You are on page 1of 16

Article

Metamorphosis

Standard Critical Path and Selection


1–16
© 2019 Indian Institute of
Management, Lucknow
of Most Economic and Quality Reprints and permissions:
in.sagepub.com/journals-permissions-india

Contractors for Construction of DOI: 10.1177/0972622519872653


journals.sagepub.com/home/met

Thermal Power Plant: A Case


Study in NTPC

D. K. Choudhury1

Abstract
In India, most of the thermal power plants were built by National Thermal Power Corporation (NTPC) Ltd and different state
electricity boards. The thumb rule indicates that out of the total project construction cost, 70 per cent goes to the cost of project
materials, while 30 per cent goes to the cost construction work which leads us to select the most competitive material suppliers and
construction contractors. The objectives of this research work are (a) to select a contractor based on cost economy, (b) to find out
the standard critical path for constructing a thermal power plant, and (c) to identify the critical activities in constructing a 500 MW
thermal power plant. Through literature review, six important factors were identified to judge the quality of the contractor before
awarding the contract. In project management, the selection of contractor on the basis of probability of their performance comes
within the purview of decision under risk, and hence decision tree has been used as a methodology for the selection of contractor. For
computing the critical path, the project network for the construction of the thermal power plant was constructed. The five thermal
power projects of NTPC—NTPC Korba, NTPC Talcher, NTPC Rihand, NTPC Sipat, and NTPC Simhadri—were considered, and the
construction data of these five projects were used to compute the critical path. Since the completion data of different activities of five
projects at different geographical locations with different climates, different site conditions, and different conglomerate of workers
were used, so the critical path estimated was accepted as the standard critical path.

Keywords
Power Project, Decision Tree, Project Network, Critical Path, Project Activities

Introduction to over 40 million families in rural and urban areas by


December 2018 at a cost of US$2.5 billion.
The power sector plays a very important role in the devel- Indian power sector is undergoing a significant change
opment of national economy. Sources of power generation that has redefined the industry outlook. Sustained economic
range from conventional sources such as coal, lignite, growth continues to drive electricity demand in India. The
natural gas, oil, hydro and nuclear power to viable non- Government of India’s focus on attaining “Power for All”
conventional sources such as wind, solar, and agricultural has accelerated capacity addition in the country. At the
and domestic waste. Demand of electricity in India has same time, the competitive intensity is increasing at both
increased rapidly and is expected to rise further in the years the market and supply sides (fuel, logistics, finances, and
to come. In order to meet the increasing demand for elec- manpower).
tricity in India, massive addition to the installed generating Total installed capacity of power stations in India stood
capacity is required. at 330,260.53 megawatt (MW) as on May 2017. The
India, at this moment, ranks 26th in the World Bank’s Ministry of Power has set a target of 1,229.4 billion units
list of electricity accessibility in 2017. (BU) of electricity to be generated in the financial year
In September 2017, the Government of India launched 2017–2018. To attain this goal, we need to construct more
the “Saubhagya” scheme to provide electricity connections and more power plants within our available resources.

1 Gitarattan International Business School, Delhi, India.

Corresponding author:
D. K. Choudhury, Gitarattan International Business School, PSP 2A & 2B Complex-II, Madhuban Chowk, Sector 14, Rohini, Delhi 110085, India.
E-mail: dkc.ashokvihar@gmail.com
2 Metamorphosis

