METHODOLOGY FOR TESTING AND COMMISSIONING

ONE AYALA AVE PTP PROJECT

General

Sequence of Work

1. Jar test – to determine the dosing of the chemicals for treatment of wastewater.
2. Influent testing by Third Party Lab – to determine the influent characteristics if it
meets the design parameters. (to be done in parallel to Jar Test)
3. Operation of System – Operate the system with the actual waster being treated
with chemical dosing
4. Weekly Sampling/Internal Testing – While operating the system we will conduct
sampling for both influent and effluent once per week to be analyzed by third party
laboratory for ROLA be shown to Manila Water
5. Rectification for wiring and termination – this will be scheduled with our
technology partnet