Professional Documents
Culture Documents
PROGRAMME
Submitted
by
Kumar Ram
(Roll no.: 922MN5001)
Geological formation and geometry of such formation: percentage of the RPM (Rotation
outcrop of each component type on the mixed face, size and distribution of per minute)
the cobblestone, blocks or spheroidal weathering stone, occurring
discontinuities
2. Literature Review
2.1 TBM tunneling in mixed ground conditions
The performance of TBM tunneling directly related to the excavation process by TBM cutters
and excavation efficiency are related to the soil/rock mass properties (Barton 2000; Barla and
Pelizza 2000; Arıog˘lu et al. 2002; Laughton 2005; Shahriar et al. 2008; Zhao and Gong 2006;
Zhao et al. 2007). The key issue for tunnel excavation by TBM is to match the mechanical
parameters of the grounds and the operational parameters of the machines. An attempt is made to
visualize unfavorable/mixed/adverse ground conditions considering:
The mixed-face ground conditions can be generally classified into following three categories:
(i) Layered or banded ground formed by sedimentary beddings, dykes, faults or shear
zones.
(ii) Interface ground of soil and rock, typically weathered materials above bedrocks.
(iii) Mixed face with cobbles or core stones surrounded by soils or soft formation.
(a) Hard and fresh granitic gneissic rock face (b) Completely weathered granitic gneissic (c) Interface ground of fresh granitic gneissic rock
and soil face
(a) Sinkhole at portal of Tunnel (b) Sinkhole on the road in Tunnel alignment
(c) Flat Wearing (d) Broken cutter discus (e) Mushroom shaped (e) Hub damages
3.0Field Study
Phase-2 of Bangalore Metro Rail Project consists of four extensions to the existing lines and two
new lines with a total length of 72.095 km and 61 stations, in which 12 are underground. Phase-2
includes the extension of the two Phase-1 corridors, as well as the construction of two new lines.
One of the new line is 21.25 km Gottigere – Nagawara line (Fig. 4). The line is mostly
underground (13.79 km), but also has a 6.98 km elevated and 0.48 km at-grade sections and all
21.25 km stretches divided into four packages, known as RT-01, RT-02, RT-03 and RT-04
(BMRCL/Phase-2/Reach-6/UG/TNL&STN/(R6-CC-02)-RT 03/2018/38 Dated 26.6.2018).
Figure 4. Tunnel alinement map -Shivajinagar to Cantonment
One of the Package (RT-03) starts at approx. Ch. 13938.328m at Shivaji Nagar Station and ends
Ch. 16822.521m at Tannery Road station. It covers approximately 2.884 km of bored
underground tunneling work and tunnel depth ranges from 10 to 16 meter below the ground level
in dense populated area.
The detailed geotechnical investigation was carried out in this package before starting the TBM
mining, and it shows mixed geological condition across the entire stretches of this project area
(Fig. 5 and Table 2).
The main strata in tunnel alinement is granitic gneiss. The granitic gneisses are mainly of
migmattitic type, highly banded varying in composition from granite to diorite and having
several degree of weathering.
The strata in tunnel alignment area is considered as five levels; residual soil, completely
weathered (W5), highly weathering (W4), and moderately weathered (W3) slightly weathering
(W2) and fresh rock (W1) (IS code: 4464-1985)
In general, it is the soil stratum consisting of 1 to 4 m of filled up soil below the existing ground
level followed by a mixture of silt and clay of low plasticity or clay or silty sand extending to
depth from 4 to 24 m by rock stratum. Rock level is varying all along the alignment of entire
package and the water table varies from 1 to 18 m below the ground level.
The stratigraphy of the entire package is generally classified into four sub-divisions: -
1. Filled up soil
2. Residual soil
a) Clay or silt of Low to Intermediate Plasticity
b) Clayey-Silt sand or Clayey sand
c) Very dense silty sand or Soft rock
3. Highly Weathered granitic gneissic rock
4. Moderately weathered to fresh hard granitic gneissic rock.
Section 1-1
Section 1-2
Figure 5. Geological longitudinal profile along Section 1 -1 and Section 1 -2. Cant to
Shivajinagar.
Table 2 Geological profile tunnel sections Shivajinagar and Cantonment station
In Bangalore metro phase-2 projects, instruments mounted or operated (Table 3) from the
surface of the ground or inside the tunnel are used to measure deformation. Instruments located
on the ground surface can be installed prior to tunnel excavation in the desired area. As a result,
their proper operation can be confirmed, and numerous zero-load measurements can be
conducted to validate their level of accuracy (by the variance of the zero-load readings). The
tunnel face (from approximately one tunnel diameter front of the face to approximately 1.5
diameters) is where the majority of earth deformation occurs. As a result, monitoring devices put
on the tunnel wall (e.g., optical reflector targets) or in the ground (e.g., borehole rod
extensometers) should be installed as soon as feasible. Unfortunately, the minimum distance of
instrument placement from the tunnel face is 2-4 meters due to inevitable interference.
