Professional Documents
Culture Documents
Engineering Geology
a r t i c l e i n f o a b s t r a c t
Article history: The EB experiment was a large-scale test performed in the Underground Research Laboratory of Mont Terri
Received 27 May 2014 (Switzerland) for the demonstration of an engineered barrier concept for nuclear waste disposal consisting of
Received in revised form 30 January 2015 the simultaneous use of high-density bentonite blocks and a lower-density bentonite pellets mixture (the gran-
Accepted 1 April 2015
ular buffer material, GBM). For that purpose, a gallery was excavated in the Opalinus clay and a dummy waste
Available online 9 April 2015
canister was placed on a bed made of bentonite blocks and surrounded by the GBM material. The bentonite bar-
Keywords:
rier was artificially hydrated with Pearson water and after 10.5 years of operation at isothermal conditions it was
Engineered barrier considered that the bentonite was completely saturated and the dismantling of the barrier was undertaken. A
Bentonite blocks sampling campaign was done to assess the final state of the bentonite barrier with regards to dry density and
Bentonite pellets water content.
Nuclear waste Upon dismantling, the GBM looked perfectly homogeneous, with every void and gap between the different ele-
Swelling ments (blocks/GBM, GBM/host rock, GBM/canister, etc.) having been sealed. Full saturation had been reached all
Large-scale test through the barrier. Moreover, the dry density of the blocks had decreased to values similar to those of the GBM,
Saturation
and the average water contents for both kinds of materials were similar. Nevertheless, the initial conditions of the
system did have a certain impact on the final distribution of dry density and water content: the bottom of the bar-
rier had a chance to quicker and higher water uptake (due to the heterogeneities in the initial porosity and char-
acteristics of the artificial hydration system), which gave place to immediate swelling that resulted irreversible,
with permanent higher water contents and lower dry densities towards the floor and back of the gallery, partic-
ularly in the GBM. Despite these heterogeneities, the water contents and dry densities of the whole barrier (GBM
and blocks) were much more homogeneous than at the beginning of the test and remained within a relatively
narrow range. The bentonite degree of saturation was homogeneous and very close to 100% all through the
barrier.
The feasibility and performance of this kind of initially heterogeneous barrier was proved in that it had an optimal
sealing capacity and developed acceptable swelling pressures between 1.3 and 2.2 MPa.
© 2015 Elsevier B.V. All rights reserved.
1. Introduction scale experiments in which the barrier around the waste packages
consisted of compacted blocks, such as the FEBEX mock-up and in situ
The backfilling and sealing of deposition galleries or holes and access tests (ENRESA, 2006; Villar et al., 2005, 2012) or the Prototype Reposi-
galleries and shafts is an important part of nuclear waste underground tory (Börgesson et al., 2002).
repository design. Any opening created during the construction of the The use of high-density bentonite pellets (combined or not with
repository is a potential preferential pathway for water, gas and radio- powdered bentonite) was also proposed long ago (Salo and Kukkola,
nuclide migration, and has to be effectively sealed. Bentonite or 1989; Volckaert et al., 1996). A mixture of high-density bentonite pel-
bentonite-based mixtures have been proposed as backfill and sealing lets and bentonite powder was used in the large-scale demonstration
materials for their low permeability, high swelling capacity and high re- experiment RESEAL, carried out in a vertical shaft under isothermal con-
tention capacity. These materials have been widely characterised in the ditions at the Hades Underground Research Facility in Mol, Belgium
form of high-density pre-compacted blocks, and their performance (Volckaert et al., 2000; van Geet et al., 2009). Bentonite pellets were
under repository conditions has been also mainly assessed in large- also proposed to backfill the slot between bentonite blocks and the
host rock in deposition holes, such as in the Prototype Repository in
⁎ Corresponding author.
situ experiment (Svensk Kärnbränslehantering AB, 2002). The advan-
E-mail addresses: jlg.sineriz@aitemin.es (J.L. García-Siñeriz), mv.villar@ciemat.es tage of this material is that it is easy to manufacture and instal: the ben-
(M.V. Villar), maria.rey@aitemin.es (M. Rey), beatriz.palacios@aitemin.es (B. Palacios). tonite pellets can be emplaced using auger discharge tubes or even
http://dx.doi.org/10.1016/j.enggeo.2015.04.002
0013-7952/© 2015 Elsevier B.V. All rights reserved.
