes) have also to be taken into account. In
utilization of the installed torque {2–7, 2–9, 2–18}. Such aspects
the case of an unexpected critical zone, reducing the amount of
are usually the responsibility of the TBM manufacturer. As a rule,
maintenance work may speed-up the TBM advance and help tem-
it should be possible to assume that the related requirements are
porarily to avoid TBM trapping, but it will increase the risk of
met.
mechanical breakdown and thus the risk of an even longer stand-
still {17–19}. Therefore, such a measure should not be applied as a
matter of course. 4.2.1. Geometry
The ground is (together with the TBM design, of course) the To reduce the friction between ground and cutter head it is first
most important parameter for achieving a given gross advance of all important that the cutter head doesn’t have greatly protrud-
rate. It represents in practical terms a purely input parameter be- ing parts (Barla and Pelizza, 2000; Schmid, 2006). This applies also
cause the possibilities of influencing its properties and behaviour for the cutters which should protrude as little as necessary for the
are very limited in relation to the particular problem investigated boring process (Korbin, 1998; McCusker, 1996).
in this paper. The pre-treatment of the ground, e.g., by grouting, Keeping the size of the cutter head small in the axial direction
reinforcement or drainage, can be carried out basically either be- reduces the area exposed to the ground pressure and is, therefore,
fore or during the TBM drive. The first solution is of course prefer- favourable (Foster, 1997; Grandori and Antonini, 1994; Maidl et al.,
able (as the improvement work will not interfere with the TBM 2001). Moreover, the cutter head can be slightly ‘‘conical”. A
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 149

reasonable conicity according to Lovat (1997) would be about 13% Overboring technology is not yet well developed and its value is
of the boring diameter. very uncertain, at least for long reaches with squeezing conditions
Theoretical considerations show that a spherical shape of the (ITA, 2003), and their successful application has yet rarely been
tunnel face (which off course necessitates a spherical form of the achieved (Wolff and Goliasch, 2003). The trouble-free application
cutter head) may reduce core extrusion and deformations in the of overboring only seems possible in rather soft rocks. The reliabil-
machine area considerably (Moulton et al., 1995). On the other ity of today’s overboring systems is in general critical {8–19}, the
hand, curvature of the tunnel face is very unfavourable for its sta- ones with continuous adjustment of the boring diameter being,
bility (Beckmann, 1984; Maidl et al., 2001; Steiner, 2000). Nowa- as a rule, the most sensitive (Gehring and Kogler, 1997; McCusker,
days almost all TBMs have flat cutter heads. 1996). The concentrated loads acting upon the extended gauge cut-
ters (Schneider and Kapeller, 1995) or their abrupt loading due to
4.2.2. Overboring falling blocks (Toolanen et al., 1993) are particularly critical, as ob-
A moderate amount of squeezing can be accommodated by bor- served, for example in the Northern Section of the Vereina Tunnel
ing a larger profile, using one to three extendable gauge cutters {8– (Switzerland, gripper TBM, D = 7.64 m), where the overcutters
10, 8–13, 8–14}. The adaptation of the boring diameter in order to were very susceptible to failure in hard or blocky rock (Hentschel,
create space for expected ground deformations was proposed on a 1997). According to Wolff and Goliasch (2003), in the Raron Sec-
conceptual basis by Lombardi (1981). After Wolff and Goliasch tion of the Lötschberg Base Tunnel (Switzerland, gripper TBM,
(2003) and Toolanen et al. (1993), respectively, the first applica- D = 9.43 m) the application of an overboring system was possible,
tions of an overboring system on full face hard rock TBMs were however only with a considerable effort.
in the Shaft Project Lohberg (Germany, gripper TBM, D = 6.50 m) Problems may also arise in heterogeneous rock masses where
and in the Piedimonte Tunnel (Italy, gripper TBM, D = 5.86 m). stretches with squeezing weak ground alternate with stretches of
The increase of the boring diameter DD depends on the chosen hard rock. The boring diameter should be enlarged before entering
system {2–8} and is, according to Wolff and Goliasch (2003), tech- the critical squeezing zones, but this is only possible if the overbor-
nologically limited to a maximum of 30 cm. (Other authors suggest ing system is able to bear the high load resulting from extending
slightly different feasible values of DD.) The amount of overboring the gauge cutters within the hard rock stretch. Such a test has been
does not depend on the boring diameter. Consequently, with carried out in the Bodio Section of the Gotthard Base Tunnel (Swit-
increasing boring diameter, the ratio between overboring (allowed zerland, gripper TBM, D = 8.80 m) and has not been successful
convergence) and boring diameter decreases and (since the ground (Gollegger et al., 2009; Rehm, 2005; Vicenzi et al., 2007).
pressure depends theoretically on this ratio) the efficiency of over- Another typical problem is represented by the blockage of the
boring also decreases. extendable gauge cutters in their start position due to their hous-
Wolff and Goliasch (2003) provided a detailed critical review of ings filling up with fine materials. In this case, it is still possible to
the different overboring systems and distinguished between the extend them, but they do not rotate anymore and, therefore, wear
following types of additional gauge cutters: (a) fixed mounted; faster and irregularly.
(b) manually extendable; (c) hydraulically extendable. The instal- In the case of a large difference between the boring diameter
lation of the first type of gauge cutters requires a halt in excavation and the diameter of the shield extrados, difficulties with the back-
{8–17} and presupposes that appropriate, empty housings have filling of the segmental lining may arise. On the one hand, the
been arranged in the cutter head {2–8}, which are covered by steel quantity of annulus grout is potentially larger. In this respect,
plates during normal operation. The manual extension of the sec- questions arise concerning the costs and the supply. On the other
ond type of gauge cutters – in steps of 25 mm (Downing et al., hand, a grout flow towards the face is easier. After Gütter (2007),
2007) – also necessitates a standstill. The hydraulic extension of a solution might be to adapt the shield diameter to the overboring
the third type of gauge cutters, however, can be carried out during in such a way that the shield continuously supports the ground. In
excavation. the same paper, however, this concept is rejected because of its
When applying overboring with shielded TBMs the centreline of technological complexity. Previous attempts to implement similar
the cutter head has to be lifted with respect to the centreline of the concepts have also been unsuccessful (cf. Section 4.3).
shield, in order to avoid sinking of the TBM (Rehm, 2005; Vigl and An alternative concept for a cutter head with a variable diame-
Jäger, 1997; Voerckel, 2001). The overboring can easily be handled ter was proposed by Baumann and Zischinsky (1993) of the com-
by gripper TBMs (Voerckel, 2001). If the TBM is equipped with a pany DMT (Deutsche Montan-Technologie). The cutter head,
cutter head shield, a re-positioning of its lower segment has to composed of two radial adjustable arms (the boring process is car-
be carried out (Wolff and Goliasch, 2003). For all TBM types a re- ried out by applying the undercutting technique), is able to exca-
positioning of the mucking buckets is also needed in order to en- vate non-circular profiles and allows for a continuous adjustment
sure efficient muck removal during overboring (Schmid, 2008). of the boring diameter depending on the thickness of the tunnel
In order to avoid over-stressing the gauge cutters (and, particu- support. It is unknown whether such a machine has ever been ap-
larly, their supports), the rotational speed of the cutter head and plied. Anyway, this concept seems to be very complex from the
the thrust force must be reduced during the overboring {8–7, 8– mechanical engineering point of view. The limited functionality
9} (Toolanen et al., 1993; Wolff and Goliasch, 2003), and this leads and reliability of such a machine has to be expected.
to a reduction of the net advance rate {7–16, 9–15–16}. So, the
overboring, if successful, leads on the one hand to a reduction of 4.3. Shield
the ground pressure acting upon the cutter head and the shield
{8–10}. On the other hand, however, it causes a slow down of The shield should be as short as possible (Lombardi, 1981). In
the TBM advance rate, which may lead to an increase of the TBM order to reduce the surface of the TBM exposed to ground pressure
loading – either during the installation of the overboring facility to a minimum, Robbins (1997) proposed the use of gripper TBMs
{17–10} or during the boring process {16–10}. Furthermore, it is without either a canopy or a cutter-head shield. Such a so-called
particularly critical to ensure timely decision-making during con- ‘‘Open Top TBM” allows support installation immediately behind
struction. Determining the right point in time for initiating compli- the cutter head and was applied (in non-squeezing conditions) in
cated overboring procedures is not easy, since the system has to be the Melbourne Underground Rail Loop (Australia, D = 6.90 m) and
activated before encountering a critical zone and before the con- in the Heitersberg Tunnel (Switzerland, D = 10.67 m). The DMT-
vergences become too large. concept mentioned in Section 4.2.2 also represents an attempt in
150 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

this direction. Anyway, gripper TBMs are generally equipped with a


short shield having a length of about half a boring diameter.
