Infrastructure Design and Engineering Group Document EVGD/09/104/A2(a)
M&W for Civil & Structural Works. Sheet 55 of 57
11.22.2 Materials
11.22.2.1 Silica fume shall be used in combination with water reducing admixture
11.22.2.2
11.22.23
11.2.3
11.22.3.1
11.22.3.2
ly 2017
and/or superplasticiser. Silica fume shall conform to the chemical and
physical requirements as given in the table below.
Chemical and physical requirements | Characteristic value (By
(BS EN 13263-1) mass of dry silica fume)
Silicon dioxide — SiOz (%) >85
Elemental silicon - Si(%) <0.4
Free calcium oxide - CaO (%) <1.0
Sulfate — SOs (%) <2.0
Chloride content (CI) (%) <0.3
Loss on ignition (LO!) (%) <4.0
Specific surface (m%/gm) 15-35
Dry mass content in slurry (%) <#- 2.0
Activity index (%) Tested at a mortar | 100
age of 28 days
The concrete mix proportions shall be determined from the results of the
trial mix testing. When desired mix properties are achieved, specimens
shall be prepared, cured and tested at 28 days and 56 days to determine
acceptability of proposed mix proportions. All specimens shall meet the
compressive strength and water penetration requirement of maximum
15mm as tested to BS EN 12390-8. In addition, the specimens when
tested in accordance with ASTM C1202 shall be in the ‘Very Low’
permeability range as defined in that test standard.
The silica fume shall come from the same source throughout the project.
Ifa single primary source of silica fume cannot be maintained throughout
a project, the Contractor shall carry out all the necessary testing to
demonstrate to the satisfaction of the Engineer that the use of silica fume
shall comply with the chemical and physical requirements as specified in
the above table.
Silica Fume Testing Requirement and Quality Assurance
In addition to rate of sampling in Clause 11.8.2, samples shall also be
taken for every 100m! of silica fume concrete delivered to site. The
silica fume concrete shall meet the specified 28-day compressive
strength and maximum water penetration at 28 days of 15mm as tested
in accordance with BS EN 12390-8. In addition, the silica fume concrete
shall be tested in accordance with ASTM C1202 and the results shall be
within the ‘Very Low’ permeability range.
In the event that the tests show that the silica fume concrete do not meet
CONTRACT T316Infrastructure Design and Engineering Group Document EVGD/09/104/A2(a)
M&W for Ci
11.22.4
11.225
11.22.5.1
11.22.5.2
11.22.6
11.22.6.1
11.22.6.2
ly 2017
& Structural Works. Sheet 56 of 57
the performance requirements, the entire batch of materials where the
samples are taken shall be rejected and the Contractor shall submit
rectification proposal for the Engineer's acceptance,
Submis:
ns
The Contractor shall submit the following information to the Engineer for
his review and acceptance:
(a) Manufacturer's product data sheets for silica fume.
(b) Laboratory test reports, name and location of primary
manufacturing source of silica fume for use on the project.
(c) Silica fume concrete mix design and should include details of
grading of fine and coarse aggregates, proportions of all ingredients
including all admixtures, water/total cementitious materials ratio,
slump (consistence) and bulk density of silica fume concrete.
(4) Proposed procedures for placing, finishing and curing silica fume
concrete
(e) Proposed procedures for protecting silica fume concrete from
drying and plastic shrinkage cracking during the placing and
finishing process.
(f) Proposed procedures for protecting fresh silica fume concrete from
rain
Production, placing and compacting
Silica fume concrete shall be ready-mixed concrete batched, mixed and
transported in accordance with ASTM C94.
The sequence and method of charging the mixer with silica fume and
other ingredients shall be reviewed by the silica fume manufacturer's
representative.
Silica fume concrete shall be placed and compacted by any of the
currently available concreting techniques with the exception that it shall
be placed at the highest practical slump typically ranging from 150mm
to 225mm
Finishing, curing and protecting
Silica fume conerete can be finished by methods similar to those used
for finishing other concrete. The Contractor shall establish exact finishing
methods for the project by carrying out trial placements prior to
start of the actual work. These trials should be repeated until the best
methods for the project and its specified mixture proportions are
identified
The Contractor shall take protective measures to ensure that the newly
placed concrete does not dry out prior to and during the finishing
operations.
CONTRACT T316Infrastructure Design and Engineering Group Document EVGD/09/104/A2(a)
M&W for Civil & Structural Works Shoot 57 of 57
11.22.63 Curing shall begin immediately after the finishing process is completed.
11.23 SELF COMPACTING CONCRETE
11.231 The constituent materials for Self-Compacting Concrete (SCC) i.e.
cement, aggregates, water and admixtures shall be in accordance with
Clause 11.2.
11.23.2 The SCC shall have sufficient fluidity to achieve a dense cement matrix
without the need for additional compaction. The Contractor shall also
ensure that the tendency for the concrete to segregate is reduced by
using a viscosity modifying agent and/or reducing the amount of fines.
11.23.3 The Contractor shall submit the mix design of SCC together with
proposed locations where they will be used to the Engineer for approval
11.234 SCC shall be designed such that the workability of the product is
maintained. During placing of SCC, free fall height shall be limited to not
more than 5m and the horizontal distance from point of discharge shall
be not more than 10m apart to prevent segregation.
sty 2017
CONTRACT T316