34 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
pneumatic projection techniques. Thus, the backfilling operation be- swelling pressure and permeability, were suitable within the limits con-
comes an easier and potentially robotised procedure. On the other sidered in the Performance Assessment of the repository concept, and
hand, the problem of this emplacement technique is that the final values this was precisely the objective of the EB experiment. This paper pre-
of the key parameters of the barrier (such as dry density and permeabil- sents a brief description of the configuration of the test and its opera-
ity), which depend on the initial characteristics of the backfill material, tion, and focuses on the observations made and results obtained
the emplacement technique used and the hydro-mechanical interaction concerning the state of the bentonite barrier upon its dismantling
between the backfill and the surrounding rock, have not been yet dem- after reaching full saturation.
onstrated (Mayor et al., 2005). Besides, in the case of horizontal place-
ment a rigid support for the canister is needed, what can be achieved 2. The EB experiment: configuration and operation
by a bentonite block bed on which the canister is laid, and this must
be used in combination with the pellets' backfill. Although the hydro- The full-scale Engineered Barrier Emplacement Experiment (EB)
mechanical characterisation of pellets performed in laboratories has was carried out in a horizontal tunnel specially excavated with a road
shown that their saturated permeability and swelling pressure are header in the Opalinus clay formation at the Mont Terri Underground
mainly controlled by the overall dry density of the sample rather than Research Laboratory (URL) in Switzerland. The EB tunnel was 15 m
the initial grain size distribution, and are thus similar to those of benton- long and had a geometry of a horseshoe section, 2.55 m high and 3 m
ite blocks of the same dry density (Imbert and Villar, 2006; Hoffmann, wide (Fig. 1). A dummy canister, with the same dimensions and weight
2005; Alonso et al., 2010), the combined use of pellets and blocks in as the Spanish reference canister (ENRESA, 1995), was placed on top of
the same section of the barrier introduces difficulties in the understand- a pedestal of highly compacted bentonite blocks which lay over a con-
ing and modelling of the system performance that have to be addressed. crete bed. The remaining volume of the drift was backfilled with a gran-
The Engineered Barrier Emplacement Experiment in Opalinus Clay, ular material made of highly compacted bentonite pellets (GBM).
“EB” Experiment, aimed the demonstration of a new concept for the Finally, the drift was sealed with a mass-type concrete plug, with a con-
construction of nuclear waste repositories in competent clay formations crete retaining wall between the plug and the GBM. Due to the short
using horizontal deposition drifts (Mayor et al., 2005). The principle of amount of free water available in this formation, an artificial hydration
the new construction method was based on the combined use of a system consisting of a series of porous tubes that crossed along the
lower bed made of highly compacted bentonite blocks in which the GBM and the bentonite blocks was installed to accelerate the hydration
waste canister rested and an upper buffer made of granular bentonite process in the bentonite (Fig. 2). The hydration tubes were connected in
material, consisting of a mixture of different-sized bentonite pellets. such a way that the water went into the material from the front to the
To asses that this backfilling technique was feasible, it had to be first back and from the floor to the roof of the gallery. To enhance the
demonstrated that the final values of the key parameters of the clay water homogeneous distribution, the concrete bed, the surface of the
buffer that may be achieved with this method, such as dry density, container and the three rings of the bentonite blocks bed were covered
Fig. 1. EB drift at Mont Terri URL, longitudinal and cross sections (Mayor et al., 2005).
J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45 35
Having the evidence that the buffer was fully saturated (as con-
firmed by the high relative humidities measured and in particular by
Gravity fall the stabilisation of the pressures inside the buffer), the main objective
of the dismantling of the EB experiment was to know the real status of
the GBM: degree of saturation, permeability, density, aspect, homoge-
neity, etc. It was also important to check the status of the bentonite
Hydration blocks that support the canister, the rock in contact with the buffer
and the degree of saturation of the concrete in the vicinity of the buffer
tubes (plug and concrete bed). Therefore, the activities of the dismantling
were coordinated with a sampling programme intended to analyse
the parameters of interest on-site as well as in the laboratories of the
different organizations involved (e.g. Stroes-Gascoyne et al., 2013; Villar
et al., 2014).