Improvements in TBM technology actually allow for a significant
reduction in the machine length (to about 1–2 boring diameters)
for single and double shielded TBMs as well. Such reductions in
length can be realized more easily with larger tunnel diameters.
For shielded TBMs, the shield length depends not only on the space
needed for the equipment, but also on the size of the segments em- Fig. 7. Construction schemes for the telescopic shield of double shielded TBMs: (a)
ployed. After Foster (1997) an increase of the segment length ‘‘Classic” design; (b) Modified design after Concilia and Grandori (2004).
necessitates an increase of double that value in the shield length.
Bigger segments – nowadays with a width of up to 2.25 m (Stahn
and Grimm, 2006) – allow for a higher gross advance rate because the shield can thus be reduced. Shield design should also take into
they reduce the operational standstill times (which is advanta- account that the ground pressure may be markedly non-uniform
geous in squeezing ground {5–17–10}) but necessitate, at the same both in the transversal and in the longitudinal direction.
time, a longer shield (which is disadvantageous in squeezing A higher deformability of the shield leads, as a rule, to a de-
ground {2–9, 2–10, 2–18}). crease of the ground pressure acting upon it. Lombardi (1981)
A slightly ‘‘conical” shield is also favourable (Lombardi, 1981). has remarked that having the possibility to reduce the diameter
The conicity of today’s single shielded TBMs amounts to 3–6 cm of the shield might be helpful in restarting the TBM after a stand-
in diameter and is realised stepwise. Depending on their design, still {2–10}. Grandori et al. (1995) proposed a flexible design of the
double shielded TBMs may have a slightly larger conicity of up to rear part of the shield. The underlying idea was that, in the case of
10 cm in diameter. An increase in the conicity and, therefore, in jamming, a small contraction of the shield should suffice in order
the overcut as well, has a positive effect with respect to the risk to free it and continue the TBM drive. The shield should return back
of shield jamming as it provides more space for the deformations to its initial, undeformed condition as soon as possible in order to
(Gehring and Kogler, 1997). The effectiveness of this measure in- allow for any subsequent exploitation of its deformability as an
creases with the ratio of overcut to boring diameter. This is a reli- unloading measure (Dowden and Cass, 1991). The application of
able measure, as it does not depend on the operability of this principle presupposes the choice of a bigger boring diameter
mechanical parts. On the other hand, such a solution implies a lar- or, at least locally, the acceptance of an under-profile with the
ger boring diameter for the entire tunnel. In the stretches with associated re-profiling works. This may be problematic particularly
non- or only slightly squeezing ground, a very wide annular gap for segmental linings, as they impose a lower limit to the inner
may have to be filled (Dowden and Cass, 1991). Besides financial diameter of the shield.
considerations, the potentially negative effect of the wide gap on The so-called ‘‘Walking Gripper Blade Shield” proposed by Rob-
the bearing capacity of the segmental lining has to be assessed bins (1997) is characterized by a shield that is divided in several,
from case to case. Wittke-Schmitt et al. (2005) examined the feasi- 1.0–1.5 m wide ‘‘blades” forming a deformable system that is able
bility of a TBM concept with a strongly conical single shield (conic- to contract inwards 7–10 cm. It is generally recognised that the
ity 60 cm in diameter) in the planning phase of the Kallidromo complexity of such a machine has a negative impact of its function-
Tunnel (Greece) and came to the conclusion that the risks and ality and reliability. The presence of several moving parts also in-
the additional costs were unacceptably high. It should also be men- creases the difficulties encountered when driving stretches in
tioned that the overcut and the conicity of the shield have first of flowing or ravelling ground. The risk of the cutter head sticking
all to permit the TBM to be steered (Amberg, 2008). If the gap be- or the shield jamming is still there, particularly in the case of a
tween the shield and the ground becomes closed, steering the TBM standstill. SNC Lavalin applied this concept by modifying a double
may become difficult or even impossible. A change in the direction shielded TBM (D = 2.91 m) for driving 1183 m of the Stillwater
of the TBM will in this case cause a considerable constraint load on Tunnel (USA) in lightly squeezing ground. Problems have been
the shield, particularly if the latter is long. reported with respect to blocky ground, steering of the machine
As observed, for example, in the Arrowhead Tunnels (USA, sin- and sealing of the main beam. A similar TBM concept was pro-
gle shielded TBM, D = 5.82 m), a closure of the radial gap between posed, but not applied, by Moulton et al. (1995) for the drive of
shield and tunnel wall may also be caused by the packing of muck the Yacambú – Quibor Tunnel (Venezuela, D = 5.00 m).
around the shield, if the material mucked out is less than the mate- Attempts to construct shrinkable shields for single shielded
rial produced by the excavation, i.e., if the capacity of the mucking TBMs are still not satisfactory (Downing et al., 2007), although
system is not attuned to the TBM advance rate. An understanding the implementation for gripper TBMs does seem to be possible. A
of the TBM’s operational parameters is also important in this re- reduction of the shield diameter of 15–20 cm is achievable apply-
gard. Packing of fines around the shield reduces the space available ing hydraulic jacks. In this respect, Robbins (1997) proposed an-
for deformations and may therefore lead to an earlier development other gripper TBM concept (never used), which was the so-called
of ground pressure upon the shield. ‘‘Low Pressure Walking Blade Canopy”. In this concept the upper
The surface of the shield should be as smooth as possible. A part of the cutter head shield of the gripper TBM would be deform-
favourable construction, which avoids the stepwise increase of able (a blade shield) while the bottom part would be practically
the rear shield diameter, is nowadays possible also for the tele- rigid.
scopic part of double shields (Fig. 7). Such a design may, neverthe- According to Gehring (1996), the injection of lubricants such as
less, present problems with the backfilling of the segments as it bentonite can reduce considerably (up to 50%) the friction between
leads to a wide gap between the tunnel wall and the extrados of shield and ground. The lubricant is injected through the shield {2–
the rear shield (Burger, 2009). 9, 2–18}. A thin lubricant film suffices to reduce skin friction.
The bearing capacity of the shield has to be high enough for the Therefore the bentonite should be sprayed and not be pumped,
ground pressure {10–18}, which acts in addition to the system in order to reduce the amount needed and the risk of an uncon-
loads (e.g., thrust force, torque, self weight). In this regard, struc- trolled flow of the suspension towards the cutter head (Schmid,
tural reserves are recommended. The design load should be higher 2008).
than the level of ground pressure that would lead to shield jam- As a further measure for single and double shielded TBMs,
ming. The probability of overloading with permanent damage to Grandori (1996) and Vigl and Jäger (1997) remarked that it is
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 151

advantageous to have the possibility of accessing the rock mass It has also to be borne in mind that the options for intervention
through the shield in order to be able to intervene (e.g., to free in the back-up area are limited to certain areas only, which are pre-
the TBM by hand-mining) whenever required. According to Gran- determined by the design of the back-up equipment. As discussed
dori (2001) this is possible for double shielded TBMs through open- in Section 3.1.3, this is particularly important for gripper TBMs.
ings in the shield or through a complete opening of the telescopic These constraints must be considered when planning a TBM drive
shield. Before initiating such an operation, a careful evaluation for squeezing ground and, where necessary, requirements must be
should be made as to whether the stability of the rock mass is suf- formulated in the TBM specifications.
ficient for ensuring working safety.