India is having huge coal deposit, and hence from the of a construction project. The quality of the decision largely
economic point of view, the thermal power plants are easy depends on the selection of an appropriate technique. For
to run with coal. But for constructing the power plants, we selecting an appropriate multi-criteria decision-making
need to choose the agencies who have expertise, adhere to (MCDM) method under a fuzzy environment, Hamed
quality, and at the same time are economic also. From this et al.1 conducted a study to compare statistically the perfor-
consideration, this research work has been carried out to mances of 10 MCDM techniques and found analytic
select a contractor who will be most economic and at hierarchy process (AHP) ranking method significantly
the same time enjoys the reputation of providing good sensitive to uncertainty levels. But the drawback of AHP
quality workmanship. The other two goals of this research is that the process is very large, elaborate, and not easy in
work are to find out the standard critical path with least computing the result.
variation for constructing a thermal power plant and to It has been observed that under uncertain conditions,
identify the critical activities in constructing a 500 MW when a decision-maker is confronted with more than one
thermal power plant. alternative solutions in a multiple event problem, research-
ers used decision tree technique by comparing the expected
value or expected utility of the available alternatives. Hulett2
Key Players in Power Sector stated that the term “expected value” or “expected utility”
in India indicates that there are alternative outcomes that can be
The power sector in India is mainly governed by the described only with statements associated with probability.
Ministry of Power. There are three major pillars of power The researcher also prescribed the ways to quantify uncer-
sector. These are generation, transmission, and distribution. tainty. When assigning a unique probability distribution is
As far as generation is concerned, it is mainly divided into not possible, a prior (posterior) over the possible distribu-
three sectors: central sector, state sector, and private sector. tions can be assessed by the decision-maker and Monte
Major Public Sector Undertakings (PSUs) involved Carlo simulation can be used to quantify uncertainty as also
in the generation of electricity include National Thermal to obtain the expected utilities.3
Power Corporation (NTPC) Ltd., Nuclear Power Corporation Researchers also used data envelopment analysis (DEA)
of India (NPCIL), and National Hydroelectric Power for conducting a performance analysis. In the supplier/
Corporation (NHPC) Ltd. Besides PSUs, several state-level contractor selection process, a little attention has been paid
corporations such as Jharkhand State Electricity Board to dual-role factors by the researchers. Jingjing et al.4 pro-
(JSEB), Maharashtra State Electricity Board (MSEB), posed a two-step approach to select suppliers using dual-role
Kerala State Electricity Board (KSEB), and Gujarat State factors. The authors conducted supplier selection in a com-
Electricity Corporation (GSEC) Ltd are also involved in the petitive environment using combination of DEA and game
generation and intra-state distribution of electricity. theory and demonstrated successfully the application of the
Other than PSUs and state-level corporations, private procedure to a data set of 18 suppliers.
sector enterprises also play a major role in generation, Often, the decision-makers are uncertain about one or
transmission, and distribution. About 61,409.24 MW of more probabilities of interest while selecting the preferred
total installed capacity is generated by private sector. course of action. The researchers from their experimental
India is the sixth largest in terms of power generation. findings ascertained that the uncertainty (ambiguity) might
About 65 per cent of the electricity consumed in India is affect decision-maker’s preferences. As a result, Emanuele
generated by thermal power plants, 22 per cent by hydroe- et al.3 argued that the decision-makers might wish to
lectric power plants, 3 per cent by nuclear power plants, incorporate ambiguity aversion in the analysis. The work
and the rest 10 per cent is generated by other alternate of Howard5 (1996) established a systematic sequence for
sources such as solar, wind, biomass, etc. It has been found the solution of decision analysis problems.6–8 Dillon et al.9
that about 53.7 per cent of India’s commercial energy stated that a key step in establishing the sequence is the
demand is met through the country’s vast coal reserves. development of a quantitative model.
In project management, the project completion time
depends on many factors, but mainly on selection of good
Literature Review materials suppliers and good construction contractors. Once
In constructing any project, it is very important for the a contract is awarded to a supplier or contractor, it becomes
project manager to take proper decision. Mainly two difficult to cancel the contract as it takes long time to repeat
important decisions are required to be taken in project con- the process of awarding the contract to a new agency. This is
struction. These are selection of good materials suppliers why for selection of suppliers/contractors, researchers sug-
and selection of good construction contractors as good sup- gested to verify the competence of suppliers/contractors at
pliers contribute in improving product quality, reducing the time of evaluation of their offers. Russell et al.10 pointed
lead time, and cost, while good contractors help to gain a out that the financial capability (FC) is one of the con-
competitive advantage over others by achieving milestones siderations of selecting a supplier/contractor and can be
Choudhury 3

