Professional Documents
Culture Documents
Analisa Unit Price 2
Analisa Unit Price 2
NO URAIAN PEKERJAAN VOL. SAT. KOEF. HARGA SAT. BAHAN UPAH TOTAL HARGA
1 2 3 4 5 6 7 8
1 1 m3 Beton K-300
Bahan
Beton readymix K-300 1.000 m3 1.100 Rp 895,000 Rp 984,500.00 Rp 984,500.00
Alat bantu 0.055 % 1.000 Rp 984,500 Rp 54,147.50 Rp 54,147.50
Tenaga
Pekerja 1.000 oh 1.650 Rp 130,000 Rp 214,500.00 Rp 214,500.00
Tukang batu 1.000 oh 0.275 Rp 165,000 Rp 45,375.00 Rp 45,375.00
Kepala Tukang 1.000 oh 0.028 Rp 185,000 Rp 5,180.00 Rp 5,180.00
Mandor 1.000 oh 0.083 Rp 225,000 Rp 18,675.00 Rp 18,675.00
Jumlah Rp 1,038,647.50 Rp 283,730.00 Rp 1,322,377.50
Pembulatan Rp 1,323,000.00
5 Pekerjaan Galian
Upah kerja
Tukang gali 1.000 OH 0.765 Rp 165,000 Rp 126,225.00 Rp 126,225.00
Mandor 1.000 OH 0.026 Rp 225,000 Rp 5,850.00 Rp 5,850.00
Alat bantu 1.000 oh 0.030 Rp 126,225 Rp 3,786.75 Rp 3,786.75
Jumlah Rp - Rp 135,861.75 Rp 135,861.75
Pembulatan Rp 136,000.00
NO URAIAN PEKERJAAN VOL. SAT. KOEF. HARGA SAT. BAHAN UPAH TOTAL HARGA
11 1 kg Pembesian wiremesh M8
Bahan
Wiremesh Dia. 8 mm 1.000 kg 10.200 Rp 11,700 Rp 119,340.00 Rp 119,340.00
###
kawat Beton 1.000 kg 0.050 Rp 35,000 Rp 1,750.00 Rp 1,750.00
Alat Bantu 0.030 % 0.030 Rp 121,090 Rp 108.98 Rp 108.98
Tenaga
Pekerja 1.000 oh 0.025 Rp 130,000 Rp 3,250.00 Rp 3,250.00
Tukang Besi 1.000 oh 0.025 Rp 165,000 Rp 4,125.00 Rp 4,125.00
Kepala Tukang 1.000 oh 0.025 Rp 185,000 Rp 4,625.00 Rp 4,625.00
Mandor 1.000 oh 0.001 Rp 225,000 Rp 225.00 Rp 225.00
Jumlah Rp 121,198.98 Rp 12,225.00 Rp 133,423.98
Pembulatan Per 10 Kg Rp 133,400.00
Pembulatan Per 1 Kg Rp 13,340.00
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN KETERANGAN
Rp.
1 2 3 4 5
II. B A H A N
A. BETON READY MIX
1 Beton Ready Mix B0 M³ 710,000.00
2 Beton Ready Mix K-175 M³ 760,000.00
3 Beton Ready Mix K-225 M³ 830,000.00
3 Beton Ready Mix K-300 M³ 910,000.00
B. BATU - BATUAN
1 Batu Kali
a Batu Bulat Utuh M³ 190,000.00
2 Kerikil
a Kerikil Beton M³ 205,000.00 100.49 per Kg
b Split M³ 240,000.00 117.65 per Kg
3 Pasir
a Pasir Pasang M³ 260,000.00 209.68 per Kg
b Pasir Beton M³ 260,000.00 209.68 per Kg
c Pasir Urug M³ 200,000.00
D. ATAP
a Rangka atap baja ringan M2 150,000.00
b Insulation M2 35,000.00
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN KETERANGAN
Rp.
1 2 3 4 5
c Atap karang pilang M2 95,000.00
d Lisplank GRC Btg 80,000.00 26,667 per m1
E. PLAFOND
a Plafond gypsum ex Jayaboard t = 9 mm + rangka M2 125,000.00 Terpasang
Plafond gypsum Water Resistan ex Jayaboard t = 9
b M2 140,000.00 Terpasang
mm + rangka
c Shadow line M1 25,000.00
d Lisplank GRC Btg 55,000.00 22,541 per m1
F. BAHAN KAYU
a ( Kelas II ) Balok M³ 1,900,000.00
b Kayu Bekisting : Papan M³ 1,600,000.00
c ( Kelas IV ) Balok M³ 1,800,000.00
d Kayu dolken Btg 12,000.00
e Plywood Vnol Film tebal 15 mm Lbr 250,000.00
G. BAHAN CAT
a Cat dasar ex. Mowilex Kg 27,500.00
b Cat finish Cendana ex. Mowilex Kg 468,181.82 18,727.27 per kg
c Cat finish eksterior ex. Mowilex (weathercoat) Kg 1,181,818.18 47,272.73 per kg
d Plamur Kg 3,400.00
e Alkali ex. Mowilex Kg 25,500.00
e Oil paint ex. Kansai Kg 57,500.00
e Thinner Kg 25,500.00
J. BAHAN PIPA
1 Pipa PVC Merk Pralon - 4 M
a PVC Dia 3/4" M' 9,375.00
b PVC Dia 2" M' 16,250.00
c PVC Dia 3" M' 30,000.00
d PVC Dia 4" M' 47,500.00
2 Pipa Galvanise - 6 M
a PVC Galvanise dia. 4" M' 62,500.00
1 2 3 4 5
1 Aluminium profil kusen 3" ex. Sakura Alexindo M1 170,000.00
2 Kaca Clear t = 6 mm ex. Asahimas M2 260,000.00
Kaca Clear t = 10 mm ex. Asahimas M2 410,000.00
Kaca Clear t = 12 mm ex. Asahimas M2 460,000.00
3 U runner 2 x 2 cm ex. YKK M1 19,000.00
4 Sealent M1 6,000.00
5 Rangka daun pintu profil aluminium ex. Sakura Alexindo M1 92,000.00
6 List aluminium rangka kaca daun pintu/jendela M1 20,000.00
7 Pull Handle SS Set 700,000.00 Pintu utama
8 Lever Handle (pintu kayu) Set 450,000.00 Pintu Kamar dan KM
9 Hinges SS Set 220,000.00 Pintu Kamar dan KM
10 Lockase Mortise (pintu kayu) Set 285,000.00 Pintu Kamar dan KM
11 Aluminium Lock KC 8128 Set 175,000.00 Pintu Aluminium
12 Floor Hinges SS Set 1,250,000.00
13 Flush Bolt Dekkson FB 508 NA Set 65,000.00
14 Rambuncis SS Set 28,500.00
15 Engsel Friction Stay SS Set 85,000.00
16 Kusen pintu oven m1 132,000.00
17 Daun pintu Engineering wood m2 750,000.00
18 Daun pintu plywood + Solid engineering m2 890,000.00
19 Daun pintu plywood + Honeycomb m2 950,000.00
20 Lapis formika m2 56,000.00
21 Cat duco m2 155,000.00