Canister The dismantling of the test started in October 2012 with the demo-
GBM lition of the concrete plug, which took almost a month, and went on
until February 2013. As the dismantling moved forward, all the experi-
ment components such as hydration pipes, sensors or metallic piping
from boreholes were also removed. The dismantling operation ended
with the removal of the Data Acquisition System. The monitoring of
the test was kept running during the whole dismantling process. A de-
tailed description of the dismantling operation was given in Palacios
et al. (2013).
Fig. 6 shows the appearance of the GBM and the bentonite blocks
upon exposure during dismantling, as well as details of the GBM-
blocks contact. The GBM looked completely homogeneous and every
Fig. 3. GBM emplacement using an auger discharge tube. void in the barrier had been filled. The contact between the blocks and
36 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
Fig. 4. Evolution of relative humidity inside the buffer in sections B1 and B2 during the first phase of operation (Mayor et al., 2005).
the GBM was easily recognisable, since the blocks presented a coarse- analysis in the laboratory. Altogether, almost 500 samples were taken.
grained texture, whereas no grains could be identified in the GBM. Around 210 of them were analysed on-site and the rest were packed
The pictures show also the numerous tubes and cables that crossed and sent to the different partners' laboratories. Most of the bentonite
the barrier and the blocks, the appearance of the steel container, the samples were taken in the vertical sections indicated in Fig. 7, following
concrete bed and the geotextile layers that separated the three rings approximate radii (Fig. 8). Sections A1, B1, E, B2 and A2 were instru-
of blocks. Regarding the rest of elements of the experiment, such as hy- mented. The origin of coordinates for location of every section and sam-
dration pipes, cables and geotextile, all of them were found in perfect ple was set on the floor, in the centre of the outer face of the concrete
conditions. In general the corrosion effects on metallic parts were plug.
negligible. After testing several sampling methods, and in order to avoid exces-
Samples of the GBM, the bentonite blocks, the concrete bed and the sive disturbance, irregular pieces of GBM were extracted with a hammer
concrete plug, the Opalinus clay, and other materials were taken for (a geologist one or an electric percussion hammer with a flat-end bit
Fig. 5. Evolution of total pressure inside the buffer (section E) during operation (Palacios et al., 2013, Appendix III).
J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45 37
Fig. 6. Appearance of the GBM (left up), the bentonite blocks (right up), the GBM-blocks contact (left bottom) and the hydration pipes (right bottom) upon dismantling. The rectangular
marks were caused by the tools used to dig the bentonite.
tool attached). For the extraction of the bentonite blocks, the percussion protection plastic. Besides, before starting sampling next day, at least
hammer was equipped with a pointy bit in order to separate the blocks 30 cm of bentonite were removed.
and remove them in one whole piece. Before extracting the blocks, the Two main parameters were determined on site: water content and
dimensions of some of them were measured. The removal of the ben- dry density (Palacios et al., 2013). These determinations were also per-
tonite was done in such a way as to keep the face of work as parallel formed at CIEMAT laboratories in Madrid in bentonite samples that
to the plug as possible. From the moment the bentonite was reached, were quickly packed after sampling and sent. The packaging consisted
a fast drying process was observed at the excavated bentonite front of a plastic film and two aluminium-foil bags that were vacuumed be-
(Fig. 9), so after every day of work, the excavation was covered with a fore being sealed.
Fig. 7. Longitudinal cross-section of the EB test at Mont Terri. Bentonite sampling sections (Palacios et al., 2013).
38 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
100
90
Hoffmann 2005
80
Villar 2012
Percentage passing
70
60
50
40
30
20
10
0
10 1 0.1 0.01
Fig. 8. Cross-section of a bentonite sampling section (section E) with indication of the sam-
Pellet diameter (mm)
ples taken (Palacios et al., 2013).
