IN THE NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI Consumer Case No. 1430 of 2017 Decided On: 23.07.2020 Appellants: Smita Uban and Ors. Vs. Respondent: Pioneer Urban Land & Infrastructure Ltd. Hon'ble Judges/Coram: R.K. Agrawal, J. (President) and Dr. S.M. Kantikar, Member Counsels: For Appellant/Petitioner/Plaintiff: Aditya Parolia, Advocate For Respondents/Defendant: T.V.S. Raghavendra Sreyas, Advocate ORDER R.K. Agrawal, J. (President) 1. This Consumer Complaint, under Section 21(a)(i) of the Consumer Protection Act, 1986 (for short "the Act"), has been filed by the Complainants against M/s. Pioneer Urban Land & Infrastructure Ltd. (hereinafter referred to as "the Developer"), seeking the following reliefs:- (a) to direct the Opposite Party to refund the entire amount of 3,22,18,954/- collected from the Complainants towards the consideration of the house along with interest @ 18% p.a. on the amount paid by them from the date of collection of the amounts till it is actually returned to the Complainants; (b) to direct the Opposite Party to pay a sum of 75,000/- (Rupees Seventy Five Thousand only) to the Complainants towards the cost of litigation; (c) Any other order(s) as may be deemed fit and appropriate may also kindly be passed; 2 . The brief facts as set out in the Complaint are that on 22.11.2011, the Complainants applied for a house in the Pioneer Group Housing Project called "Araya" to be developed by the Opposite Party Developer in Sector 62, Gurgaon, Haryana, by paying an booking amount of 30,00,000/-. The Apartment Buyer's Agreement was executed between the parties on 07.03.2012 and the Complainants were allotted Unit No. 1202 A, Floor 13, Tower C admeasuring super area of approx. 3498 Sq. Ft. in the said housing Project, for a total consideration of 3,45,22,779/-. The total sale consideration was to be paid as per Payment Plan given in the Buyer's Agreement. 3 . It is averred in the Compliant that as per Clause 11.2 of the Apartment Buyer's Agreement dated 07.03.2012, the Developer was under an obligation to make all efforts to apply for the Occupation Certificate of the proposed residential Project within thirty nine (39) months from the date of excavation i.e. by October 2015. The Developer was also entitled to a grace period of one hundred and eighty (180) days,
21-05-2021 (Page 1 of 10) www.manupatra.com Jamia Millia Islamia
after expiry of the said 39 months period for applying and obtaining the requisite Occupancy Certificate in respect of the said Housing Complex. The demand for the start of excavation was raised by the Opposite Party and was duly paid by the Complainants in June, 2012 and as such, the possession of the allotted Unit was to be handed over to the Complainants by October, 2015. 4. It is stated by the Complainants that they have regularly visited the site but they were utter surprised and shocked to see that the construction was never in progress. The entire site was seemed to be an abandoned piece of land with semi constructed structure. Even, no one was present on the site to address their queries about the completion of construction. According to them, till 16.12.2015 they had paid a sum of 3,22,18,954/- out of the total consideration of 3,45,22,779/- i.e. almost 95% of the total Consideration towards the cost of the apartment. However, the Developer has failed to deliver the possession of the Unit, complete in all respect, even after expiry of a long period of approx. five years despite repeated requests and remedies over letters, email, phone calls and personal visits. 5. It is further stated in the Complaint that the Complainants were forced to sign the one-sided Flat Buyer Agreement in the year 2012 on the dotted lines; as per Clause 11.5 of the Buyer's Agreement, the Developer has agreed to pay to the Complainants a compensation @10/- per sq. ft. per month for the period of delay in handing over possession. But, if it is calculated in terms of financial charges, it comes to approximate @1.4% p.a. rate of interest and even these charges are to be paid after 39 months which is period for completion of construction. This shows that the Developer has found a cheap source of funding the Commercial Projects from the hard earned savings of the Complainants. The Complainants have lost all faith in the Project of the Developer and they want refund of the deposited amount with interest and reasonable compensation. As per Clause 6.3 (ii) of the Buyer's Agreement, the Developer was charging interest @ 18% from the Purchasers for delay in payment of any of the instalments and as such on parity and equity they are liable to pay interest @18% p.a. on refund of the deposited amount. 6 . Hence, alleging deficiency in service on the part of the Developer in not completing the construction of the Project in time and not handing over the possession within the prescribed time as per Apartment Buyer's Agreement dated 07.03.2012, the Complainants filed the present Complaint seeking aforesaid reliefs. 7. Upon notice, the Complaint has been contested by the Opposite Party, Developer, by filing its Written Statement, raising preliminary objections that the real motive of instituting this Complaint by the Complainants is to seek more than the contractual benefits from the Developer and that the Complainants were expecting high speculative gains from the booked Unit, but failed due to depressed Real Estate market. 8 . On merits, it is contended that the time of 45 months (including grace period) from the date of excavation, to deliver the possession of the Unit, was tentative and the delay in handing over possession has been purely on account of Force Majeure factors which are as under:- (i) Delay in payments by many Customers:- The most important factor in the delay of the Project is that the Complainants have not adhered to the payment schedule and the Developer waived off the option to cancel the Agreement for non-payment; in terms of Clauses 5, 6 and 23 of the