judged on the basis of credit ratings, bank arrangements, the expected project completion probability according to
bonding capacity, and bank’s financial statement of the a set of specified durations (optimistic time, most likely
supplier/contractor. Merna and Smith11 focused on three time, and pessimistic time) as per each identical activity.
factors which are financial stability; managerial capability; To estimate the probability of completing a project by a
and organizational strength, expertise, and experience of given date, researchers used the classical PERT approach
comparable construction. The Manoliadis et al.12 men- using the path with the longest duration as the critical path.
tioned that the qualification-based selection (QBS) may be Soroush18 studied the “most critical path” problem and for-
used for the procurement of professional services. This is a mulated it as an optimal path problem considering two attrib-
good suggestion as there is a substantial difference between utes fractional objective function in a deterministic network.
the performance of an industrial training institute (ITI)- The author presented an approach for the solution of optimal
qualified welder and an ordinary welder. path problem which also provides the solution to the most
Severson et al.13,14 stated that the contractors’ financial critical path problem. Soroush18 with illustrative examples
data in the form of the assets, liabilities, and stockholders’ and computed results argued that the proposed algorithm
equity portion of the contractors’ balance sheet, as well as provides much accurate estimates for the probabilities of
the contractors’ income statement are to be examined for completion time than those of the classical approach.
awarding a contract as the aforementioned documents
are indicators of contractors’ likelihood of deviating from
the contract and making a claim. The authors opined that the Scope and Objective of the
trend of financial data of construction contractors are the Research Work
indicators of contractors’ sustainable capacity of financing a
This study considered the construction of 500 MW capa-
contract, and this is the most important decision parameter in
city of power plants by NTPC with following research
awarding a contract. Saaty15 suggested to consider the fol-
objectives:
lowing factors for making decision on engaging a contractor
in a project work: (a) the contractor’s permanent place of
1. To select most economic contractor backed up with
business, (b) adequacy of plant and equipment to do the
quality workmanship.
work properly and expeditiously, (c) suitability of FC to
2. To find out the standard critical path for construc-
meet obligations required by the work, (d) appropriateness
tion of thermal power plant.
of technical ability and experience, (e) performance of work
3. To identify the critical activities for the construction
of the same general type and on a scale not less than 50 per
of thermal power plant.
cent of the amount of the proposed contract, (f) the fre-
quency of previous failures to perform contracts properly
or fail to complete them on time, (g) the current position The entire data used for conducting this study was collected
of the contractor to perform the contract well, and (h) the from NTPC.
contractor’s relationship with subcontractors, or employees.
In this present era and under increased competition, the Research Methodology
construction agencies make deliberate attempt to complete
the projects in the foresighted time. The project manage- The thermal power project construction work proceeds
ment is considered effective when the project is completed through uncertain conditions. For constructing a thermal
without any time and cost overrun. In construction, Project power plant, it is required for the client to select a suitable
Evaluation and Review Technique (PERT) and Critical Path contractor from available alternatives in an uncertain condi-
Method (CPM) are regarded as two contemporary planning tion. Sharma19 stated that the decision tree is a technique that
and scheduling techniques. Mazlum et al.16 applied fuzzy can be used for taking a decision in an uncertain condition.
PERT and fuzzy CPM in fuzzy project management of an Podgorelec et al.20 found decision tree as a reliable and
online internet branch. The authors expressed that these effective technique in decision-making with the application
techniques can be applied in the programming of large-scale of gathered information. The selection of contractor on the
projects as well. These two techniques provide great benefit basis of probability of their performance comes within the
to the decision-makers as these are easy to apply. purview of decision under risk.21,22 Therefore, on the basis
Remon17 argued that PERT is the most essential in con- of recommendations of researchers, the decision tree has
struction projects as the activities in a project have optimis- been used as a methodology for the selection of contractor.
tic, most likely, and pessimistic durations. In his research The decision tree has been constructed considering three
paper, the author focused on the probability of completion decision branches which indicate three alternative courses of
of repetitive construction projects within the contractual actions. These decision branches, originated from decision
duration using Line of Balance technique. The author node, represent three contractors out of which one is to be
mentioned about a simplified software called Repetitive selected. The first branch terminates at the first event node
Projects Evaluation and Review Technique (RPERT) where from five chance branches, called state of nature,
designed by Java programming to provide information on have emanated. These five branches represent the five states
4 Metamorphosis