4.6. Tunnel support
4.4. Thrust force and torque
Concerning conceptual design of tunnel support in squeezing
Improvements in TBM technology allow the installation of high- ground, a distinction is usually made between two principles:
er thrust forces and torques. the ‘‘resistance principle” and the ‘‘yielding principle” (Kovári,
For gripper TBMs the achievable reaction forces have to be 1998). In the first case, one applies a practically rigid lining, which
borne in mind when selecting the installed thrust force and torque. must be strong enough to bear the ground pressure developing
For given ground parameters {1–7, 1–9, 1–18}, the achievable reac- when preventing ground deformations. In the second case, one
tion forces depend primarily on the dimensions of the grippers and avoids the development of excessive ground pressures by accept-
on the installed gripper force {2–7, 2–9, 2–18} (cf. Section 3.1.2). ing a certain amount of ground deformation. In reality, the interac-
The total gripper force (perpendicularly to the tunnel axis) is, as tion between lining and ground leads as a rule to a situation that is
a rule, higher by a factor 2.0–3.5 than the installed thrust force. somewhere between the two extremes. For the sake of simplicity,
An actual gripper TBM with a boring diameter of about 10 m can however, the following discussion will retain the distinction be-
dispose of an installed thrust force of about 30–35 MN and a break- tween a practically rigid and a yielding support.
out torque of about 10–15 MNm. It should be noted that the tunnel support – besides ensuring
For shielded TBMs with a similar boring diameter, a thrust force stability and limiting deformations of the tunnel – may also reduce
of up to 150–200 MN and a breakout torque of up to 30–40 MNm shield loading. The installation of a stiff support immediately be-
are nowadays feasible. As a temporary solution, the thrust force hind the shield improves load transfer by arching in the longitudi-
can be increased on the construction site by installing removable nal direction (Fig. 8), thus leading to a reduction of the ground
auxiliary hydraulic jacks. This has been done, for example, in the pressure acting upon the shield {5–10} (Anagnostou and Ramoni,
Arrowhead Project (USA, single shielded TBM, D = 5.82 m) and in 2007). This effect is more pronounced for short shields and stiff lin-
the Uluabat Tunnel (Turkey, single shielded TBM, D = 5.05 m). In ings according to the ‘‘resistance principle”. On the other hand, the
the first case the segmental lining has already been able to bear load developing upon a stiff lining installed immediately behind
the higher axial loads, while in the second case it became damaged. the shield is bound to be higher than the load upon a more deform-
As reported by Iwasaki et al. (1999), Shimaya (2005) and Terada able support installed at a greater distance behind the face.
et al. (2008), a design combining the thrusting systems of gripper
and single shielded TBM was developed and applied for the drive 4.6.1. Practically rigid supports
of the Hida Tunnel (Japan, D = 12.84 m). The thrusting mode (i.e., Segmental linings (the standard support with shielded TBMs) can
grippers or hydraulic jacks) was chosen according to the support be classified – on the basis of their high stiffness and strength –
applied. The possibility of installing a segmental lining was fore- as tunnel supports which follow the ‘‘resistance principle”. Pre-
seen in order to achieve a higher thrust force (55 MN in single fabrication makes it possible to achieve high uniaxial compressive
shielded TBM mode vs. 33 MN in gripper TBM mode) and to strengths in the concrete (up to 50 MPa or even more) with sufficient
achieve a faster (and, therefore, favourable {16–10, 17–10}) TBM levels of reliability and thus the ability to cope with high ground
advance in difficult ground conditions, including but not limited pressures. In order to be able to utilize fully the installed thrust force
to squeezing ground. The papers referred to do not describe any and torque, the lining design has to take into account of course the
practical experience with squeezing ground that might or might combined action of ground pressure and TBM forces. A proper and
not confirm the suitability of this concept. fast-acting embedment of the segmental lining is very important
for its bearing capacity. Rapidly setting, two-component grouts
(applied through the shield tail as in soft ground TBMs) may be
4.5. Back-up equipment advantageous in this respect.
For shielded TBMs, it has also been proposed to use the segmen-
The production rate of the TBM may also be affected by the per- tal lining to support the tail shield in the case of major squeezing.
formance and layout of the back-up equipment. From a logistical For the Wienerwald Tunnel (Austria, single shielded TBM,
point of view, it is very important that supplies to the machine area D = 10.67 m) this has been planned as a counter measure for unex-
and mucking out, as well as all activities in the back-up area (e.g.,
casting of an invert arch), do not affect TBM performance {3–17}. A
robust design of the back-up equipment is important for reducing
mechanical breakdowns, which might also affect TBM advance {3–
19}.
Problems in the back-up area may also slow down or even halt
the TBM drive {13–19, 14–19}. Jamming of the back-up equipment
is particularly critical, as it always leads to the machine being
stopped and, possibly, further problems as well {19–10, 19–13,
19–14}. Therefore, it is a good idea to make the back-up trailers
small enough relatively to the boring diameter to gain some space
in case of unexpectedly high ground deformations in the back-up
area {3–13, 3–14}, i.e., if the support installed should not suffice Fig. 8. Arch action in longitudinal direction around the shield in the presence of a
to prevent ground deformations {5–13, 5–14, 6–14}. rigid lining.
152 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

pected stops of the TBM drive in squeezing ground (Matter et al., tural detailing, a sufficiently high yield pressure is very important
2007). As a similar special measure, Gütter (2007) suggested for safety (Anagnostou and Cantieni, 2007; Cantieni and Anagnos-
inserting air cushions between the tail shield and the segmental tou, 2009), but may be difficult to be achieved in combination with
lining in order to provide a temporary support to the tail shield, shotcrete because (in contrast to conventional tunnelling) the ad-
which, as a rule, is thinner and less stiff than the rest of the shield. vance rates are high relative to the time needed for shotcrete hard-
As an alternative for implementing the ‘‘resistance principle”, ening. Steel sets with sliding connections are advantageous in this
Babendererde (1986) proposed the use of extruded concrete. Nel- respect. Furthermore, long bolts (>5–6 m for common cross-sec-
son et al. (1992) and Einstein and Bobet (1997) also emphasized tions of traffic tunnels) are indispensable, particularly for coping
the advantages of a machine employing extruded concrete, partic- with non-uniform rock convergences and in order to ensure the
ularly in combination with a shorter shield than the one of Babend- stability of deformable tunnel supports during the yielding phase.
ererde (1986), and proposed the so-called ‘‘MIT Continuous TBM”. It should be noted that systematic bolting (in contrast to shotcrete
The papers referred to do not describe any case histories where or steel sets) does not consume bored space, thus leaving more
these TBM concepts have been applied in squeezing ground. In space free for the ground deformations to occur. The support pres-
spite of the practical applications reported in Babendererde and sure achievable by bolts is, nevertheless, rather low (0.1–0.3 MPa).
