DAFTAR ANALISA HARGA SATUAN

A.2.3.1.4 Penggalian 1 M3 Tanah Keras sedalam 1 m


1.000 OH Pekerja Rp. 79,000.00 Rp. 79,000.00
0.032 OH Mandor Rp. 118,000.00 Rp. 3,776.00
Jumlah Rp. 82,776.00
OH & Profit 10% Rp. 8,277.60
Total Rp. 91,053.60
Dibulatkan Rp. 91,053.00

A.2.3.1.9 Pengurugan kembali 1 M3 Galian


0.500 OH Pekerja Rp. 79,000.00 Rp. 39,500.00
0.050 OH Mandor Rp. 118,000.00 Rp. 5,900.00
Jumlah Rp. 45,400.00
OH & Profit 10% Rp. 4,540.00
Total Rp. 49,940.00
Dibulatkan Rp. 49,940.00

A.4.4.2.2 1 M2 Plesteran 1Pc : 2Ps, Tebal 15 mm


10.224 Kg Semen Portland Rp. 1,475.00 Rp. 15,080.40
0.020 M3 Pasir Pasang Rp. 135,000.00 Rp. 2,700.00
0.300 OH Pekerja Rp. 79,000.00 Rp. 23,700.00
0.150 OH Tukang Batu Rp. 122,000.00 Rp. 18,300.00
0.015 OH Kepala Tukang Rp. 138,000.00 Rp. 2,070.00
0.015 OH Mandor Rp. 118,000.00 Rp. 1,770.00
Jumlah Rp. 63,620.40
OH & Profit 10% Rp. 6,362.04
Total Rp. 69,982.44
Dibulatkan Rp. 69,982.00

A.4.4.2.4 1 M2 Plesteran 1Pc : 4Ps, Tebal 15 mm


6.240 Kg Semen Portland Rp. 1,475.00 Rp. 9,204.00
0.024 M3 Pasir Pasang Rp. 135,000.00 Rp. 3,240.00
0.300 OH Pekerja Rp. 79,000.00 Rp. 23,700.00
0.150 OH Tukang Batu Rp. 122,000.00 Rp. 18,300.00
0.015 OH Kepala Tukang Rp. 138,000.00 Rp. 2,070.00
0.015 OH Mandor Rp. 118,000.00 Rp. 1,770.00
Jumlah Rp. 58,284.00
OH & Profit 10% Rp. 5,828.40
Total Rp. 64,112.40
Dibulatkan Rp. 64,112.00

A.4.6.1.15 1 M3 Pasang Konstruksi Kuda-Kuda Kayu


1.100 M3 Kayu Kelas II Rp. 6,260,000.00 Rp. 6,886,000.00
15.000 Kg Besi Strip Rp. 20,000.00 Rp. 300,000.00
0.800 Kg Paku biasa 2" - 5" Rp. 17,000.00 Rp. 13,600.00
4.000 OH Pekerja Rp. 79,000.00 Rp. 316,000.00
12.000 OH Tukang Kayu Rp. 122,000.00 Rp. 1,464,000.00
1.200 OH Kepala Tukang Rp. 138,000.00 Rp. 165,600.00
0.200 OH Mandor Rp. 118,000.00 Rp. 23,600.00
Jumlah Rp. 9,168,800.00
OH & Profit 10% Rp. 916,880.00
Total Rp. 10,085,680.00
Dibulatkan Rp. 10,085,680.00

A.4.6.1.21 1 M' Pasang Lisplank uk. 2,5 x 25 cm


0.0108 M3 Papan Lisplang Rp. 6,260,000.00 Rp. 67,608.00
0.100 Kg Paku biasa 2" - 5" Rp. 17,000.00 Rp. 1,700.00
0.100 OH Pekerja Rp. 79,000.00 Rp. 7,900.00
0.200 OH Tukang Kayu Rp. 122,000.00 Rp. 24,400.00
0.020 OH Kepala Tukang Rp. 138,000.00 Rp. 2,760.00
0.005 OH Mandor Rp. 118,000.00 Rp. 590.00
Jumlah Rp. 104,958.00
OH & Profit 10% Rp. 10,495.80
Total Rp. 115,453.80
Dibulatkan Rp. 115,453.00
A.4.5.2.14 1 M2 Pasang Atap Spandeck 0,35 mm Cat Pabrik
1.050 M2 Atap Spandeck 0.35 mm Cat Pabrik Rp. 70,000.00 Rp. 73,500.00
0.200 Kg Paku Seng Ulir Rp. 30,000.00 Rp. 6,000.00
0.200 OH Pekerja Rp. 79,000.00 Rp. 15,800.00
0.100 OH Tukang Kayu Rp. 122,000.00 Rp. 12,200.00
0.010 OH Kepala Tukang Rp. 138,000.00 Rp. 1,380.00
0.001 OH Mandor Rp. 118,000.00 Rp. 118.00
Jumlah Rp. 108,998.00
OH & Profit 10% Rp. 10,899.80
Total Rp. 119,897.80
Dibulatkan Rp. 119,897.00

