Professional Documents
Culture Documents
Valdtek Planilha Calculo 77 Dias
Valdtek Planilha Calculo 77 Dias
SERVIÇOS: Ordem:
H/h / Função
Tubulação
o
o
r
Ajudante
Soldado
Mecanic
Encanad
ade
Descrição do Material Ø Qtde Unid. Peso Unit. Peso Total
Produtivid
Total H/h
20% 15% 50% 15%
H/h /
% H/h % H/h % H/h % H/h
Anel Principal
comprimento dependendo
(Dep_Bobinas_HID.dwg; 10" 174.45 m 60.48 10,550.74 0.25 1,582.61 316.52 237.39 791.31 237.39
do limite de escopo
Dep_Bobinas_Hid_Iso.dwg)
6" 103.00 m 28.17 2,901.51 0.41 713.77 142.75 107.07 356.89 107.07
4" 238.00 m 15.98 3,803.24 0.51 1,163.79 232.76 174.57 581.90 174.57
SPRINGER 1 6" 122.00 m 28.17 3,436.74 0.41 845.44 169.09 126.82 422.72 126.82
4" 51.30 m 15.98 819.77 0.51 250.85 50.17 37.63 125.43 37.63
3" 12.50 m 11.32 141.50 0.61 51.79 10.36 7.77 25.89 7.77
2 1/2" 10.20 m 8.70 88.74 0.70 37.27 7.45 5.59 18.64 5.59
2" 6.10 m 5.40 32.94 0.76 15.02 3.00 2.25 7.51 2.25
1 1/2" - m 4.04 - 0.85 - - - - -
1 1/4" - m 3.40 - 1.19 - - - - -
1" 26.14 m 2.54 66.42 1.19 47.43 9.49 7.11 23.71 7.11
3/4" 75.68 m 1.72 130.17 1.45 113.25 22.65 16.99 56.62 16.99
SPRINGER 2 6" - m 28.17 - 0.41 - - - - -
4" 16.00 m 15.98 255.68 0.51 78.24 15.65 11.74 39.12 11.74
3" 24.00 m 11.32 271.68 0.61 99.43 19.89 14.92 49.72 14.92
2 1/2" 8.00 m 8.70 69.60 0.70 29.23 5.85 4.38 14.62 4.38
2" 8.00 m 5.40 43.20 0.76 19.70 3.94 2.95 9.85 2.95
1 1/2" 64.20 m 4.04 259.37 0.85 132.28 26.46 19.84 66.14 19.84
1 1/4" 129.00 m 3.40 438.60 1.19 313.16 62.63 46.97 156.58 46.97
1" 64.20 m 2.54 163.13 1.19 116.48 23.30 17.47 58.24 17.47
3/4" 129.00 m 1.72 221.88 1.45 193.04 38.61 28.96 96.52 28.96
SPRINGER 3 6" - m 28.17 - 0.41 - - - - -
4" 16.00 m 15.98 255.68 0.51 78.24 15.65 11.74 39.12 11.74
3" 24.00 m 11.32 271.68 0.61 99.43 19.89 14.92 49.72 14.92
2 1/2" 8.00 m 8.70 69.60 0.70 29.23 5.85 4.38 14.62 4.38
2" 8.00 m 5.40 43.20 0.76 19.70 3.94 2.95 9.85 2.95
1 1/2" 64.20 m 4.04 259.37 0.85 132.28 26.46 19.84 66.14 19.84
1 1/4" 129.00 m 3.40 438.60 1.19 313.16 62.63 46.97 156.58 46.97
1" 64.20 m 2.54 163.13 1.19 116.48 23.30 17.47 58.24 17.47
3/4" 129.00 m 1.72 221.88 1.45 193.04 38.61 28.96 96.52 28.96
SPRINGER 4 6" - m 28.17 - 0.41 - - - - -
4" - m 15.98 - 0.51 - - - - -
3" 24.00 m 11.32 271.68 0.61 99.43 19.89 14.92 49.72 14.92