Babendererde (2001), extruded concrete has not been established In tunnelling with shielded TBMs, coping with squeezing pres-
in tunnelling practice. One reason for this seems to be the high sure may necessitate very thick segments, which, besides increas-
mechanical complexity of these machines. Furthermore, it is ques- ing the required boring diameter, are difficult to handle.
tionable whether the thrust force requirements for squeezing Deformable segmental lining systems specifically for shielded
ground can be satisfied. TBMs have therefore been the subject of intensive past and current
In the case of gripper TBMs, the applicability of the ‘‘resistance research and development (e.g., Billig et al., 2007a; Schneider et al.,
principle” is more limited than in shielded TBMs because it is dif- 2005; Vigl, 2003). A deformable segmental lining can be realized
ficult to achieve the same high quality and resistance for the shot- basically in two ways: either (i) by arranging a compressible layer
crete applied in the machine area as in the case of a prefabricated between the ground and the lining (the ground experiences con-
segmental lining. In order to achieve a comparably high support vergences, while the deformations of the lining remain small,
resistance, a large quantity of shotcrete must be applied and this Fig. 9a) or (ii) by arranging special deformable elements in the lon-
slows down the advance rate considerably. Furthermore, the load gitudinal joints of the lining that allow for a reduction of its cir-
on the tunnel support in the machine area increases with the ad- cumference (Fig. 9b).
vance of the tunnel face and this happens simultaneously with
the hardening of the shotcrete. The higher the gross advance rate, 4.6.2.1. Yielding layers between segmental lining and ground. The ba-
the lower will be the strength and stiffness of the shotcrete in the sic idea has been proposed and was patented in England in 1979 –
machine area {16–5, 17–5} and, therefore, the less the shotcrete J. Mowlem, UK Patent application GB 2013 757 A, cf. Schneider
will contribute to the load bearing action in the longitudinal direc- et al. (2005). For a TBM drive through swelling ground, Lombardi
tion around the shield (Fig. 8). This is unfavourable for the shield (1981) proposed the application of a compressible layer consisting
{5–10}. During long standstills, however, the longitudinal arch ac- of polyurethane foam. Wittke-Schmitt et al. (2005) investigated
tion between core and tunnel support can be enhanced by building the possibility of using expanded clay as a backfilling material
a thicker shotcrete ring (30 cm or more) immediately behind the (cf. Section 4.3). Vigl (2003) presented a ‘‘convergence-compatible”
shield. This leads to lower shield loads, as discussed above. Such segmental lining. The segments in this so-called ‘‘CO–CO-system”
a precautionary measure was applied, for example, in the Faido incorporate at their extrados supporting ribs, which are in contact
Section of the Gotthard Base Tunnel (Switzerland, gripper TBM, with the rock. The ground is allowed to squeeze into the space be-
D = 9.43 m) during the holiday break of Easter 2008. tween the ribs, which can be either empty or filled by a compress-
ible material. Another possibility is given by the addition of a
4.6.2. Yielding supports compressible layer fixed at the extrados of the segments in combi-
In tunnelling with gripper TBMs, the same yielding supports can nation with a traditional annular grouting or a compressible grout
be applied as for conventional tunnelling. The Northern Section of (Billig et al., 2007a; Schneider et al., 2005).
the Vereina Tunnel (Switzerland, D = 7.64 m) and the Sections A compressible annulus grouting material must have, with the
Amsteg (D = 9.58 m) and Faido (D = 9.43 m) of the Gotthard Base exception of a high deformability of course, all of the other usual
Tunnel (Switzerland) may be mentioned as practical examples. properties of gap grouting materials: easy processing, pumpability
The applicability range of the ‘‘yielding principle” is, neverthe- and high stability of the material. For these and for economic rea-
less, strongly limited by the fixed geometry of the equipment sons light weight concrete is usually proposed (Strohhäusl, 1996).
and the required clearance profile. The design of the yielding sup- Schneider et al. (2005) developed the so-called ‘‘Compex”, a com-
port must be considered when selecting the boring diameter and pressible mortar with expanded polystyrene that can be com-
the dimensions of the back-up equipment in order to avoid costly pressed up to 50%. Billig et al. (2007a) reported about the
(and sometimes dangerous) re-profiling works or jamming of the development of the so-called ‘‘DeCo Grout”, a cement-based pum-
back-up equipment {3–13, 5–13, 3–14, 5–14, 6–14}. The continu- pable mortar with expanded polystyrene pearls and foam, which is
ous adjustment of the boring diameter using overboring tech- also characterized by a maximum compression of about 50%.
niques is still not sufficiently reliable today and, if at all feasible,
the increase that can be achieved in the boring diameter is also 4.6.2.2. Deformable longitudinal joint elements. Wood was often
limited (cf. Section 4.2.2). On the other hand, the choice of a fixed, used in the past as a compressible element in mining (Fig. 10a)
but larger boring diameter for the entire tunnel is often not eco- and it is interesting to note that it was also applied in combination
nomical. It should be also noted, that the deformability of the lin- with prefabricated concrete elements many years ago (Lenk, 1931).
ing leads to a reduction of its loading, but weakens the longitudinal Recent, mainly experimental, attempts to increase the flexibility of
arch action and thus leads to an increase in the ground pressure precast segmental linings utilize neoprene elements or hydraulic
acting upon the shield {5–10}. Furthermore, allowing larger defor- devices, which are arranged in the longitudinal joints (Fig. 10b
mations may lead to major loosening phenomena or to a softening and c).
of the ground. This has to be taking into account in the design of Brunar and Powondra (1985) reported on the development of
the deformable tunnel support. In addition to an appropriate struc- the so-called ‘‘Meypo deformable elements”, which should be
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 153

achieved for a shielded TBM with a segmental lining (Schneider


and Spiegl, 2008). The reasons for this can be traced back to some
critical aspects, which are common to all proposed concepts.
There is, first of all, a fundamental difference between imple-
menting the yielding principle in a gripper TBM (or in conventional
tunnelling) and implementing the yielding principle in a shielded
TBM. In the first case, the tunnel support (which consists usually
of shotcrete, steel sets and bolts) has as a rule only a temporary
function: it has only to ensure stability and to preserve the shape
of the opening during construction. After construction of the final
lining by cast-in-situ concrete, the condition of the temporary sup-
port (whether heavily cracked or deformed) is absolutely irrele-
vant. This is not true for a tunnel support by precast segments as
Fig. 9. Concepts for deformable segmental linings: (a) Compressible layer between this support represents in most cases the final lining as well and
rock and lining; (b) Deformable elements in the longitudinal joints between the
has, in general, to fulfil two requirements in addition to safety:
segments.
the geometry of the clearance profile must not deviate too much
from the theoretical one and, as a rule, the lining must be practi-
cally waterproof. The uncertainties are large with respect to these
objectives, because a flexible lining adjusts its shape to the ground
deformations and the distribution of the latter along the circumfer-
ence of the opening cannot be predicted with sufficient reliability.
Such a system is very vulnerable to non-uniformly distributed
pressures. An asymmetrically squeezing ground can displace the
lining entirely.
In order to ensure that the clearance profile will not be violated,
sufficient tolerances and thus a larger boring diameter are neces-
sary. (According to Schneider and Spiegl (2008), the machine
Fig. 10. Prefabricated segmental lining with compressible longitudinal joints: (a) should allow for adjustments in the size of the annular gap.) Con-
Wood (Lenk, 1931); (b) Neoprene layers and flatjacks (Croci, 1986); (c) Hydraulic cerning continuous adjustments in the gap size, the same critical
jacks (Baumann and Zischinsky, 1993); (d) Steel tubes (Tusch and Thompson, remarks apply as for the gripper TBMs. Furthermore, a reliable
1996); (e) Highly deformable concrete elements (Kovári, 2005).
forecast of ground deformations is often difficult. An underestima-
tion of the gap size will cause over-stressing of the support. This
placed in the longitudinal joints of a segmental lining and allow for applies of course to gripper TBMs as well. The difference is, again,
a reduction of its circumference. The Meypo elements have been that it may be acceptable to exploit a large percentage of the bear-
applied in a tunnel in the Ibbenbüren Coalmine in Germany at a ing capacity for a temporary structure, but for a final structure it is
depth of about 1500 m (inner diameter of the segmental lining not.