of nature: (a) similar work experience of the contractor (c) equipment and machinery resource (EMR), (d) financial
(SWEC), (b) manpower resource of the contractor (MRC), capability (FC), and (e) past performance have been identi-
(c) equipment and machinery resource of the contractor fied by researchers10–15 to judge the quality, competence, and
(EMRC), (d) financial capability (FC), and (e) feedback suitability of the contractor before selecting and awarding
from past client (FPC). Each of these five states of nature the contract.
branches terminated at second event node where from two For awarding a contract for supply, fabrication, and
branches originated and ultimately terminated at the last installation of utility piping, a real-life situation was con-
event node. Out of these two branches, one was represented sidered and a case study was conducted at NTPC Contract
by fair chance of completing the project in time and the other Services, Noida.
was represented by chance of project not completing in time. The decision tree has been constructed considering
The probability of completing in time and the probability of three decision branches which indicate three alternative
not completing in time were decided in consensus by project courses of actions. These decision branches originated
management executives of NTPC. At the last node of the from decision node represent three contractors out of which
decision tree, the pay-offs, that is, the prices quoted by the one is to be selected. The first branch terminates at the first
contractor were considered for decision-making. The event node where from five chance branches, called state
expected monetary value of each alternative at the last but of nature, have emanated. These five branches represent
one node of the decision tree was computed and the the five states of nature: (a) SWEC, (b) MRC, (c) EMRC,
minimum value pertaining to the course of action (alterna- (d) FC, and (e) FPC. Each of these five states of nature
tive) has been selected as most preferred contractor for branches terminated at second event node. From the second
awarding the contract. event node, two branches originated: (a) pay-off without
The construction of thermal power project includes large any liquidated damage and (b) pay-off after liquidated
number of interrelated activities (or tasks) which are required damage as per contract agreement. At the last node of the
to be completed in a specified sequence and time. The PERT decision tree, the pay-offs, that is, the prices quoted by
developed by a research team in 1956–1958 for planning the contractor, have been proportioned for each of five
and scheduling the activities for completing the nuclear factors for decision-making. The summation of the product
submarine missile project involving thousands of activities of probability assigned to each state of nature (decided in
consensus with NTPC project site management) and the
was found to be the most useful by researchers for projects
pay-off (the amount quoted by the individual contractor
having element of uncertainty in estimating duration of
for executing the contract) became the expected pay-off at
project, critical areas, and critical path of a project.19 In view
the last but one node of the decision tree. Applying the
of this, the PERT has been used for identification of critical
backward induction and same methodology as mentioned
activities and estimation of critical path by developing a
above, the resultant pay-off at each of the first chance node
network which is the graphical representation of logical
has been computed which is expected monetary value of
sequence of various activities to be performed for comple-
the contract and the minimum value pertaining to the
tion of thermal power plant. A case study was conducted in
course of action (alternative) has been selected as most
NTPC Contract Services at Noida. The data were collected preferred contractor for awarding the contract.
from project task forces of NTPC Korba, NTPC Talcher,
NTPC Rihand, NTPC Sipat, and NTPC Simhadri for (a) The Decision Table: Based on the above considera-
estimating and standardizing the critical path. tions and the data collected from NTPC, the deci-
sion tables (Tables 1–3) have been developed and
Selection of Most Economic and are shown in the following.
(b) Construction of Decision Tree: Considering all the
Quality Contractor details given in Tables 1–3, the decision trees have
For the construction of thermal power plant, the following been constructed and are shown in Figures 1–3. The
main contract packages are usually prepared by NTPC: probability of project completion in time is denoted
by PPCT and the probability of not completion in
1. Main plant time is denoted by PNCT.
2. Coal handling plant (c) Evaluation of Alternatives: The three alternatives
3. Ash handling plant have been evaluated by computing the expected
4. Water treatment plant monetary value of the proposals using the decision
5. Boiler plant trees as shown in Figures 1–3.
6. Turbo-generator plant
7. Fuel oil handling plant For Contractor 1, the expected monetary value of the proposal
8. Utility services = [(92 × 0.6) + (87.4 × 0.4)] + [(69 × 0.6) + (65.55 × 0.4)] +
[(34.5 × 0.3) + (32.78 × 0.7)] + [(23 × 0.6) + (21.85 × 0.4)] +
The five important factors such as (a) similar work experi- [(11.5 × 0.3) + (10.93 × 0.7)]
ence (SWE) of the company, (b) manpower resource (MR), = `187.72
Choudhury 5