2 1/2" 8.00 m 8.70 69.60 0.70 29.23 5.85 4.38 14.62 4.38
2" 8.00 m 5.40 43.20 0.76 19.70 3.94 2.95 9.85 2.95
1 1/2" 59.92 m 4.04 242.08 0.85 123.46 24.69 18.52 61.73 18.52
1 1/4" 120.40 m 3.40 409.36 1.19 292.28 58.46 43.84 146.14 43.84
1" 59.92 m 2.54 152.26 1.19 108.71 21.74 16.31 54.36 16.31
3/4" 120.40 m 1.72 207.09 1.45 180.17 36.03 27.02 90.08 27.02
SPRINGER 5 6" - m 28.17 - 0.41 - - - - -
4" 50.70 m 15.98 810.19 0.51 247.92 49.58 37.19 123.96 37.19
3" 19.50 m 11.32 220.74 0.61 80.79 16.16 12.12 40.40 12.12
2 1/2" 7.80 m 8.70 67.86 0.70 28.50 5.70 4.28 14.25 4.28
1
CÁLCULO DE ORÇAMENTO - TUBULAÇÃO
SERVIÇOS: Ordem:
H/h / Função
Tubulação
o
o
r
Ajudante
Soldado
Mecanic
Encanad
ade
Descrição do Material Ø Qtde Unid. Peso Unit. Peso Total
Produtivid
Total H/h
20% 15% 50% 15%
H/h /
% H/h % H/h % H/h % H/h
2" 3.90 m 5.40 21.06 0.76 9.60 1.92 1.44 4.80 1.44
1 1/2" 3.90 m 4.04 15.76 0.85 8.04 1.61 1.21 4.02 1.21
1 1/4" - m 3.40 - 1.19 - - - - -
1" 103.50 m 2.54 262.99 1.19 187.78 37.56 28.17 93.89 28.17
3/4" 165.60 m 1.72 284.83 1.45 247.80 49.56 37.17 123.90 37.17
SPRINGER 6 6" - m 28.17 - 0.41 - - - - -
4" 50.70 m 15.98 810.19 0.51 247.92 49.58 37.19 123.96 37.19
3" 19.50 m 11.32 220.74 0.61 80.79 16.16 12.12 40.40 12.12
2 1/2" 7.80 m 8.70 67.86 0.70 28.50 5.70 4.28 14.25 4.28
2" 3.90 m 5.40 21.06 0.76 9.60 1.92 1.44 4.80 1.44
1 1/2" 3.90 m 4.04 15.76 0.85 8.04 1.61 1.21 4.02 1.21
1 1/4" - m 3.40 - 1.19 - - - - -
1" 103.50 m 2.54 262.99 1.19 187.78 37.56 28.17 93.89 28.17
3/4" 165.60 m 1.72 284.83 1.45 247.80 49.56 37.17 123.90 37.17
SPRINGER 7 6" 24.60 m 28.17 692.98 0.41 170.47 34.09 25.57 85.24 25.57
4" 37.00 m 15.98 591.26 0.51 180.93 36.19 27.14 90.46 27.14
3" 12.30 m 11.32 139.24 0.61 50.96 10.19 7.64 25.48 7.64
2 1/2" 8.20 m 8.70 71.34 0.70 29.96 5.99 4.49 14.98 4.49
2" 4.10 m 5.40 22.14 0.76 10.10 2.02 1.51 5.05 1.51
1 1/2" 94.16 m 4.04 380.41 0.85 194.01 38.80 29.10 97.00 29.10
1 1/4" 189.20 m 3.40 643.28 1.19 459.30 91.86 68.90 229.65 68.90
1" 94.16 m 2.54 239.26 1.19 170.83 34.17 25.62 85.42 25.62
3/4" 189.20 m 1.72 325.42 1.45 283.12 56.62 42.47 141.56 42.47 factor in
3,467.53 33,285.50 10,807.85 2,161.57 1,621.18 5,403.92 1,621.18 0.6
EFETIVO PREVISTO MOD
Horas 8 semanas, 11 horas por dia, incluindo
Total H/h Dias Uteis Nº Funcionários FUNÇÃO Horario Util
Trabalhadas Sabados.