9.47 m). In this case, however, the tunnel was driven convention- In addition to the fundamental issues addressed above, there is
ally, support during excavation consisted of shotcrete and rock a series of specific disadvantages. So, for example, systems com-
bolts and the segmental lining was applied as a final tunnel sup- prising deformable joints are very costly (in terms of materials
port. The deformable elements fulfilled expectations, but it was and time), particularly if the tunnel lining must be waterproof
also realized that the costs of such a solution would be too high and, consequently, the deformable elements need to provide a
for it to be systematically applied in tunnelling (Maidl et al., sealing function (another difficult problem, which is, nevertheless,
2001). The suggestion was therefore made of deploying reusable irrelevant to the temporary support applied when employing a
deformable elements, which must be removed after the ground gripper TBM).
has deformed and before setting the system rigid by applying shot- Questions also arise with respect to the other type of deform-
crete into the longitudinal slots. Baumann and Zischinsky (1993) able segmental linings (employing a compressible layer between
proposed the use of hydraulic jacks for this purpose. (As reported lining and rock). The characteristics of the backfilling material
by Croci (1986), hydraulic jacks have also been applied earlier in must be such that it is able to deform but at the same time it
Italy in the Tunnel Santomarco.) These are also expensive, slowing should be stiff enough to assure a proper bedding of the segmental
down installation considerably and necessitating heavy reinforce- lining. In general, the application of a compressible layer at the
ment in order to overcome burst and shear forces. extrados of the segmental lining weakens its bedding (McCusker,
The technical literature also includes other types of deformable 1996) and decreases, therefore, its bearing capacity with respect
elements. So, for example, Strohhäusl (1996) proposed plastic to non-uniformly distributed loads. A highly compressible backfill
bodies. Other possibilities are the application of steel or plastic decreases the hoop forces but markedly increases the bending mo-
pipes (Maidl et al., 2001; Tusch and Thompson, 1996) or, as pro- ments in the segments (cf., e.g., Graziani et al., 2007). Billig et al.
posed by Kovári (2005), of highly deformable concrete elements (2007b) acknowledged the ‘‘bedding problem” and proposed
(Fig. 10d and e). adjusting the time-dependent development of the stiffness and
strength of the compressible mortar by using an appropriate mix-
ture – a demanding task under construction site conditions.
4.6.3. On the appropriate support concept Finally, a low stiffness of the annulus material may also present
Apart from a 20 m long successful test drive in no squeezing problems with respect to the jacking forces. Small, practically
ground (Schneider and Spiegl, 2009) accomplished with the ‘‘Com- unavoidable deviations from the axial direction may push the lin-
pex” compressible mortar (c.f. Section 4.6.2) in the framework of ing aside. This is particularly true in the case of a rapidly squeezing
the Jenbach Tunnel (Austria, mixshield, D = 13.00 m), up until to- ground that exerts a considerable load on the shield, thus necessi-
day, in spite of considerable research and development efforts, tating a high thrust force in order to keep the machine advancing.
no successful implementation of the ‘‘yielding principle” has been In this respect, it is worth remembering that the ground pressure
154 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

which develops upon the shield when applying a yielding support that the ground would immobilize the TBM at a depth of about
is in general higher than in the case of a practically rigid lining {5– 300 m, which is slightly lower than the depth at which over-stress-
10}, as the latter facilitates arch action in the longitudinal direction ing of the 35 cm thick lining would occur. By installing a higher
around the shield. A compressible layer around the segmental lin- thrust force of 250 MN – which, according to Burger (2009), is
ing may therefore affect system behaviour in that (i) it reduces the technologically possible for common boring diameters of traffic
squeezing pressure acting upon the lining but (ii) increases the tunnels – and by taking additional measures to reduce skin friction
ground loading of the shield and (iii) this means that it may be nec- (lubrication), jamming would not occur until the depth of cover
essary to increase the jacking forces, while, (iv) at the same time, reached about 500 m, while the bearing capacity of the lining
the bearing capacity and the stiffness of the lining will in general would become relevant at a depth of 300–350 m. Lining design
be lower due to the weaker embedment. for greater depths should also take into account the higher axial
It should be noted, furthermore, that it is questionable if a high load caused by the thrust force. A solution based on the resistance
deformability of the segmental lining is at all necessary. As indi- principle would be, nevertheless, still possible in the present exam-
cated by numerical simulations, jamming of the shield (rather than ple: one could increase the thickness of the segments (which is fea-
over-stressing of the lining) is the relevant hazard scenario in sible up to 70 cm) or apply segments made of high performance
many cases: under adverse conditions squeezing will halt the concrete (HPC) having a very high uniaxial compressive strength
TBM advance before endangering the structural safety of the seg- (a design value of up to 50–60 MPa).
mental lining. Fig. 11 shows computational results obtained for a Should it be necessary to further increase the resistance of the
10 m long, single shielded TBM boring a 10 m diameter tunnel in segmental lining (beyond the resistance offered by segments of
weak sedimentary rock. The computational method is after Anag- manageable thickness and weight), it is possible to design a lining
nostou (2007) and assumes axial symmetry and linearly elastic, system consisting of two concentric segment rings (Fig. 12). The in-
perfectly plastic ground behaviour with the Mohr–Coulomb yield ner segmental lining would be applied (by the same erector) only
criterion. The diagram shows the effect of the depth of cover H when required. The outer ring could be made of HPC, while normal
on the risk of shield jamming or lining over-stressing (solid and concrete would be advantageous for the inner ring (on account of
dashed lines, respectively). The risk of shield jamming is expressed its higher fire resistance). Depending on the water pressures in
by the ratio of the installed thrust force Fi to the force Ff needed for the project area, it might be also possible for the inner ring alone
overcoming friction. The risk of over-stressing is expressed by the to be waterproof. A solution with a double segmental lining makes
ratio of the allowable loading of the lining rmax to the ground pres- sense only in heavily squeezing ground and should, therefore, be
sure r developing far behind the face. For an installed thrust force combined with a minimum possible shield length in order to re-
Fi = 150 MN (a high but nevertheless achievable value) and an uni- duce the surface exposed to rock pressure and to utilize the favour-
axial compressive strength for the lining of fc = 25 MPa (a design able longitudinal arching (Fig. 8).
value already incorporating a safety factor), the diagram shows The above discussion suggests that shield jamming limits feasi-
bility to a larger extent than lining over-stressing. It could be ar-
gued, however, (i) that shield jamming, in contrast to segmental
lining damage, may be regarded as an acceptable risk and (ii) that
if the deformations develop slowly, the shield may advance with-
out any problems even if a high rock load develops far behind
the face (in this case too, lining over-stressing rather shield jam-
ming would be the relevant factor). Concerning the first point, it
is impossible to make a generally valid statement as the acceptan-
cy of jamming depends of course on the potential damage to the
TBM as well as on the frequency of the events necessitating
hand-mining for freeing the TBM. With regard to the second objec-
tion, it should be noted that estimating the intensity of squeezing
is an extremely uncertain task in the planning phase and, conse-
quently, decision-making should make some contingency for rap-
idly developing deformations. This is also why the computational
methods employed in engineering practice (during design for the
assessment of squeezing) usually do not take into account the
time-dependency of ground behaviour.
In conclusion, the traditional, practically rigid segmental lining
seems to be the appropriate solution for shielded TBMs crossing

Fig. 11. Effect of an increase of the depth of cover H on the risk of shield jamming
(safety factor Fi/Ff) or of over-stressing of the lining (safety factor rmax/r) for a 10 m
long single shielded TBM with a boring diameter of 10 m. Fig. 12. Double segmental lining.
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 155

squeezing ground: precast segments can bear high ground pres- bearing capacity of the ground is in the gripper area; on how rap-
sures and, if properly bedded, high thrust forces as well. Indeed, idly the convergences or ground pressures develop; on how much
it seems to be a contradiction to incorporate expensive, high-qual- support has to be installed in the TBM area in order to stabilize the
ity precast segments (which are constructed with tolerances of 1– opening and control the deformations.