Table 1.  Decision Table for First Alternative: Contractor 1

Pay-off
Contra State of Contractor’s Loading
ctor’s Nature Rating against Pay-off
Quoted Considered Against Each Each state of Estimated Pay-off
Price for Decision- State of Probability of Nature (In Against Each (` in Lakhs) Without and
(` in Lakhs) making Nature completion Percentage) (` in Lakhs) With Liquidated Damage
230 SWE Very good 1. P = 0.6 for fair chance 40 `92 1. `92 without LD when
of completion in time P = 0.6
2. P = 0.4 2. `87.40 with LD
for chance of not when P = 0.4
completing in time
230 FC Very good 1. P = 0.6 for fair chance 30 `69 1. `69 without LD when
of completion in time P = 0.6
2. P = 0.4 2. `65.55 with LD
for chance of not when P = 0.4
completion in time
230 EMR Good 1. P = 0.3 for average 15 `34.5 `34.5
chance of completion in without LD when P = 0.3
time
2. P = 0.7 2. `32.78 with LD when
for chance of not P = 0.7
completion in time

230 MR Very good 1. P = 0.6 10 `23 1. `23


for fair chance of without LD when P = 0.6
completion in time
2. P = 0.4 2. `21.85 with LD when
for chance of not P = 0.4
completion in time
230 FPC Good 1. P = 0.3 for average 5 `11.5 1. `11.5
chance of completion in without LD when P = 0.3
time
2. P = 0.7 for chance of 2. `10.93 with LD
not completion in time when P = 0.7
Source: The Author, using the data collected from project sites of NTPC (National Thermal Power Corporation).

Table 2. Decision Table for Second Alternative: Contractor 2

Pay-off
State of Pay-off Estimated
Nature Loading Against Each
Contractor’s Considered Contractor’s Against State of Pay-off
Quoted Price for Decision- Rating Probability of Each (In Nature (` in Lakhs) Without or
(` in Lakhs) making Against Each Completion Percentage) (` in Lakhs) With Liquidated Damage
242 SWE Very good 1. P = 0.6 for fair chance 40 `96.8 1. `96.8 without LD
of completion in time when P = 0.6
2. P = 0.4
for chance of not 2. `91.96 with LD
completion in time when P = 0.4
242 FC Good 1. P = 0.3 for average 30 `72.6 1. `72.6 without LD
chance of completion in when P = 0.3
time
2. P = 0.7 2. `68.97 with LD
for chance of not when P = 0.7
completion in time
(Table 2 continued)
6 Metamorphosis

(Table 2 continued)

Pay-off
State of Pay-off Estimated
Nature Loading Against Each
Contractor’s Considered Contractor’s Against State of Pay-off
Quoted Price for Decision- Rating Probability of Each (In Nature (` in Lakhs) Without or
(` in Lakhs) making Against Each Completion Percentage) (` in Lakhs) With Liquidated Damage
242 EMR Good 1. P = 0.3 for average 15 `36.3 1. `36.3
chance of completion in without LD when P = 0.3
time
2. P = 0.7 2. `34.77 with LD when
for chance of not P = 0.7
completion in time
242 MR Good 1. P = 0.3 10 `24.2 1. `24.2
for average chance of without LD when P = 0.3
completion in time
2. P = 0.7 2. `22.99 with LD when
for chance of not P = 0.7
completion in time
242 FPC Average 1. P = 0.1 for less chance  5 `12.1 1. `12.1
of completion in time without LD when P = 0.1
2. P = 0.9 for chance of 2. `10.89 with LD
not completion in time when P = 0.9
Source: The Author, using the data collected from project sites of NTPC (National Thermal Power Corporation).