A.4.5.2.35 1 M' Bubungan/ Rabung Spandeck 0,35 mm Cat Pabrik Rangka


1.100 M' Bubungan Spandeck 0,35 mm Cat Pabrik Rp. 40,000.00 Rp. 44,000.00
0.050 Kg Paku Seng Ulir Rp. 30,000.00 Rp. 1,500.00
0.250 OH Pekerja Rp. 79,000.00 Rp. 19,750.00
0.150 OH Tukang Kayu Rp. 122,000.00 Rp. 18,300.00
0.015 OH Kepala Tukang Rp. 138,000.00 Rp. 2,070.00
0.013 OH Mandor Rp. 118,000.00 Rp. 1,534.00
Jumlah Rp. 87,154.00
OH & Profit 10% Rp. 8,715.40
Total Rp. 95,869.40
Dibulatkan Rp. 95,869.00

A.4.6.1.19 1 M2 Pemasangan Rangka Langit-langit (60 x 120 cm), Kayu Kelas II


0.0154 M3 Kaso-kaso 5 x 7 cm Rp. 6,260,000.00 Rp. 96,404.00
0.200 Kg Paku 7 cm - 10 cm Rp. 17,000.00 Rp. 3,400.00
0.150 OH Pekerja Rp. 79,000.00 Rp. 11,850.00
0.300 OH Tukang Kayu Rp. 122,000.00 Rp. 36,600.00
0.030 OH Kepala Tukang Rp. 138,000.00 Rp. 4,140.00
0.075 OH Mandor Rp. 118,000.00 Rp. 8,850.00
Jumlah Rp. 161,244.00
OH & Profit 10% Rp. 16,124.40
Total Rp. 177,368.40
Dibulatkan Rp. 177,368.00

A.4.5.1.5 1 M2 Pemasangan Langit-langit Triplek ukuran (120 x 240) cm, tebal 6 mm


0.3750 Lbr Triplek 6 mm Rp. 98,000.00 Rp. 36,750.00
0.030 Kg Paku Triplek Rp. 23,000.00 Rp. 690.00
0.100 OH Pekerja Rp. 79,000.00 Rp. 7,900.00
0.100 OH Tukang Kayu Rp. 122,000.00 Rp. 12,200.00
0.010 OH Kepala Tukang Rp. 138,000.00 Rp. 1,380.00
0.005 OH Mandor Rp. 118,000.00 Rp. 590.00
Jumlah Rp. 59,510.00
OH & Profit 10% Rp. 5,951.00
Total Rp. 65,461.00
Dibulatkan Rp. 65,461.00

A.4.7.1.4 1 M2 Pengecatan Bidang Kayu Baru (setara Avian)


(1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
0.200 Kg Cat Menie Rp. 43,000.00 Rp. 8,600.00
0.150 Kg Plamir Rp. 20,000.00 Rp. 3,000.00
0.170 Kg Cat Kayu Dasar Rp. 54,000.00 Rp. 9,180.00
0.260 Kg Cat penutup 2 x (setara Avian) Rp. 72,000.00 Rp. 18,720.00
0.010 Bh Kuas Rp. 22,000.00 Rp. 220.00
0.030 Kg Pengencer/Tiner Rp. 250,000.00 Rp. 7,500.00
0.200 Lbr Amplas Rp. 3,500.00 Rp. 700.00
0.070 OH Pekerja Rp. 79,000.00 Rp. 5,530.00
0.009 OH Tukang Kayu Rp. 122,000.00 Rp. 1,098.00
0.006 OH Kepala Tukang Rp. 138,000.00 Rp. 828.00
0.0030 OH Mandor Rp. 118,000.00 Rp. 354.00
Jumlah Rp. 55,730.00
OH & Profit 10% Rp. 5,573.00
Total Rp. 61,303.00
Dibulatkan Rp. 61,303.00
A.4.7.1.10 1 M2 Pengecatan Tembok Baru Dulux Weathershield
(1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
0.1000 Kg Plamir Rp. 20,000.00 Rp. 2,000.00
0.1000 Kg Cat Tembok Dasar Dulux Weathershield Rp. 68,000.00 Rp. 6,800.00
0.2600 Kg Cat penutup 2 x Dulux Weathershield Rp. 95,000.00 Rp. 24,700.00
0.0200 OH Pekerja Rp. 79,000.00 Rp. 1,580.00
0.0630 OH Tukang Cat Rp. 122,000.00 Rp. 7,686.00
0.0063 OH Kepala Tukang Rp. 138,000.00 Rp. 869.40
0.0030 OH Mandor Rp. 118,000.00 Rp. 354.00
Jumlah Rp. 43,989.40
OH & Profit 10% Rp. 4,398.94
Total Rp. 48,388.34
Dibulatkan Rp. 48,388.00

A.4.7.1.11 1 M2 Pengecatan Tembok Lama Dulux Weathershield


(1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
0.1200 Kg Cat Tembok Dasar Dulux Weathershield Rp. 70,000.00 Rp. 8,400.00
0.1800 Kg Cat penutup 2 x Dulux Weathershield Rp. 130,000.00 Rp. 23,400.00
0.0280 OH Pekerja Rp. 79,000.00 Rp. 2,212.00
0.0420 OH Tukang Cat Rp. 122,000.00 Rp. 5,124.00
0.0042 OH Kepala Tukang Rp. 138,000.00 Rp. 579.60
0.0030 OH Mandor Rp. 118,000.00 Rp. 354.00
Jumlah Rp. 40,069.60
OH & Profit 10% Rp. 4,006.96
Total Rp. 44,076.56
Dibulatkan Rp. 44,076.00