2 mm) into a support system that may experience uncontrollable Without a thorough analysis, taking into account all the specif-
deformations of several cm – 10–20 cm radial convergence after ics of a given geotechnical situation, it is not easy to judge which
Schneider et al. (2005) and Billig et al. (2007a). The large flexibility factor will have the greater impact. Depending on the geological
of deformable segmental linings is favourable with respect to their conditions, the advantages of one TBM type may or may not coun-
structural safety but (almost by definition) unfavourable as regards teract the disadvantages of the other types. It is therefore impossi-
serviceability requirements, which as said above are particularly ble to provide universally valid recommendations. A systematic
important given the permanent character of the structure. approach such as the one outlined in Section 3 is indispensable
For gripper TBMs, however, yielding supports appear to be more for the identification and assessment of the interactions between
attractive: the serviceability requirements are of secondary impor- ground, tunnelling equipment and support.
tance for temporary supports; the implementation of the ‘‘yielding
principle” in a gripper TBM bears less risks than in a shielded TBM
because the thrusting system does not depend on the behaviour of Acknowledgements
the support and one can apply the same yielding elements as in
conventional tunnelling. It should be noted, however, that the con- This paper evolved within the framework of the research pro-
sequent application of the ‘‘yielding principle” is rarely possible as ject ‘‘Design aids for the planning of TBM drives in squeezing
the boring diameter and the clearance profile determine the ground”, which is being carried out at the ETH Zurich, supported
amount of permissible convergence. On the other hand, the imple- by the Swiss Tunnelling Society (STS) and financed by the Swiss
mentation of the ‘‘resistance principle” may necessitate, depending Federal Roads Office (FEDRO). The authors would also like to ex-
on the ground pressure, such a thick shotcrete shell that the avail- press their gratitude for the helpful discussions and suggestions
able space does not suffice. So, both design principles may require that have taken place with W. Burger and U. Rehm (Herrenknecht
the choice of a bigger diameter in order to accommodate either a AG) and L. Schmid (Consulting Engineer) as well as with the mem-
thicker lining or ground deformations. The scope of action is in fact bers of the commission following this project on behalf of FEDRO:
fairly limited. F. Amberg (Amberg Engineering AG), F. Bertholet (Marti Tunnelbau
AG), M. Bosshard (Basler & Hofmann AG), T. Edelmann (Herrenkn-
echt AG) and C. Gametter (FEDRO).
5. Closing remarks
References
TBM performance is the result of a complex interaction be-
tween the ground, the tunnelling equipment (TBM and back-up) Amberg, R. 1992. Economic aspects when building tunnels with major overburden.
and the support. The factors resulting from the three main compo- Tunnel 3/92, 120-124.
nents of the system affect the TBM drive simultaneously and are Amberg, F., 2008. Amberg Engineering AG (Personal Communication, February
2008).
usually coupled with each other. Together with ‘‘external” factors Anagnostou, G., 2007. Continuous tunnel excavation in a poro-elastoplastic
(such as the organisation of the construction site) they ultimately medium. In: Tenth International Symposium on Numerical Models in
result in the achievement of a gross advance rate, which represents Geomechanics, NUMOG X, Rhodes, Taylor & Francis Group, London, pp. 183–
188.
the main outcome of the interaction and at the same time a factor Anagnostou, G., 2009. The effect of advance-drainage on the short-term behaviour
influencing the interaction. of squeezing rocks in tunnelling. In: International Symposium on
When planning a TBM drive in squeezing ground, the tunnelling Computational Geomechanics (COMGEO I), Juan-les-Pins, International Centre
for Computational Engineering Rhodes, pp. 668–679.
engineer is confronted with a complex problem, where conflictive Anagnostou, G., Cantieni, L., 2007. Design and analysis of yielding support in
requirements may be present. In the tunnel engineering commu- squeezing ground. In: The second half century of rock mechanics, 11th Congress
nity there is a certain degree of controversy concerning the most of the International Society for Rock Mechanics (ISRM), Lisbon, vol. 2. Taylor &
Francis Group, London, pp. 829–832.
appropriate machine type for coping with squeezing ground. The
Anagnostou, G., Ramoni, M., 2007. Untersuchungen zum TBM-Vortrieb südlich der
application of gripper TBMs is proposed on the grounds of their Chiera Synform. AlpTransit Gotthard, Gotthard-Basistunnel, Teilabschnitt Faido,
shorter length as well as their greater flexibility with respect to Bericht 071101 – 20. Dezember 2007, Professur für Untertagbau, Institut für
tunnel support. On the other hand, it is emphasized that single Geotechnik (IGT), ETH Zürich, Interner Bericht.
Babendererde, S., 1986. Extruded concrete lining. In: International Congress on
or double shielded TBMs allow for highly industrialized tunnel Large Underground Openings, Florence, vol. 1. SIG Milan, pp. 607–611.
construction, and this – in combination with the higher thrust Babendererde, S., Babendererde, J.O., 2001. Extruded concrete lining – The future
force and torque that can be applied by these machines – results lining technology for industrialized tunnelling. In: Rapid Excavation and
Tunnelling Conference, San Diego, SME Inc. Littleton, pp. 679–685.
in a higher advance rate. Barla, G. 2001. Tunnelling under squeezing rock conditions. In: Eurosummer-School
The differing opinions can possibly be traced back to the differ- in Tunnel Mechanics, Innsbruck, Logos Verlag Berlin, pp.169–268.
ent project-specific geological conditions and tunnelling experi- Barla, G., Pelizza, S., 2000. TBM tunnelling in difficult ground conditions.
GeoEng2000 – International Conference on Geotechnical & Geological
ence of the authors. Consider, for example, a small diameter Engineering, Melbourne, vol. 1. Technomic Publishing Company Inc.
tunnel (say D = 5 m) and compare a gripper TBM (equipped with Lancaster, pp. 1471–1489.
only a short cutter head shield) with a 10 m long double shielded Baumann, L., Zischinsky, U., 1993. Neue Löse- und Ausbautechniken zur
maschinellen ‘‘Fertigung” von Tunneln in druckhaftem Fels. In: Innovationen
TBM. The length of the double shield is potentially disadvanta- im unterirdischen Bauen, STUVA-Tagung ‘93, Hamburg, Forschung+Praxis 35,
geous with respect to the risk of jamming. It cannot, however, be Alba Fachverlag GmbH + Co. KG Düsseldorf, pp. 64–69.
said that this disadvantage is really relevant in a particular geo- Beckmann, U., 1984. Tunnelbau im Untertagebau – Tunnelbohrmaschinen und ihr
Einsatz im Festgestein. In: Taschenbuch für den Tunnelbau 1985, VGE Verlag
technical situation (it depends on how rapidly the ground con-
Glückauf GmbH Essen, pp. 57-101.
verges). On the other hand, a gripper TBM also has potential Bergmeister, K., 2007. Brenner base tunnel: link between Munich and Verona.
disadvantages such as lower thrust (particularly in the case of grip- Tunnel 1/2007, pp. 9-20.
per bracing problems) or lower advance rate (particularly if the Billig, B., Ebsen, B., Gipperich, C., Schaab, A., Wulff, M., 2007a. DeCo Grout –
Innovative grout to cope with rock deformations in TBM tunnelling. In:
support requirements are big). Again, these disadvantages may Underground Space – The 4th Dimension of Metropolises, ITA World Tunnel
be relevant or not depending on the geology: on how high the Congress 2007, Prague, vol. 2. Taylor & Francis Group, London, pp. 1487–1492.
156 M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157

Billig, B., Gipperich, C., Wulff, M., Schaab, A. 2007b. Ausbausysteme für den Stuttgart, Forschung+Praxis 36, Alba Fachverlag GmbH + Co. KG Düsseldorf,
maschinellen Tunnelbau in druckhaftem Gebirge. In: Taschenbuch für den pp. 23–29.
Tunnelbau 2008, VGE Verlag GmbH Essen, pp. 223-262. Kovári, K. 1998. Tunnelling in squeezing rock. Tunnel 5/98, 12-31.
Brunar, G., Powondra, F., 1985. Nachgiebiger Tübbingausbau mit Meypo- Kovári, K., 2005. Method and device for stabilizing a cavity excavated in
Stauchelementen. Felsbau 3 (4), 225–229. underground construction. US Patent 20050191138.