Fig. 10. Granulometric curve of the GBM used for the EB test as determined by dry sieving
in two laboratories.
4. Material
5. Methodology of postmortem tests obtained in the laboratory were on average 0.7% higher than those ob-
tained on site, and the dry densities 0.2% higher. For section E the
5.1. On-site determinations water contents obtained in the laboratory were on average the same
as those obtained on-site and the dry densities 1.4% higher. The differ-
The samples for the on-site determinations were taken from sec- ences were very small, particularly regarding water content, conse-
tions A1–25, B1, E, B2 and A2. After collecting every GBM sample, it quently they are not considered significant. This proved that the
was cut and trimmed into three subsamples of between 6 and 12 cm3 packaging methods were good enough to keep the physical conditions
in volume. The water content was obtained from all the subsamples of the samples upon extraction. In the following, the determinations
and the dry density from two of them. performed on-site and in the laboratory are jointly considered.
The gravimetric water content (w) is defined as the ratio between
the mass of water and the mass of dry solid expressed as a percentage. 6. Results
The mass of water was determined as the difference between the
mass of the sample and its mass after oven drying at 110 °C for 48 h 6.1. Dry density and water content
(mass of dry solid). Dry density (ρd) is defined as the ratio between
the mass of the dry sample and the volume occupied by it prior to dry- The samples for the water content and density determinations were
ing. The volume of the specimens was determined by immersing them taken following approximately sampling radii in the GBM, as shown in
in a recipient containing mercury and by weighing the displaced mercu- Fig. 8. As the dismantling operation started it was observed that the bot-
ry. The same samples whose volumes had been determined were used tom part of the barrier, particularly the zones closer to the concrete bed,
for the water content determination. looked wetter than the rest of the GBM, and it was also decided to ana-
lyse the samples taken from the part of the barrier closer to the floor and
5.2. Laboratory determinations not belonging to any particular radius. About 300 bentonite samples
were analysed.
The samples for the laboratory determinations were taken from sec- The results obtained in the different sampling sections were plotted
tions CMT1, CMT2 and CMT3, and also duplicates of some of the samples in contour maps using a grid-based mapping software that interpolates
taken in sections E and B2. Until their analysis, the packed samples sent irregularly spaced XYZ data into a regularly spaced grid. Kriging was
from Mont Terri were kept at CIEMAT facilities in a storage room in used as gridding method. Fig. 11 shows this representation for section
which the temperature was between 7 and 16 °C and the relative hu- B2, which was one of the most thoroughly sampled. Each point in the
midity between 70 and 90%. The samples were taken one at a time out figures is the average of two or three measurements. The higher water
of the storage room and unpacked in the laboratory. content and lower dry density of the GBM at the bottom of the barrier
The dry density and water content were determined in small sam- becomes clear in this kind of representation, whereas the degree of sat-
ples to complement the determinations performed on site. These sam- uration did not display any particular spatial trend. The same kind of
ples were prepared by trimming regular specimens of the right size, technique was used to obtain longitudinal sections along the barrier.
with volumes of between 6 and 13 cm3. Two specimens were trimmed Fig. 12 shows two of these sections for the water content, one corre-
and analysed from each GBM sample. The subsamples from each block sponding to the low part of the barrier (Y coordinate: 44–54 cm) and
were taken at three different distances from the container, and for the other one to the top (Y coordinate: 190–210). The former shows
each distance at least two specimens were used. The methodology the lower water content in the blocks in relation to the adjacent GBM,
followed was the same as for the on-site determinations. Additionally, whereas the latter displays the trend to find slightly higher water con-
in some cases larger samples were used just for water content tents in the GBM towards the back of the gallery. The dry density follows
determination. the inverse behaviour.
From these representations, the software allows one to compute the
5.3. Evaluation of the methodology median values for each vertical sampling section, blocks and GBM in-
cluded. These values have been plotted in Fig. 13 as “GBM + blocks”.