21-05-2021 (Page 2 of 10) www.manupatra.com Jamia Millia Islamia
Agreement, the Developer was entitled to forfeit the earnest money or to cancel/terminate the agreement in case there was any fault on the part of the Complainants to fulfil the terms and conditions of the agreement, however, the Developer has not exercised this option in the interest of customers; (ii) Dispute with Contractors:- The contract to complete the construction of the towers (Structural and Finishing Works) within 30 months, was given to M/s. Urban Ecoinfra Pvt. Ltd. However, as the progress of the work was very slow, the contract was foreclosed and terminated when the Contractor had left behind half of the work. (iii) Labour and Water Shortage: There was also shortage of labour and water in the NCR Region which affected the construction directly. (iv) Lack of Infrastructural support from State Government:- Despite payment of External Development Charges, the State Government did not provide the basic amenities such as drinking water, sewerage, drainage including storm water line, road etc. in time. (v) Storage of Raw Material:- The Hon'ble Supreme Court vide order dated 08.05.2009, suspended all the mining operations in the Aravalli Hill range falling in the State of Haryana which led to a situation of scarcity of the sand and other raw materials for the construction. (vi) Delay in approvals by the State Government:- There was a substantial delay on the part of the Government Departments in granting approval/sanctions for which the Developer cannot be held solely responsible. (vi) Jat Reservation Agitation:- The Jat Reservation Agitation in February, 2016 paralyzed the Construction activities badly in the State of Haryana. The instant stoppage of work on the fear of riots and remobilization of work force took considerable time of 3-4 months. (vii) NGT Order:- In compliance with the order passed by the National Green Tribunal, all the development/construction activities were stopped by the Developer in April 2015 and November, 2016 due to emission of dust and unprecedented pollution. (viii) Demonetization of Rs. 500/- and Rs. 1000/- currency notes:- On 8th November, 2016, the Government of India demonetized the currency notes of Rs. 500/- and Rs. 1000/- due to which there was crunch of funds for the material and labour for 4 to 5 months. 9. It is further submitted that as the delay in completing the Project was due to the reasons beyond their control, the prayer by the Complainants for refund of the deposited amount is not tenable and even if, the Complainants are entitled for refund, they would not ask for interest for the time period between the last date of payment and date of filing of Complaint. It is strenuously stated that the parties are bound by the terms of contract and entitled to a compensation, if any, in terms of the contract only. Further, for refund and compensation, the Complainants have to adhere to the provisions made in Clause 11.5 of the Agreement. 10. All other averments made in the Complaint have been specifically denied by the
21-05-2021 (Page 3 of 10) www.manupatra.com Jamia Millia Islamia
Developer and prayed dismissal of the Complaint with exemplary costs. The Complainants filed their Rejoinder denying all the rival contentions raised by the Opposite Party in its Reply and reiterating the averments made in the Complaint. 1 1 . We have heard the Learned Counsel for the parties at some length and also perused the material available on record as well as the Written Arguments. 12. In brief, it is the Complainants' case that they booked the Unit No. 1202A, 13th Floor, Tower C admeasuring 3489 sq. ft. and the Apartment Buyer's Agreement with regard to the said Unit was executed between the parties on 07.03.12. In terms of Clause 11.2 of the Agreement, the Developer was committed to deliver the possession of the Apartment to the Complainants, complete in all respect, within 39 months from the date of excavation with grace period of 180 days. Admittedly, the excavation started on 04.06.2012. The construction, therefore, ought to have been completed and the Developer ought to have applied for Occupancy Certificate on or before 04.09.2015. However, till date, the possession of the booked Unit has not been offered by the Developer despite making 95% payment of the total consideration till December, 2015. 