Burger, W., 2009. Herrenknecht AG (Personal Communication, March 2009). Lano, R.J., 1990. The N2 chart. In: System and Software Requirements Engineering,
Cantieni, L., Anagnostou, G., 2009. The interaction between yielding supports and IEEE Computer Society Press Washington, pp. 244–271.
squeezing ground. Tunnelling and Underground Space Technology 24 (3), 309– Lenk, K., 1931. Der Ausgleich des Gebirgsdruckes in grossen Teufen beim Berg- und
322. Tunnelbau. Springer-Verlag, Berlin.
Concilia, M., Grandori, R., 2004. New viola water transfer tunnel. In: Mechanized Lombardi, G., 1981. Bau von Tunneln bei grossen Verformungen des Gebirges. In:
Tunnelling: Challenging Case Histories, International Congress, Turin, GEAM Tunnel 81, Internationaler Kongress, Düsseldorf, Band 2, Messegesellschaft
Turin, pp. 27–34. mbH NOEWA Düsseldorf und Deutsche Gesellschaft für Erd – und Grundbau
Croci, G., 1986. Progettazione, costruzione e sperimentazione del rivestimento e.V. Essen, pp. 351–384.
prefabbricato della galleria Santomarco, nella zona interessata da terreni Lovat, 1997. Questionnaire on the TBM design for the experimental tunnel under
estremamente spingenti con ricoprimento di circa 1000 metri. In: Congresso the Gibraltar Straits (TBM manufacturers inquiry). In: Workshop ‘‘The Gibraltar
internazionale su grandi opere sotterranee, Firenze, vol. 1. Dipartimento di Crossing”, Tarifa, ITA Bron Cedex.
ingegneria civile, Università di Firenze, pp. 137–146. Maidl, B., Schmid, L.R., Ritz, W., Herrenknecht, M., 2001. Tunnelbohrmaschinen im
Dowden, P.B., Cass, D.T., 1991. Shielded TBM’s – Matching the machine to the job. Hartgestein. Ernst & Sohn Verlag für Architektur und technische
In: Rapid Excavation and Tunnelling Conference, Seattle, SME Inc. Littleton, pp. Wissenschaften GmbH, Berlin.
787–805. Matter, J., Stauber, A., Bauer, F., Daller, J., 2007. ÖBB Wienerwaldtunnel –
Downing, B., Carter, T., Beddoes, R., Moss, A., Dowden, P., 2007. Use of tunnel boring Erfahrungen aus dem Vortrieb. In: FGU-Fachtagung für Untertagbau, Swiss
machines at depth: extending the limits. In: Rapid Excavation and Tunnelling Tunnel Congress 2007, Luzern, D0222, SIA Zürich, pp. 101–112.
Conference, Toronto, SME Inc. Littleton, pp. 1131–1142. McCusker, T.G., 1996. Tunnelling in difficult ground. In: Tunnel Engineering
Einstein, H.H., Bobet, A., 1997. Mechanized tunnelling in squeezing rock – From Handbook, second ed. Chapman & Hall, New York. pp. 153–176.
basic thoughts to continuous tunnelling. In: Tunnels for People, ITA World Moulton, B.G., Cass, D.T., Nowak, D.E., Poulin, R.M., 1995. Tunnel boring machine
Tunnel Congress ’97, Vienna, vol. 2, A.A. Balkema, Rotterdam, Brookfield, pp. concept for converging ground. In: Rapid Excavation and Tunnelling
619–632. Conference, San Francisco, SME Inc. Littleton, pp. 509–523.
Farrokh, E., Rostami, J., 2009. Effect of adverse geological condition on TBM NASA, 2007. Systems Engineering Handbook. NASA/SP-2007-6105 Rev1, National
operation in Ghomroud tunnel conveyance project. Tunnelling and Aeronautics and Space Administration, Washington.
Underground Space Technology 24 (4), 436–446. Nasri, V., Fauvel, P., 2005. Lyon-Turin long and deep railway tunnel project. In:
Floria, V., Fidelibus, C., Repetto, L., Russo, G., 2008. Drainage and related increase of Rapid Excavation and Tunnelling Conference, Seattle, SME Inc. Littleton, pp.
short-term strength of low permeability rock mass. In: Building Underground 531–543.
for the Future, AFTES International Congress Monaco, Montecarlo, Edition Nelson, P.P., Peterson, C.R., Einstein, H.H., Hood, M., 1992. Manufacturing
Specifique Limonest, pp. 281–284. underground space. In: Towards New Worlds in Tunnelling, International
Foster, J.R., 1997. Characterisation of tunnel boring machines. In: Workshop ‘‘The Congress, Acapulco, vol. 1. A.A. Balkema, Rotterdam, Brookfield, pp. 29–36.
Gibraltar Crossing”, Tarifa, ITA Bron Cedex. Pelizza, S., Peila, D., 2005. TBM tunnelling in rock: ground probing and treatements.
Gehring, K.H., 1996. Design criteria for TBM’s with respect to real rock pressure. In: In: International Symposium on Design, Construction and Operation of Long
Tunnel Boring Machines – Trends in Design & Construction of Mechanized Tunnels, Taipei, vol. 1. Chinese Taipei Tunnelling Association, pp. 1–36.
Tunnelling, International Lecture Series TBM Tunnelling Trends, Hagenberg, Pliego, J.M., 2005. Open Session – The Gibraltar Strait Tunnel. An overview of the
A.A. Balkema, Rotterdam, Brookfield, pp. 43–53. study process. Tunnelling and Underground Space Technology 20 (6), 558–569.
Gehring, K., Kogler, P., 1997. Mechanized tunnelling: where it stands and where it Prader, D., 1972. Beispiele von Druckerscheinungen im Tunnelbau. In:
has to proceed from a manufacturers view point. In: Tunnels for People, ITA Internationales Symposium für Untertagbau, Luzern, Schweizerische
World Tunnel Congress ’97, Vienna, vol. 2. A.A. Balkema, Rotterdam, Brookfield, Gesellschaft für Boden– und Felsmechanik Zürich, pp. 82–98.
pp. 651–664. Ramoni, M., Anagnostou, G., 2007a. The effect of advance rate on shield loading in
Gollegger, J., Priller, A., Rausch, M., 2009. The use of open tunnel boring machines in squeezing ground. In: Underground Space – The 4th Dimension of Metropolises,
squeezing rock in the Gotthard Base Tunnel. Geomechanics and Tunnelling 2 ITA World Tunnel Congress 2007, Prague, vol. 1. Taylor & Francis Group, London,
(5), 591–600. pp. 673–677.
Grandori, R., 1996. La TBM universale alle soglie del 2000 – Aspetti tecnici ed Ramoni, M., Anagnostou, G., 2007b. Numerical analysis of the development of
imprenditoriali. Gallerie e grandi opere sotterranee 28 (50), 38–48. squeezing pressure during TBM standstills. In: The Second Half Century of Rock
Grandori, R., 2001. Manila Aqueduct (Philippines) – The construction of the Mechanics, 11th Congress of the International Society for Rock Mechanics
Umiray – Angat Tunnel Project – A success of organisation and technology (ISRM), Lisbon, vol. 2. Taylor & Francis Group, London, pp. 963–966.
against a unique combination of the most adverse conditions ever encountered Ramoni, M., Anagnostou, G., 2009. Experiences and basic considerations on TBM
in tunnelling. In: Rapid Excavation and Tunnelling Conference, San Diego, SME tunnelling in squeezing ground. Research Project FGU 2007/005, Report 090201
Inc. Littleton, pp. 777–790. (Revision B) of the Institute of Geotechnical Engineering (IGT) of the ETH Zurich
Grandori, R., Antonini, F., 1994. Double shield TBM excavation technique – Recent to the Swiss Federal Roads Office (FEDRO).
experiences and future development. Felsbau 12 (6), 490–494. Rehm, U., 2005. Herrenknecht AG (Personal Communication, May 2005).