Table 3.  Decision Table for Third Alternative: Contractor 3

Pay-off Loading
State of Nature Against Pay-off
Contractor’s Considered Contractor’s Each State of Estimated Pay-off
Quoted Price for Decision- Rating Against Probability of Nature (In Against Each (` in Lakhs) Without or
(` in Lakhs) making Each Completion Percentage) (` in Lakhs) With Liquidated Damage
237 SWE Good 1. P = 0.3 for average chance 40 `94.8 1. `94.8 without LD
of completion in time when P = 0.3
2. P = 0.7 for chance of not 2. `90.06 with LD
completion in time when P = 0.7
237 FC Good 1. P = 0.3 for average chance 30 `71.1 1. `71.1 without LD
of completion in time when P = 0.3
2. P = 0.7 for chance of not 2. `67.55 with LD
completion in time when P = 0.7
237 EMR Very good 1. P = 0.6 for fair chance of 15 `36.3 1. `36.3
completion in time without LD when P = 0.6
2. P = 0.4 for chance of not 2. `34.77 with LD when
completion in time P = 0.4
237 MR Very good 1. P = 0.6 for fair chance of 10 `24.2 1. `24.2
completion in time without LD when
P = 0.6
2. P = 0.4 for chance of not
completion in time 2. `22.99 with LD when
P = 0.4
237 FPC Good 1. P = 0.3 for average chance  5 `12.1 1. `12.1
of completion in time without LD when P = 0.3
2. P = 0.7 for chance of not 2. `10.89 with LD
completion in time when P = 0.7
Source: The Author, using the data collected from project sites of NTPC (National Thermal Power Corporation).
Choudhury 7

Figure 1.  Decision Tree (Part 1) for Contractor 1


Source: The Author, applying the fundamental principles of “Operations Research”.

Similarly, for Contractor 2, the expected monetary value likely time (tm), the optimistic time (to), and the pessimistic
of the proposal = `234.45 time (tP) were computed with following considerations
Similarly, for Contractor 3, the expected monetary value using the collected set of data pertaining to NTPC Korba,
of the proposal = `230.35 NTPC Talcher, NTPC Rihand, NTPC Sipat, and NTPC
Based on the evaluation done above, the contract is to Simhadri:
be awarded to Contractor 1.
1. Most likely time (tm): The mean of the time taken to
complete each activity of the collected five data
Estimation of Critical Path series was considered.
First, the project network has been constructed which is 2. Optimistic time (to) : The least time for each activity
shown in Figures 4–6. The critical path was computed from collected five data series was considered.
based on the data collected from contracts department of 3. Pessimistic time (tP) : The highest time for each activ-
NTPC, Noida. For finding out the critical path, the most ity from collected five data series was considered.
8 Metamorphosis

Figure 2.  Decision Tree (Part 2) for Contractor 2


Source: The Author, applying the fundamental principles of “Operations Research”.
Choudhury 9

Figure 3.  Decision Tree (Part 3) for Contractor 3


Source: The Author, applying the fundamental principles of “Operations Research”.
10 Metamorphosis

Figure 4.  Project Network (Part 1) for Construction of Thermal Power Plant
Source: The Author, applying the fundamental principles of “Operations Research”.
Choudhury 11

Figure 5.  Project Network (Part 2) for Construction of Thermal Power Plant
Source: The Author, applying the fundamental principles of “Operations Research”.
12 Metamorphosis

Figure 6.  Project Network (Part 3) for Construction of Thermal Power Plant

The computed values of tm, to, and tp are furnished in Table 4. in NTPC, Noida where from all the relevant data pertaining
Using the expected completion time as computed and to piping contract of NTPC, Korba and other required
furnished in Table 4, the earliest starting time, latest starting project construction data were collected. The piping work
time, and slack for each activity have been computed and was awarded to Stewarts and Lloyds of India Ltd, Kolkata
presented in Table 5. From Figure 5 and the slack computed by NTPC. It has been found that NTPC, as per their
in Table 5, it is evident that the critical path is 1–8–9–10–11– standard practice, asked the contractors to submit along
12–13–14–15–45 and the length of the critical path is 58.89 with their bid (a) the solvency certificate issued by their
months. banker to verify the contractor’s FC, (b) the completion
certificate issued by the client for executing the contracts
in last three years for assessing the performance and
Discussion of the Result verifying if the contractors do have similar nature of work
The decision tree has been used in this article for finding experience, and (c) the list of available construction
out the most suitable contractor. The study was conducted equipment and manpower available with them. Based on
Choudhury 13

Table 4.  Completion Time of Project Activities for Construction of a Thermal Power Plant (500 MW Capacity)