Since most of the samples analysed had very high water contents, The average of these median values for all the sampling sections
much higher than hygroscopic, their manipulation could imply certain would be 35.4 ± 1.2% for the water content, 1.36 ± 0.02 g/cm3 for the
water content change. The process of trimming took some minutes, dry density and 97 ± 1% for the degree of saturation. Fig. 13, shows
and during this time some drying of the sample could have taken also the average values for each sampling section computed from the in-
place, because the samples remained exposed to drier room conditions dividual measurements, separately for the GBM and for the blocks. The
than those in the barrier. In particular, the relative humidity and tem- trend for the water content and dry density change along the barrier ob-
perature at the gallery of the Mont Terri URL where the determinations served in Fig. 12 is also clear in this kind of representation, particularly
were done were 48% and 17 °C, and the CIEMAT's laboratory conditions for the GBM.
during the determinations were relative humidity of 35 ± 6% and tem- All the results obtained for the GBM in terms of water content and
perature of 22 ± 1 °C. dry density are plotted as a function of the Y coordinate of the samples
In order to determine how this drying could affect the values of in Figs. 14 and 15. The origin for this coordinate is the middle point of
water content obtained, some samples were allowed to air dry both in the floor of the gallery (Fig. 8). Each point is the average of three mea-
the laboratory and in the gallery, and their weight change was periodi- surements for those determinations performed on-site and of two mea-
cally checked before putting the samples in the oven to determine their surements for the determinations performed in the laboratory. The
dry mass. Taking into account that the trimming process took less than trend for the water content to increase and the dry density to decrease
20 min, it was concluded that the decrease in water content during ma- towards the floor is very clear and can even be fit to a potential expres-
nipulation could have been between 0.7 and 1.5%, which would imply a sion. The samples having higher water contents (higher than 45%) and
decrease in the degrees of saturation computed, of 2% in the worst cases lower dry densities are those located at the lower part of the gallery,
(Palacios et al., 2013; Villar, 2013). close to the concrete bed. The average of all the GBM water content
Additionally, a comparison of the results obtained on-site and in the measurements is 36.9 ± 4.3%, with the mode in 35.6%, and of the dry
laboratory was made. Twin samples were taken in sections E and B2; density 1.33 ± 0.07 g/cm3, with the mode in 1.36 g/cm3. Note that
one of them was analysed on-site and the other one was sent to the lab- these average values are higher for the water content and lower for
oratories in Madrid. A total of 13 samples from section B2 and 17 from the dry density than the average values found for the whole barrier,
section E were cross-checked. For section B2 the water contents blocks and GBM together (see above), whereas the mode values for
40 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
densities to decrease towards the concrete bed, that is, away from the
container. This was also the predominant trend in the sections sampled
on-site (A1, B1, E and B2). However, in section CMT3 these trends were
not observed. In any case, all the values are within a range of between 34
and 37% water content and between 1.33 and 1.39 g/cm3 dry density.
These ranges have been marked in Fig. 15, and are slightly above the av-
erage of the GBM for the dry density and below for the water content.
However, the mode for the GBM values is comprised between these
ranges, i.e. the values measured in the blocks are the same as those
more frequently found in the GBM. In terms of degree of saturation of
the blocks there were no clear spatial trends. The values measured
were between 95 and 101%.
Fig. 12. Water content along the bentonite barrier in two longitudinal sections (bottom and top).
blocks along the Z axis was also proven by the evolution of the distance content 14%) and pellets (Granular Buffer Material, GBM, average
between the front face of the canister and the front face of the concrete installed dry density around 1.3 g/cm3 and water content 3%) was
bed. They were aligned when the EB dismantling started and at the end checked in a large-scale experiment performed in a tunnel excavated
of the dismantling operation there was a separation of about 4 cm be- in Opalinus clay. After five years of artificial hydration and a total of
tween both. 10.5 years of observation at isothermal conditions the test was disman-
tled. The measurements of the relative humidity and total pressure sen-
7. Discussion sors placed in the barrier indicated that a steady state had been reached
and that the bentonite was fully saturated. The GBM looked homoge-
The performance of an engineered barrier for a nuclear waste repos- neous and no gaps or voids remained in the barrier system. Numerous
itory composed of bentonite blocks (dry density 1.7 g/cm3, water samples were taken for their analysis on-site and in the laboratory.