Grandori, R., Jäger, M., Antonini, F., Vigl, L., 1995. Evinos–Mornos Tunnel – Greece. Robbins, R.J., 1982. The application of tunnel boring machines to bad rock
Construction of a 30 km long hydraulic tunnel in less than three years under the conditions. In: Rock Mechanics: Caverns and Pressure Shafts, ISRM
most adverse geological conditions. In: Rapid Excavation and Tunnelling Symposium, Aachen, vol. 2. A.A. Balkema, Rotterdam, pp. 827–836.
Conference, San Francisco, SME Inc. Littleton, pp. 747–767. Robbins, R.J., 1992. Large diameter hard rock boring machines: state of the art and
Graziani, A., Capata, A., Romualdi, P., 2007. Analysis of rock-TBM-lining interaction development in view of alpine base tunnels. Felsbau 10 (2), 56–62.
in squeezing rock. Felsbau Magazin 25 (6), 23–31. Robbins, R.J., 1997. Hard rock tunnelling machines for squeezing rock conditions:
Gütter, W., 2007. Weiterentwicklung einer 10-m-Doppelschild-TBM für stark three machine concepts. In: Tunnels for People, ITA World Tunnel Congress ’97,
druckhaftes Gebirge. Felsbau Magazin 25 (6), 32–37. Vienna, vol. 2. A.A. Balkema, Rotterdam, Brookfield, pp. 633–638.
Hentschel, H. 1997. Breakthrough at the vereina tunnel. Tunnel 4/97, 10-22. Schmid, L.R., 2006. TBM-Vortrieb im Fels – Möglichkeiten und Grenzen. Geotechnik
Hoek, E., 2001. Big tunnels in bad rock. Journal of Geotechnical and 29 (2), 194–198.
Geoenvironmental Engineering 127 (9), 726–740. Schmid, L., 2008. SMH Tunnelbau AG (Personal communication, March 2008).
ITA, 2003. Long traffic tunnels at great depth. In: ITA Working Group N° 17 – Long Schneider, W., Kapeller, E., 1995. Überbohrsystem – Praktische Erfahrungen. In:
Tunnels at Great Depth, ITA Lausanne. TBM know-how zum Projekt NEAT, The Robbins Company Symposium, Luzern,
Iwasaki, T., Miura, K., Kawakita, M., Yamada, T., Sano, N., 1999. A long tunnel project The Robbins Company Kent.
by TBM method. In: Challenges for the 21st Century, ITA World Tunnel Congress Schneider, E., Spiegl, M., 2008. Convergency compatible support systems. Tunnels &
’99, Oslo, vol. 2. A.A. Balkema, Rotterdam, Brookfield, pp. 857–863. Tunnelling International, June 2008, pp. 40–43.
John, M., Schneider, E., 2007. TBM tunnelling in squeezing rock. Felsbau Magazin 25 Schneider, E., Spiegl, M., 2009. SSP BauConsult GmbH (Personal Communication,
(6), 12. May 2009).
Korbin, G.E., 1998. Claims and tunnel boring machines: contributing factors and Schneider, E., Rotter, K., Saxer, A., Röck, R., 2005. Compex support system. Felsbau
lessons learned. In: Engineering Geology – A Global View from the Pacific Rim, 23 (5), 95–101.
8th International Congress of the International Association for Engineering Schneider, E., Home, L., Sänger, B., Kolb, S. 2007. Innovative concept for constructing
Geology and the Environment (IAEG), Vancouver, vol. 5. A.A. Balkema, the Brenner Base Tunnel with previously produced exploratory tunnel. Tunnel
Rotterdam, Brookfield, pp. 3523–3528. 1/2007, 21-33.
Kovári, K. 1986a. Rock deformation problems when using full-facing cutting Schubert, W., 2000. TBM excavation of tunnels in squeezing rock. In: Lo scavo
equipment in rock, part 1. Tunnel 3/86, 236-244. meccanizzato delle gallerie, mir2000 – VIII ciclo di conferenze di meccanica e
Kovári, K. 1986b. Rock deformation problems when using full-facing cutting ingegneria delle rocce, Torino, Pàtron Editore Bologna, pp. 355–364.
equipment in rock, part 2. Tunnel 4/86, 289-298. Shimaya, S., 2005. 12.84m-diameter TBM bores a 10.7 km-long tunnel at great
Kovári, K., 1995. The two Base Tunnels of the Alptransit Project: Lötschberg and depth. In: International Symposium on Design, Construction and Operation of
Gotthard. In: Worldwide innovations in tunnelling, STUVA-Tagung ’95, Long Tunnels, Taipei, vol. 1. Chinese Taipei Tunnelling Association, pp. 159–166.
M. Ramoni, G. Anagnostou / Tunnelling and Underground Space Technology 25 (2010) 139–157 157

Stahn, C., Grimm, K., 2006. Der Wienerwaldtunnel – Eine tunnelbautechnische Vicenzi, I., Pedrazzini, S., Ferrari, A., Gubler, G., Böckli, O., 2007. Deep tunnelling in
Herausforderung. Geotechnik 29 (2), 167–172. hardrock with large diameter TBM: what’s up? An Experience from the
Steiner, W., 2000. TBM tunnelling – Geotechnics influencing mechanics. Felsbau 18 Gotthard Base Tunnel. In: Underground Space – The 4th Dimension of
(2), 28–34. Metropolises, ITA World Tunnel Congress 2007, Prague, vol. 1. Taylor &
Sterpi, D., Gioda, G., 2007. Ground pressure and convergence for TBM driven tunnels Francis Group, London, pp. 267–272.
in visco-plastic rocks. In: ECCOMAS Thematic Conference on Computational Vigl, A., 2003. TBM support in squeezing rock – A convergence-compatible
Methods in Tunnelling, EURO:TUN 2007, Vienna University of Technology p.89. segmental lining system. Felsbau 21 (6), 14–18.
Strohhäusl, S., 1996. TBM tunnelling under high overburden with yielding Vigl, L., Jäger, M., 1997. Double shield TBM and open TBM in squeezing rock – A
segmental linings; Eureka Project EU 1979 – ‘‘Contun”. Tunnel boring comparison. In: Tunnels for People, ITA World Tunnel Congress ’97, Vienna, vol.
machines – Trends in design & construction of mechanized tunnelling, 2. A.A. Balkema, Rotterdam, Brookfield, pp. 639–643.
International lecture series TBM tunnelling trends, Hagenberg, A.A. Balkema, Voerckel, M., 2001. Tunnelling with TBM – State of the art and future development.
Rotterdam, Brookfield, pp. 61–68. In: Progress in Tunnelling after 2000, ITA World Tunnel Congress 2001, Milan,
Terada, M., Moriyama, M., Yamazaki, T., 2008: 12.84 m diameter TBM excavated the vol. 2. Pàtron Editore Bologna, pp. 493–500.
long expressway tunnel with 1000 m overburden. In: Underground Facilities for Wittke-Schmitt, B., Gattermann, J., Wittke, W., 2005. Risiken bei konventionellen
Better Environment & Safety, ITA World Tunnel Congress 2008, Agra, vol. 2. und maschinellen Vortrieben sowie Massnahmen zur Minimierung. In:
Central Board of Irrigation & Power New Delhi, pp. 1098–1106. Taschenbuch für den Tunnelbau 2006, VGE Verlag Glückauf GmbH Essen, pp.
Toolanen, B., Hartwig, S., Janzon, H., 1993. Design considerations for large hard rock 49–92.
TBMs when used in bad ground. In: Rapid Excavation and Tunnelling Wolff, W., Goliasch, R., 2003. Überschneideinrichtungen auf Hartgesteins-TBM –
Conference, Boston, SME Inc. Littleton, pp. 853–868. Kritische Betrachtungen anhand der Erfahrungen vom Lötschberg Basistunnel.
Tusch, K.N., Thompson, J.F.K., 1996. Method of connection. US Patent 5489164. Felsbau 21 (5), 147–154.

You might also like