You are on page 1of 2

CC Well cementing

1. Bottom plugs are :


a) Hollow
b) red or yellow
c) black
d) red

2. top plugs are :


a) solid and black
b) red
c) black
d) all the above

3. why do we cement ?
a) provide zonal abandon
b) well repair
c) protect casing for corrosion
d) all the above

4. conductor casing
a) establish returns to surface
b) not always required
c) prevent washout out uder rig
d) all the above

5. surface casing
a) protech fresh water sand
b) not always required
c) case consolidated formations
d) all the above

6. intermediate casing
a) high pressure zone
b) lost circulation
c) salt zone
d) all the above

7. production casing
a) complet the well for production
b) provide presure contrô le
c) well control when perforating
d) all the above

8. guide shoe
a) run on the top on the casing
b) with valve device
c) use to guide casing into the hole
d) all the above

9. Shoe track
a) Area between the shoe and collar
b) Top of cement sheet
c) Area between rat hole and the top of cement
d) All the above

10. Different type of cement head


a) Liner
b) subsea release
c) one plug, two plugs
d) all the above

11. pumpability time


a) it is the process to simulate pumping condition in order to determine a displacement
time before the cement becomes difficult or impossible to pump.
b) Measured by cistometer
c) Bearden units of consistency, Bc
d) All the above

12. Compatibility testing


a) Cement density >= spacer density> mud density
b) Spacer density > mud density > cement density
c) Mud density >= cement density >= spacer density
d) Cement density > mud density>= spacer density

13. Squeeze cement pumping :

a) Through perforations
b) Through imtended leaks
c) In casing hole
d) All the above

14. before cement slurry is pumped downhole, drilling mud from the rig pump is circulated
through the well to condition the mud and abandon the well.
a) False
b) True

15. The treating lines must be pressure tested to ensure that they can withstand the
pressures required during the cementing operation.
a) False
b) True

16. The spacer is a fluid. It role is keep the drilling mud and water separated during the
displacement process.
a) False
b) True

17. There are two kind of slurry, lead slurry and tail slurry.

a) False
b) True

18. Lead slurry is a higher density slurry for covering the upper part of the annulus.
a) False
b) true

19. Tail slurry is a low is density slurry for covering the shoe.
a) False
b) True

20. Poor or non-existing cement could allow salt water /oil to travel along the casing and
contaminate the fresh water bearing formation
a) False
b) true