44 1.45
GBM GBM
1.43
42 blocks blocks
1.41
GBM+blocks GBM+blocks
Dry density (g/cm3)
1.39
40
Water content (%)
1.37
38 1.35
1.33
36
1.31
1.29
34
1.27
32 1.25
300 400 500 600 700 800 300 400 500 600 700 800
Fig. 13. Average values of water content and dry density for the different sampling sections along the barrier (the “blocks” and “GBM” values are the average computed from all the mea-
surements in each material, the “GBM + blocks” values are the median vales computed for each section with the mapping software).
42 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
52 towards the back of the gallery. The disposition of the hydration tubes,
A1-25 which were connected in such a way that the water went into the ma-
50 terial from the front to the back of the gallery and from the floor to
CMT1
the roof, could be an explanation for this observation. The higher
48 B1 water contents in these zones were accompanied by lower dry densi-
CMT2 ties, a consequence of swelling. This swelling seems to have been irre-
46
E versible, since the density difference among different parts of the
Water content (%)
Fig. 15. Dry density of GBM samples from different sampling sections as a function of co- The EB experiment was a large-scale test performed in the Under-
ordinate Y. The shadowed area shows the range of the measurements in blocks. ground Research Laboratory of Mont Terri (Switzerland) for the
J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45 43
40 1.41
39 1.40
1.39
38
w.c. CMT1
1.38
37 w.c. CMT2
35 d.d. CMT2
1.35
d.d. CMT3
34
1.34
33 1.33
32 1.32
50 70 90 110 130
Fig. 16. Water contents (w.c.) and dry densities (d.d.) measured in blocks from three sampling sections (each point is the average of two measurements).
Table 2 groundwater, was used. The test was instrumented, and among other
Average values measured in blocks from different sections. parameters, the relative humidity and total pressure at different points
Section Dry density (g/cm3) Water content (%) Degree of saturation (%) inside the barrier were monitored. Most of the sensors recorded relative
CMT1 1.36 ± 0.02 35.4 ± 1.6 97 ± 2
humidity values of 100% only one year after the beginning of the test,
CMT2 1.38 ± 0.01 34.7 ± 1.1 98 ± 2 whereas it took four years for the total pressure sensors to record stable
CMT3 1.36 ± 0.01 35.5 ± 0.5 98 ± 1 values that kept approximately constant until the end of the test. Conse-
quently, after 10.5 years of operation it was considered that the benton-
ite was completely saturated and the dismantling of the barrier was
demonstration of an engineered barrier concept for nuclear waste dis- undertaken. The GBM looked perfectly homogeneous, with every void
posal consisting of the simultaneous use of high-density bentonite and gap between the different elements (blocks/GBM, GBM/host rock,
blocks (dry density 1.7 g/cm3, water content 14%) and a lower density GBM/canister, etc.) having been sealed. During dismantling a large
bentonite pellets mixture (the granular buffer material, GBM, with an number of samples of the different elements were taken, particularly
average installed dry density around 1.3 g/cm3 and a water content of of bentonite. Namely a thorough bentonite sampling was done to assess
3%). For that, a gallery was excavated in the Opalinus clay and a the final state of the barrier with regards to dry density and water con-
dummy waste canister was placed on a bed made of bentonite blocks tent. The analyses were performed both on-site and in the laboratory in
and surrounded by the GBM material. The bentonite barrier was artifi- Madrid, the comparison of both sets of results showing a very good
cially hydrated for five years under the isothermal conditions prevailing agreement.