Name of Instrument Installation Purpose of Instrumentation
location
Ground Settlement Marker Surface Measuring vertical (up/down) movement
Building Settlement Building/Structure Measuring building movement in up and
Marker down direction
Extensometers Surface Vertical convergence of rock/soil at
different depth
Inclinometers Surface Lateral ground movement
Survey Targets(BRT) Structure Movement of structures
Tilt Meters Building/Structure Tilting of structure in Incline direction
Piezometers Surface Measure groundwater levels or pressures
Table 3 Instrument installation position and their purpose to monitor deformation during the
Tunneling -
0 CMRS-PTYT-
SETTLE-
-5 GSM64
-10 CMRS-PTYT-
GSM65
-15
Alert
-20
Action
-25 Alarm
-30
15-Jan-22
25-Jan-22
4-Feb-22
14-Feb-22
24-Feb-22
6-Mar-22
5-Apr-22
5-May-22
15-May-22
25-May-22
14-Jun-22
24-Jun-22
14-Jul-22
24-Jul-22
3-Aug-22
13-Aug-22
23-Aug-22
2-Sep-22
12-Sep-22
22-Sep-22
12-Oct-22
22-Oct-22
1-Nov-22
11-Nov-22
21-Nov-22
1-Dec-22
11-Dec-22
5-Jan-22
16-Mar-22
26-Mar-22
15-Apr-22
25-Apr-22
4-Jun-22
4-Jul-22
2-Oct-22
DATE
-10 BS398
UL303-
TLE-
SET-
-20 BS399
m)
-30 UL303-
BS400
-40 Alert
Action
4-Apr-22
2-May-22
16-May-22
30-May-22
13-Jun-22
27-Jun-22
11-Jul-22
25-Jul-22
8-Aug-22
22-Aug-22
5-Sep-22
19-Sep-22
17-Oct-22
31-Oct-22
14-Nov-22
28-Nov-22
12-Dec-22
26-Dec-22
18-Apr-22
3-Oct-22
DATE
While executing the mining operations for Ring No 97 at cutter head chainage
14649.662(Figure-10), a sink hole was observed with maximum approx. dimensions as 3 Rmt
Length ,1.8 m Width and 1.5m Depth. The location of sinkhole was 1.243 Rmt behind the cutter
head location observed on Sultanti Gunta Road.
After formation of sinkhole, cavities was filled with M5 grade of lean concreate and sand, then
after filling of cavities, Dynamic Cone Penetration Test using for assessment of disturb or
unstable subsurface soil zone. Dynamic Cone Penetration Test is simple machine for probing the
soil strata. DCPT result consist of number of blow count with respect to penetration depth to
obtain qualitative and quantitative data on the soil resistance to penetration and in particular to
determine the compactness of soil shown in fig.12 (Stefanoff et al. 1988).
After Assessment of disturb zone, the ground improvement work was carried out. Ground
improvement technique considered is a permeation grouting technique wherein chemical grout is
injected in the soil stratum to improve its strength and minimize the seepage and air loss. The
chemical grout was prepared by mixing of sodium silicate with cement grout (grout ratio 3:1).
The mixture of grout was forming gel from 6 minutes to 7 minutes. The approximate mix
proportion for making gel will be 1:1 for sodium silicate to cement grout. The 40% sodium
silicate was diluted in 60% water.
Grout holes G1 to G13 (figure-8) designed around the unstable area/sinkhole. In this holes TAM
pipe (50 mm dia. 10-bar pressure) installed using ROC drilling machine up to the depth of 8 to 9
meter side of the TBM and 16 mts infront of TBM face(figure no-10). The diameter of the hole
is 89 mm. After installation of, 50 mm dia TAM grout pipes primary grout filled in surrounding
of the pipe with water to cement ratio of 3:1. The grouting was be carried out by two TW-7 grout
pumps with pressure up to six bar pressure. The OPC grade-53 with 40% sodium silicate
suspension used for the grouting. In parallel to the grouting operation, the cutter head chamber of
the TBM was filled with bentonite slurry and cutter head regularly rotated along with slight
sliding of shields so that shield does not get struck due to grouting. After completion of grouting
work, tunneling excavation was resumed.
Figure 9. Grout hole location (G1 to G13) and DCPT blow compression graph of pre and post
grouting
Immediate settlement in residential area lead to major accident and life loss. To avoid this major
accident and life loss, following measures taken during TBM tunneling-
4.0 Conclusion
TBM tunneling in mixed geological conditions presents a challenge for tunnel construction,
because no single TBM tunneling method is suitable for all mixed geological conditions. For a
long tunnel section, the geological conditions are varying. The geological information obtained
during the tunnel investigation stage is limited. The related TBM design based on the geological
information cannot solve all the uncertain problems to be encounter during TBM tunneling
However, the goal is always to achieve highly efficient and safe TBM tunneling. TBM tunneling
involves three specific processes, i) excavation at tunnel face, ii) the movement of machine
through gripping the rock wall, and iii) stability and support of the tunnel opening. Therefore,
further research related to effective and safe TBM tunneling under mixed geological conditions
must be address-
III) To be Developed Vibration control measures during the TBM operation and reduces the
damages of surficial infrastructure/building.