1 3 . In support of his case, Learned Counsel appearing for the Complainants has placed reliance on the decision dated 23.10.2018 rendered by a Coordinate Bench of this Commission in Consumer Complaint No. 238 of 2017 (Mrs. Geetu Gidwani Verma Vs. Pioneer Urban Land and Infrastructure Ltd. And Consumer Complaint Nos. 239 of 2017 (Mr. Govindan Raghavan Vs. Pioneer Urban Land and Infrastructure Ltd.) which relates to the same Project, i.e. "The Araya". We find that the defence taken by the Developer in the present Complainant is more or less similar to that taken in the abovesaid Consumer Complaints. While dealing with the similar reasons taken by the Developer for delay in handing over the possession in the afore referred Complaints, the Coordinate Bench of this Commission has observed as under:- "3. The complaints have been resisted by the OP which had admitted the allotment made to the complainants as well as the payment received from them. It is inter-alia stated in the written version filed by the OP that the construction could not be completed within the stipulated time on account of reasons beyond its control The said reasons, according to the OP, are as under: (a) The delay on the part of several flat buyers in making timely payment, (b) the dispute of the developer with the contractor, (c) shortage of water, (d) Lack of infrastructural support from the State Government, (e) Shortage of raw material, (f) Delay in approvals, (g) Jat reservation agitation, (h) NGT order stopping construction and (i) Demonetization of the currency. 4 . As far as the delay on the part of the several flat buyers is concerned, admittedly, the OP had a right to cancel the allotment due to the alleged non-payments. After cancelling the allotments made to the defaulting customers, the OP could have sold those flats in the open market to other willing buyers. Having not exercised the right available to it, to cancel the allotment on account of the alleged non- payment, the OP, in my view, cannot deny refund and compensation to the flat buyers who have been making payments in time or from whom interest for delay in payment has been charged. Therefore, I
21-05-2021 (Page 4 of 10) www.manupatra.com Jamia Millia Islamia
find no merit in the aforesaid ground. xxxxxx 6. As far as the alleged dispute with the contractor is concerned, the case of the OP is that initially, the work was awarded to M/s. Urban Eco Infra Pvt. Ltd. which did not maintain the assured timeline and therefore, the OP took over the construction work from the said contactor and awarded the same to another contractor M/s. Leighton Contractors Pvt. Ltd. In my view, the dispute if any, between OP and the contractor engaged by it, cannot justify the delay in completion of the construction. If the OP suffers any loss or has to pay compensation/damages on account of the delay committed by the contractor engaged by it, it will be entitled to avail such remedy as may be available to it in law against the contractor responsible for the delay, but it cannot deny refund and a fair compensation to a flat buyer who does not wish to wait any more for the possession of the alleged flat and wants refund of the money paid by him alongwith compensation. 7 . As far as the alleged water shortage and labour shortage is concerned, there is no evidence on record to prove that no water or labour was actually available in the market at the relevant time to carry out construction. The delay cannot be justified on such bald allegations without substantiating the same by hard evidence showing actual non-availability of water and labour in the market. 8 . As far as the alleged delay on the part of the Government agencies in laying infrastructure is concerned, there is no evidence of any particular timeline having been committed by such agencies to the developer for laying infrastructure and having not maintained the said timeline. As far as the alleged shortage of raw material is concerned, the case of the OP is that sand was not available in the vicinity of the complex due to restriction on mining imposed in Aravali region and therefore, they had to procure sand from the neighbouring city of Rajasthan. In its written version, the OP has referred to an order dated 08.05.2009 stated to have been passed by the Hon'ble Supreme Court stopping the mining operations in Aravali range. The agreement with the complainant having been executed much much later on 04.06.2012, the said order was already in the knowledge of the developer and therefore, it knew that it will have to procure sand from other places, on account of mining having been stopped in Aravali region. Therefore, shortage of sand in Aravali region cannot be a good ground for delaying the construction. 9 . As regards the delay in grant of approvals from the State Government is concerned, neither any particulars of the alleged delay have been given nor any evidence has been led to prove that there was abnormal delay on the part of Government Authorities in granting approval and the said delay had contributed to the delay in completion of the construction. 10. As regards the Jat reservation agitation, there is no evidence of
21-05-2021 (Page 5 of 10) www.manupatra.com Jamia Millia Islamia