in the gallery, and then it was allowed to evolve during five and a half Full saturation had been reached all through the barrier. Moreover,
years more. Pearson water, which simulates the clay formation the dry density of the blocks had significantly decreased and that of
the GBM had increased, and the water contents for both kinds of mate-
rials were similar. Nevertheless, the initial conditions of the system did
have a certain impact on the final distribution of dry density and water
content: the lower part of the barrier saturated earlier (probably be-
cause of initial porosity heterogeneities and the hydration system
configuration) and had a chance to a higher water uptake and immedi-
ate swelling that resulted irreversible, giving rise to permanent higher
water contents and lower dry densities towards the floor and back of
the gallery, particularly in the GBM. Despite these heterogeneities, the
water contents and dry densities of the whole barrier (GBM and blocks)
were much more homogeneous than at the beginning of the test
and remained within a relatively narrow range. Since the hydro-
mechanical properties of the bentonite, particularly swelling capacity
and permeability, depend mainly on dry density, it is expected that
the values for these properties be quite homogeneous through the bar-
rier. In fact, the pressure developed by the bentonite as measured by the
sensors remained during operation within an optimal range of between
Fig. 17. Cross section of the compacted bentonite blocks used (Mayor et al., 2005). 1.3 and 2.2 MPa and the hydraulic conductivity measured in the
44 J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45
Fig. 18. Pressure evolution in section E during dismantling. The ascending line shows the progress of dismantling along the Z axis, with indication of the moments at which each section
was dismantled. The dotted vertical line indicates the moment from which the GBM was removed before the blocks (Palacios et al., 2013, Appendix III).
References
Swelling pressure (MPa)
2.0 Alonso, E.E., Hoffmann, C., Romero, E., 2010. Pellet mixtures in isolation barriers. J. Rock
Mech. Geotech. Eng. 2 (1), 12–31.
Börgesson, L., Gunnarsson, D., Johannesson, L.E., Sandén, T., 2002. Installation of buffer,
canisters, backfill and instruments in Section 1. SKB Progress Report IPR-02-23.
Swedish Nuclear Fuel and Waste Management Company (SKB), Stockholm, Sweden.
ENRESA, 1995. Almacenamiento Geológico Profundo de Residuos Radiactivos de Alta
Actividad (AGP). Diseños Conceptuales Genéricos. Publicación Técnica ENRESA 11/
1.0 95 (Madrid).
ENRESA, 2006. FEBEX Full-scale Engineered Barriers Experiment, updated final report
1994–2004. Publicación Técnica ENRESA 05-0/2006, Madrid (590 pp.).
García-Siñeriz, J.L., Rey, M., Mayor, J.C., 2008. The engineered barrier experiment at Mont
Terri Rock Laboratory. Sci. Technol. Ser. 334, 65–75 (Andra).
Hoffmann, C., 2005. Caracterización hidromecánica de mezclas de pellets de bentonita.
Estudio experimental y constitutivo. (PhD Thesis), Universitat Politècnica de
0.0 Catalunya, Barcelona (387 pp.).
Imbert, Ch., Villar, M.V., 2006. Hydro-mechanical response of a bentonite pellets/powder
1 1.1 1.2 1.3 1.4 1.5 mixture upon infiltration. Appl. Clay Sci. 32, 197–209.
3 Mayor, J.C., García-Siñeriz, J.L., Alonso, E.E., Alheid, H.-J., Blümbling, P., 2005. Engineered
Final dry density (g/cm )
barrier emplacement experiment in Opalinus Clay for the disposal of radioactive
waste in underground repositories. Final Report. Publicación Técnica ENRESA 02/05
Fig. 19. Empirical correlation between swelling pressure and dry density for the FEBEX (Madrid, 101 pp.).
bentonite (solid line, Eq. (2); the dotted lines indicate the 25% range of variation) and Mayor, J.C., García-Siñeriz, J.L., Alonso, E.E., Alheid, H.-J., Blümbling, P., 2007. Engineered
total pressure measured by the sensors before dismantling against the dry density of the barrier emplacement experiment in Opalinus Clay for the disposal of radioactive
samples retrieved in section E (squares). waste in underground repositories. In: Bossart, P., Nussbaum, C. (Eds.), Mont Terri
J.L. García-Siñeriz et al. / Engineering Geology 192 (2015) 33–45 45
Project — Heater Experiment, Engineered Barriers Emplacement and Ventilation Villar, M.V., 2013. EB experiment. Contribution of CIEMAT to EB dismantling report. Phys-
Tests. Rep. Swiss Geol. Surv. 1, pp. 115–180. ical state of the bentonite. EC Contract 249681 PEBS. Informe Técnico CIEMAT/DMA/
Palacios, B., Rey, M., García-Siñeriz, J.L., 2013. Engineered barrier emplacement experi- 2G210/04/2013 (Madrid, 21 pp.).
ment in Opalinus Clay: “EB” experiment. As-built of dismantling operation. PEBS Villar, M.V., Lloret, A., 2008. Influence of dry density and water content on the swelling of
Deliverable-n°: D2.1–4. Contract Grant Agreement Number FP7 249681. AITEMIN a compacted bentonite. Appl. Clay Sci. 39, 38–49.
