Professional Documents
Culture Documents
) / Fifth Semester
Alternative Dispute Resolution (2022-23)
Notice for Arbitration
BETWEEN:
(CLAIMANT)
-AND-
(RESPONDENT)
Ashutosh Bansal
44-A Andheri West, Mumbai
0222-6117895
Counsel for Claimant 04 November, 2022
I. INTRODUCTION
ii. The Parties’ contractual relationship and the nature and circumstances of the
Parties’ dispute giving rise to Claimant’s claims (III);
iii. The dispute resolution clause, the proposed governing law, the seat and
language of the arbitration (IV);
iv. Claimant’s position as regards the composition of the Arbitral Tribunal (V);
3. This dispute principally concerns Claimant’s claim of the payment of the invoice of
rupees 3,00,000, retained fee of Rupees 8,00,000, payment of additional costs of
rupees 2,00,000 incurred by the Claimant between September and October 2015 due
to Respondent's failure to perform its contractual obligations in relation to the 1st
milestone and loss of profits in respect of the whole contract of rupees 20,00,000.
II. THE PARTIES [NOTE: SECTION 2(1)(h) of the Arbitration and Conciliation
Act,1996]
A. Claimant
6. Claimant’s counsel, to whom all correspondence should be sent in this arbitration, are:
Ashutosh Bansal
44-A Andheri West, Mumbai
0222-6117895
bansal.ashutosh@gmail.com
B. Respondent
9. On 15 September 2022, the parties entered into an agreement. Under the Agreement
Claimant undertook to provide various engineering consultancy services in accordance
with several pre-determined milestones specified in the Agreement, each priced at a
fixed sum, over two years for a total of Twenty Lac. On 28 September 2022, Claimant
delivered Layout plan (that was Milestone 1) which also included its best estimate of a
revised Budget. It also tendered an invoice for the work completed to date, pro-rated at
rupees 5,00,000. On 29 September 2022, Respondent sent the following email: "Thank
4
you for your message. We are reviewing it. Due to changes in government policy in
relation to our work, your company shall have to modify the plan. We shall get back to
you with our requirement within a week time.” Rupees 1,00,000 was received by
Claimant as initial amount from Respondent on 29 September, 2022. In the meantime,
the Claimant carried on working as best it could on the project and further sent several
chasing emails in October, 2022, all of which remained unanswered.
10. The claim is for the payment of the invoice of rupees 3,00,000, retained fee of Rupees
8,00,000, payment of additional costs of rupees 2,00,000 incurred between September
and October due to Respondent's failure to perform its contractual obligations in
relation to the 1st milestone and loss of profits in respect of the whole contract of
rupees 20,00,000.
11. As per the agreement between the parties, the respondent had to pay a fix amount
pertaining to various milestones, wherein Milestone 1 involved the delivery of a layout
plan and was priced at rupees 5,00,000 payable on delivery of the plan. The
Respondent failed to do so and hence breached the agreement.
5
English or Hindi.
16. Article 4 of the Agreement provides that committee of arbitrators shall consist of 3
(three) arbitrators appointed mutually by the Parties. Each Party shall appoint a
chairman. If the Arbitrators cannot agree on the appointment of the Chairman, then
the Chairman shall be appointed by the concerned authority under the applicable law
Ashutosh Bansal
44-A Andheri West, Mumbai
0222-6117895
bansal.ashutosh@gmail.com
18. Damages arising out of the default of payment of the invoice of rupees 3,00,000,
retained fee of Rupees 8,00,000 and demand of the payment of additional costs of
rupees 2,00,000 incurred by claimant between September and October due to
respondent's failure to perform its contractual obligations in relation to the 1st
milestone.
21. As a result, Claimant respectfully requests the Arbitral Tribunal to issue an award:
i. declaring that the Arbitral Tribunal has jurisdiction to consider the dispute
between the Parties described herein;
6
ii. ordering Respondent to compensate Claimant for the damages and losses
suffered as a result of Respondent’s breaches of the Contract, currently
estimated to be in the amount of Rs 13,00,000;
iv. ordering payment Respondent to pay interest rate of 6% on all of the above
amounts as of the date these amounts were due, until the date of their effective
payment.
22. For the avoidance of doubt, Claimant reserves its right to:
i. raise all further claims arising out of or in connection with the disputed matters
described in this Request or otherwise arising between the Parties; and
iv. seek interim and provisional measures before this Arbitral Tribunal or any
competent national court.
23. Pursuant to Section 38 of the Arbitration and Conciliation Act, 1996, Claimant is
sending an advance payment of Rs 30,000 with the Request for Arbitration. Claimant
acknowledges that this payment is non-refundable and shall be credited to its portion
of the advance on costs.
Respectfully submitted,
Ashutosh Bansal
44-A Andheri West, Mumbai
0222-6117895
bansal.ashutosh@gmail.com