the said agitation having actually resulted in stoppage of work at the site of the project. More importantly, the aforesaid protest is stated to have started in February 2016 whereas the construction was required to be completed by September 2015, much before the said agitation started in Gurgaon. 11. As regards NGT having stopped construction in April 2015 and November 2016, no order of NGT passed in April 2015 and stopping construction on the project in question has been placed on record. As far as the order of NGT dated 08.11.2016 is concerned, that came to be passed much later than the last date stipulated in the Buyers Agreement for completion of the construction. Moreover, the said order was operative only for a period of one week. 12. As far as demonetization is concerned, I fail to appreciate how it could have affected the construction since there was no restriction on payment by means of cheques/demand drafts and through other modes of banking transactions. Moreover, the demonetization came to force on 08.11.2016, much after the last date stipulated for completion of the construction had already expired." 14. With regard to Clause 11.5 of the Agreement upon which the reliance has been placed by the Developer for refund and compensation payable to the Complainants, the Coordinate Bench referring to another decision of this Commission in Consumer Complaint No. 2000 of 2016 -Geeta Bansal Vs. M/s. Ireo Grace Realtech Pvt. Ltd. & Ors. - decided on 24.09.2018, has held that such a Clause is wholly one sided and unfair and, therefore, the Complainants would not be bound by the same. If the Developer is unable to justify the delay, this Commission would be competent to direct refund of the amount paid by them to the Developer along with appropriate compensation. 15. At this juncture, it is pertinent to mention that Civil Appeal Nos. 12238 of 2018 and 1677 of 2019 were filed by the Developer, Pioneer Urban Land and Infrastructure Ltd. before the Hon'ble Supreme Court of India against the order dated 23.10.2018 passed by the Coordinate Bench of this Commission in Geetu Gidwani's case (Supra). Vide order, dated 02.04.2019, the Hon'ble Supreme Court of India affirmed the finding returned by this Commission and dismissed the Civil Appeals with the following observations:- "6. We have heard the learned Counsel for both the parties, and perused the pleadings, and written submissions filed. 6.1. In the present case, admittedly the Appellant-Builder obtained the Occupancy Certificate almost 2 years after the date stipulated in the Apartment Buyer's Agreement. As a consequence, there was a failure to hand over possession of the flat to the Respondent-Flat Purchaser within a reasonable period. The Occupancy Certificate was obtained after a delay of more than 2 years on 28.08.2018 during the pendency of the proceedings before the National Commission. In Lucknow Development Authority v. M.K. Gupta - MANU/SC/0178/1994 : (1994) 1 SCC 243, this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a "service" as defined by Section 2 (o) of
21-05-2021 (Page 6 of 10) www.manupatra.com Jamia Millia Islamia
the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service. In Fortune Infrastructure and Anr. v. Trevor D'Lima and Ors., MANU/SC/0253/2018 : (2018) 5 SCC 442, this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation. 6.2. The Respondent-Flat Purchaser has made out a clear case of deficiency of service on the part of the Appellant-Builder. The Respondent-Flat Purchaser was justified in terminating the Apartment Buyer's Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession whenever it is offered by the Builder. The Respondent-Purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation. 6.3. The National Commission in the Impugned Order dated 23.10.2018 held that the Clauses relied upon by the Builder were wholly one-sided, unfair and unreasonable, and could not be relied upon. The Law Commission of India in its 199th Report, addressed the issue of 'Unfair (Procedural & Substantive) Terms in Contract'. The Law Commission inter-alia recommended that a legislation be enacted to counter such unfair terms in contracts. In the draft legislation provided in the Report, it was stated that: "A contract or a term thereof is substantively unfair if such contract or the term thereof is in itself harsh, oppressive or unconscionable to one of the parties." 6.4. A perusal of the Apartment Buyer's Agreement dated 08.05.2012 reveals stark incongruities between the remedies available to both the parties. For instance, Clause 6.4 (ii) of the Agreement entitles the Appellant-Builder to charge Interest @18% p.a. on account of any delay in payment of installments from the Respondent-Flat Purchaser. Clause 6.4 (iii) of the Agreement entitles the Appellant-Builder to cancel the allotment and terminate the Agreement, if any installment remains in arrears for more than 30 days. On the other hand, as per Clause 11.5 of the Agreement, if the Appellant- Builder fails to deliver possession of the apartment within the stipulated period, the Respondent-Flat Purchaser has to wait for a period of 12 months after the end of the grace period, before serving a Termination Notice of 90 days on the Appellant-Builder, and even thereafter, the Appellant-Builder gets 90 days to refund only the actual installment paid by the Respondent- Flat Purchaser, after adjusting the taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the Appellant-Builder is liable to pay Interest @9% p.a. only. 6.5. Another instance is Clause 23.4 of the Agreement which entitles the Appellant-Builder to serve a Termination Notice upon the Respondent-Flat Purchaser for breach of any contractual obligation. If the Respondent-Flat