(95 pp.). Villar, M.V., Garcia-Sineriz, J.L., Barcena, I., Lloret, A., 2005. State of the bentonite barrier
Palacios, B., García-Siñeriz, J.L., Mayor, J.C., 2014. Outcome of the dismantling of “EB” ex- after five years operation of an in situ test simulating a high level radioactive waste
periment. In: Schäfers, A., Fahland, S. (Eds.), Proceedings International Conference repository. Eng. Geol. 80, 175–198.
on the Performance of Engineered Barriers, 6–7 February 2014. BGR, Hannover, Villar, M.V., Martín, P.L., Bárcena, I., García-Siñeriz, J.L., Gómez-Espina, R., Lloret, A., 2012.
pp. 45–52. Long-term experimental evidences of saturation of compacted bentonite under re-
Pearson, F., 1998. Artificial waters for use in laboratory and field experiments with pository conditions. Eng. Geol. 149–150, 57–69.
Opalinus Clay. Paul Scherrer Institut TM (44-98-08). Villar, M.V., Campos, R., Gutiérrez-Nebot, L., 2014. EB experiment. Laboratory post-
Salo, J.-P., Kukkola, T., 1989. Bentonite pellets, an alternative buffer material for spent fuel mortem analyses report. EC Contract 249681 PEBS. PEBS Deliverable 2.1–7. Technical
canister deposition holes. NEA/CEC Workshop “Sealing of Radioactive Waste Reposi- Report CIEMAT/DMA/2G210/01/2014 (Madrid, 34 pp.).
tories”. (Braunschweig, Germany), OECD, Paris. Volckaert, G., Bernier, F., Alonso, E., Gens, A., Samper, J., Villar, M.V., Martín, P.L., Cuevas, J.,
Stroes-Gascoyne, S., Frutschi, M., Hamon, C., Bagnoud, A., Leupin, O., Bernier-Latmani, R., Campos, R., Thomas, H.R., Imbert, C., Zingarelli, V., 1996. Thermal–hydraulic–mechan-
2013. Microbiological analysis of samples from the Engineered Barrier Experiment ical and geochemical behaviour of the clay barrier in radioactive waste repositories
at Mont Terri Rock Laboratory. Final Report. TN 2013-56 (23 pp.). (model development and validation). Nuclear science and technology. EUR 16744.
Svensk Kärnbränslehantering AB, 2002. Äspö Hard Rock Laboratory. Annual Report 2001. Commission of the European Communities, Luxembourg (722 pp.).
SKB Technical Report TR-02-10 (Stockholm. 184 pp.). Volckaert, G., Dereeper, B., Put, M., Ortiz, L., Gens, A., Vaunat, J., Villar, M.V., Martín, P.L.,
Van Geet, M., Bastiaens, W., Volckaert, G., Weetjens, E., Sillen, X., Maes, N., Imbert, C., Billaud, Imbert, C., Lassabatère, T., Mouche, E., Cany, F., 2000. A large-scale in situ demonstra-
P., Touzé, G., Filippi, M., Plas, F., Villar, M.V., García-Gutiérrez, M., Mingarro, M., Gens, A., tion test for repository sealing in an argillaceous host rock. Reseal project — Phase I.
Vallejan, B., 2009. RESEAL II. A large-scale in situ demonstration test for repository EUR 19612. Commission of the European Communities, Luxembourg (273 pp.).
sealing in an argillaceous host rock — Phase II. Final report.: EUR 24161, Nuclear Science
and Technology, European Commission, Luxembourg (288 pp.).