IV) Enhancing Ground improvement technique before the tunneling to control the settlement.
References.
Barla, G., Pelizza, S., 2000. TBM tunnelling in difficult ground conditions. In: GeoEng2000 –
An International Conference on Geotechnical & Geological Engineering. Melbourne,
Australia, p. 20.
Barton NR, Lien R, Lunde J (1974) Engineering classification of rock masses for the design of
tunnel support. Rock Mech Rock Eng 6(4):189–236
Bosse Marc, C., 2005. Performance of EPB-TBM in Mixed Face Conditions. City of Edmonton
South LRT Extension: University Station to Health Sciences Station. University of
Alberta, Canada, p. 234.
Büchi, E.T., 1992. New TBM generation with 20” cutters – tunnelling experience at Klippen
Hydropower Sweden. In: TBM Symposium – Lucia 1992, Atlas Copco Stockholm,
BeFo Stiftelsen Bergteknisk Forskning, BK Bergsprengningskommiten, and Stockholm.
Dudt, J.P., Delisio, A., 2016. The, ‘‘penalty factors” method for the prediction of TBM
performances in changing grounds. Original Research Article. Tunn. Undergr. Space
Technol. 57, 195–200.
Krulc MA, Murray JJ, McRae MT, Schuler KL. Construction of a mixed face reach through
granitic rocks and conglomerate. In: Proceedings of the rapid excavation and tunneling
conference, Toronto; 2007. p. 928–42.
Liu XY. Causes for wearing of disc cutters of shield machines in mixed ground and
countermeasures. Tunnel Constr 2006;26(Supp. 2):77–80.
Liu LY. On the construction of TBM through the granite globular weathering body. Guangdong
Sci. Technol. 2010;19(4):180–2.
Luo S, ZhangH R. Discussion on prevention and control of delayed settlement induced by shield
tunneling in water-rich sandy cobble stratum in Chengdu. Tunnel Constr 2010;3:317–9.
Marinos PG, Novack M, Benissi M, Stoumpos G, Papouli D, Panteliadou M, Marinos V,
Boronkay K, Korkaris K. Assessment of ground conditions with respect to mechanized
tunnelling for the construction of the extension of the Athens Metro to the city of
Piraeus. Bull Eng Geol Environ 2009; 68:17–26.
Osborne NH, Knight Hassell K, Tan LC, Wong RA. Review of the performance of the tunneling
for Singapore’s circle line project. In: World tunnel congress 2008-underground facilities
for better environment and safety, India; 2008. p. 1497–508.
Shahriar K, Sharifzadeh M, Hamidi JK (2008) Geotechnical risk assessment based approach for
rock TBM selection in difficult ground conditions. Tunn Undergr Space Technol
23(3):318–325
Schwarz H, Bote R, Gens A. Construction of a new metro line in Barcelona: design criteria,
excavation and monitoring system. In: Proceedings of the 5th international symposium
TC28, Amsterdam; 2005. p. 757–63.
Steingrimsson JH, Grøv E, Nilsen B. The significance of mixed-face conditions for TBM
performance. World Tunnell 2002;15(9):435–41.
Zhao J, Gong QM, Eisensten Z. Tunnelling through a frequently changing and mixed ground: a
case history in Singapore. Tunn Undergr Space Technol 2007;22(4):388–400.
Zhang KZ, Yu HD, Liu ZP, Xinmin Lai XM. Dynamic characteristic analysis of TBM
tunnelling in mixed-face conditions. Simul Model Pract Theory 2010;18:1019–31
Zhu WB, Ju SJ. Mix ground and shield tunneling technology in Guangzhou. In: Proceedings of
2005 Shanghai international forum on tunnelling, Shanghai; 2005. p. 165–73.
1. Uneven Cutting Forces: The contrasting properties of different ground types in mixed-
face conditions can lead to uneven cutting forces on the TBM's cutterhead. This uneven
distribution can strain the TBM's mechanical components and reduce its overall cutting
efficiency.
2. Reduced Penetration Rates: Transitioning between hard and soft rock formations can
significantly impact the TBM's penetration rate. Hard rock formations can cause
excessive wear on the cutters, while soft ground can lead to excessive muck
accumulation, both hindering the TBM's advance.
3. Groundwater Infiltration: The presence of groundwater in mixed-face conditions can
introduce additional challenges, such as ground instability, water ingress into the tunnel,
and potential damage to the TBM's electrical components.