21-05-2021 (Page 7 of 10) www.manupatra.com Jamia Millia Islamia
Purchaser fails to rectify the default within 30 days of the Termination Notice, then the Agreement automatically stands cancelled, and the Appellant-Builder has the right to forfeit the entire amount of Earnest Money towards liquidated damages. On the other hand, as Clause 11.5 (v) of the Agreement, if the Respondent- Flat Purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the Agreement thereafter, and shall be bound by the provisions of the Agreement. 6.6. Section 2 (r) of the Consumer Protection Act, 1986 defines 'unfair trade practices' in the following words: " 'unfair trade practice' means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice...", and includes any of the practices enumerated therein. The provision is illustrative, and not exhaustive. In Central Inland Water Transport Corporation Limited and Ors. v. Brojo Nath Ganguly and Ors.,: MANU/SC/0439/1986 : (1986) 3 SCC 156, this Court held that: 8 9 . ... Our judges are bound by their oath to 'uphold the Constitution and the laws'. The Constitution was enacted to secure to all the citizens of this country social and economic justice. Article 14 of the Constitution guarantees to all persons equality before the law and equal protection of the laws. This principle is that the courts will not enforce and will, when called upon to do so, strike down an unfair and unreasonable contract, or an unfair and unreasonable Clause in a contract, entered into between parties who are not equal in bargaining power. It is difficult to give an exhaustive list of all bargains of this type. No court can visualize the different situations which can arise in the affairs of men. One can only attempt to give some illustrations. For instance, the above principle will apply where the inequality of bargaining power is the result of the great disparity in the economic strength of the contracting parties. It will apply where the inequality is the result of circumstances, whether of the creation of the parties or not. It will apply to situations in which the weaker party is in a position in which he can obtain goods or services or means of livelihood only upon the terms imposed by the stronger party or go without them. It will also apply where a man has no choice, or rather no meaningful choice, but to give his assent to a contract or to sign on the dotted line in a prescribed or standard form or to accept a set of Rules as part of the contract, however unfair, unreasonable and unconscionable a Clause in that contract or form or Rules may be. This principle, however, will not apply where the bargaining power of the contracting parties is equal or almost equal. This principle may not apply where both parties are businessmen and the contract is a commercial transaction. ... These cases can neither be enumerated nor fully illustrated. The court must judge each case on its own facts and circumstances.
21-05-2021 (Page 8 of 10) www.manupatra.com Jamia Millia Islamia
(Emphasis supplied) 6.7. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one- sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder. 7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer's Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder could not seek to bind the Respondent with such one-sided contractual terms. 8 . We also reject the submission made by the Appellant-Builder that the National Commission was not justified in awarding Interest @10.7% S.I. p.a. for the period commencing from the date of payment of each installment, till the date on which the amount was paid, excluding only the period during which the stay of cancellation of the allotment was in operation. In Bangalore Development Authority v. Syndicate Bank,: MANU/SC/2718/2007 : (2007) 6 SCC 711, a Coordinate Bench of this Court held that when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable Interest thereon from the date of payment till the date of refund. 8.1. In the present case, the National Commission has passed an equitable Order. The Commission has not awarded any Interest for the period during which the Order of stay of cancellation of the allotment was in operation on the request of the Respondent-Flat Purchaser. The National Commission has rightly awarded Interest @10.7% S.I. p.a. by applying Rule 15 of the Haryana Real Estate (Regulation And Development) Rules, 2017 from the date of each installment till 05.02.2017 i.e. till the date after which the Order of stay of cancellation of the allotment was passed; and thereafter, from the date of the Commission's final Order till the date on which the amount is refunded with Interest. 9 . We see no illegality in the Impugned Order dated 23.10.2018 passed by the National Commission. The Appellant-Builder failed to fulfil his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to the Respondent-Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent-Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired. During this period, the Respondent-Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest @10% to the Bank. In the meanwhile, the Respondent-Flat Purchaser also located an alternate property in Gurugram. In these circumstances, the Respondent-Flat
21-05-2021 (Page 9 of 10) www.manupatra.com Jamia Millia Islamia