NOSSO
PRAZO DA OBRA: 77 Dias Úteis: 66 66
PRAZO:
2
Planilha de Custos
3
Planilha de Custos
I - CUSTOS VISITAS
Qtde Valor Unit Total
Técnica
- R$ 200.00 R$ -
Qtde Valor Unit Total
Famíliar
VISITAS
R$ 150.00 R$ -
Qtde Valor Unit Total
Projeto
R$ 200.00 R$ -
Qtde Valor Unit Total
R$ -
4
Planilha de Custos
VISITAS
R$ -
5
PLANILHA DE SERVIÇOS DE TERCEIROS
H/h MONTAGEM
DESCRIÇÃO M O D C +D M O I A +B TOTAL
H/h MONTAGEM 15,102.95 2,582.00 17,684.95
TOTAL GERAL 17,684.95
RESUMO
SALÁRIOS (MOI A+B) R$ 39,937.53
93.00% R$ 77,079.43
ENCARGOS SOCIAIS (% MOI A+B) R$ 77,079.43
SALÁRIOS (MOD C+D) R$ 81,301.22
80.00% R$ 146,342.20
ENCARGOS SOCIAIS (% MOD C+D) R$ 146,342.20
EQUIPAMENTOS (Guindastes, Caminhão Munck, Perua Kombi e Onibus) R$ -
ANDAIMES R$ -
PINTURA (JATO E ACABAMENTO) 100% R$ -
CONTAINER R$ -
ALUGUEL DE FERRAMENTAS (MÁQUINAS DE SOLDA, ESMERILHADEIRAS E OUTROS) R$ -
MATERIAIS DE APLICAÇÃO 0% R$ -
REFEIÇÕES / HOSPEDAGEM R$ 38,256.84
ELETRODOS R$ -
VARETAS R$ -
GASES R$ -
EPI'S + UNIFORMES (% SOBRE MOD) 5.00% R$ 7,317.11
FERR / MAT. CONS (% SOBRE MOD) 0.00% R$ -
RIGGING / RIGGER (% SOBRE TRANSPORTE) 0.00% R$ -
QUALIFICAÇÃO DE SOLDADORES / PROCEDIMENTOS (% SOBRE SOLDADORES) 10.00% R$ 1,923.52
CONTROLE DE QUALIDADE (% SOBRE MOD) 0.00% R$ -
VISITA TÉCNICA I / PROJETOS R$ -
VISITA FAMÍLIAR R$ -
EXAMES MÉDICOS R$ 446.61
INST. PROVISÓRIA (% SOBRE MOD) 3.00% R$ 4,390.27
Total MDO R$ 275,755.96
Equipamentos R$ -
Terceiros R$ -
TOTAL GERAL R$ 275,755.96
BDI
% Total Lucro real (%)
LUCRO OPERACIONAL 27.02% R$ 74,519.06 17.80%
ADM CENTRAL 0.00% R$ -
ADM SOBRE TERCEIROS 0.00% R$ -
T B =2 %;O T C =5 %;P G =2
ISS 2.00% R$ 8,370.77
%;CP=5%;PI=2%
PIS / PASEP 0.65% R$ 2,720.50
COFINS 3.00% R$ 12,556.16
CSLL 2.88% R$ 12,053.91
IRRF 7.40% R$ 30,971.86
CPMF 0.38% R$ 1,590.45
TOTAL GERAL 6.53% R$ 142,782.72 ÍNDICE
TOTAL GERAL DE RESUMO + BDI R$ 418,538.69 2.86
CONTINGENTES 2% R$ 8,370.77
NEGOCIAÇÃO: 5% R$ 21,345.47
Materiais R$ -
Materiais c/ BDI R$ -
Total R$ 448,254.93
ITEM DESCRIÇÃO QTDE UNID. VL UNIT. VL TOTAL
1 -
2 -
3 -
4 -
5 -
6 -
7 -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
Total Material de Aplicação -
FRETES ………………………. 5%
EMBALAGENS ……………… 5%
OUTROS IMPOSTOS ……….. 5%
TOTAL …………………………………………
R$ TOTAL
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -
R$ -