Expected
Most Likely Optimistic Pessimistic Completion
Project Time (tm) Time (to) Time (tP) Time (te)
Activities Name of Project Activities in Months in Months in Months in Months
Civil Works
A1 Piling and foundation for chimney 4.3 3.8 5.2 4.37
A2 Construction of super structure 7.3 6.8 8.5 7.42
B1 Levelling of boiler plant area 5.2 4.3 9 5.68
B2 Piling and foundation of boiler 14.3 13.6 15.5 14.38
C1 Levelling of Mill Bunker base area 10.3 9.8 12.3 10.55
C2 Piling and foundation of Mill Bunker 11.3 10.7 12.4 11.38
C3 Bunker base structural erection 5.5 4.5 6.8 5.55
C4 Roof clad floor 5.2 4.7 7.3 5.47
C5 Precast slab 3.3 2.5 4.9 3.43
C6 Finishing touch 2.3 1.6 3.8 2.43
D1 Levelling of turbo-generator main plant area 12.3 11 14 12.37
D2 Piling and foundation of turbo-generator plant 15.3 13.9 17 15.35
E1 Piling and foundation of turbo-generator 5.3 3.8 5.8 5.13
E2 Structural erection of turbo-generator plant 5 4.6 6.3 5.15
E3 Precast slab for turbo-generator control bay 4 3.7 5.7 4.90
E4 Roof clad floor of turbo-generator control bay 4.2 3.5 6.5 4.47
E5 Balance finish 2.3 1 3 2.2
E6 Underground trench for turbo-generator bay 8.3 6.8 8.9 8.15
F1 Construction of unit pump house 21.4 20.5 21.5 21.27
F2 Construction of fire-fighting building 17.5 17 18.3 17.55
F3 Construction of switch gear building 12 10.6 13.4 12
F4 Laying of intake and discharge ducts 18.8 17.6 20.1 18.82
G1 Construction of intake pump house 20 19.5 22.5 20.33
G2 Pedestals for laying pipelines 14.2 13.5 16.1 14.40
H1 Construction of diesel generator set building 22 20.9 23.8 22.12
H2 Construction of DM plant building 26 25.1 27.6 26.12
H3 Construction of cooling tower and SG room 22 20.7 24 22.12
H4 Construction of cooling towers 26 25.5 27.3 26.13
I1 Construction of coal handling plant 15 14.3 16.8 15.18
I2 Construction of balance portion of coal handling plant 13.3 12.7 15.3 13.53
J1 Construction of ash pump house 24.2 23.1 24.8 24.12
J2 Construction of fuel oil plant 24.1 22.8 25.5 24.12
J3 Construction of hydrogen plant 26.3 25 28 26.37
J4 Construction of compressor house 24.6 23.1 26 24.58
J5 Construction of steel trestles for pipes and cable support 24.6 23.5 25.9 24.63
J6 Construction of water treatment plant 17.6 16.6 18.4 17.57
Mechanical Works
B1 High pressure piping 9.5 8.3 9.8 9.35
C1/ Erection of boiler 22 20.6 23.8 22.06
C2// Erection of milling plant 10.3 9.4 10.8 10.23
D1/ Erection of overhead cranes 2.6 1.5 3.5 2.57
D2/ Erection of condenser 3.5 2 4.8 3.33
D3/ Turbo-generator box up 11.2 9.3 13 11.18
D4/ Flushing of pipelines 2.5 1.6 3.5 2.52
E1/ Cooling tower erection 4.6 3.1 5.7 4.53
G1/ Erection of coal handling plant equipment (Bay 1) 13.5 12.5 15.4 13.65
G2/ Erection of coal handling plant equipment (Bay 2) 2.7 1.7 3 2.58
F2// Installation of fire-fighting system 5.3 4.1 6.7 5.33
F1// Erection of utility piping system 6 5.5 7.5 6.16
E1// Testing of cooling tower system 2.5 1.5 4 2.58
G1// Installation of make-up pumps 6.6 5.5 7.9 6.63
J1/ Installation of equipment and piping system in ash handling 5.4 4 6.3 5.32
plant
J2/ Installation of equipment of fuel oil system 5.7 4 7.4 5.70
(Table 4 continued)
14 Metamorphosis

(Table 4 continued)

Expected
Most Likely Optimistic Pessimistic Completion
Project Time (tm) Time (to) Time (tP) Time (te)
Activities Name of Project Activities in Months in Months in Months in Months
J3/ Installation of equipment of hydrogen plant 3.5 2 5 3.5
J4/ Installation of compressors in compressor house
J6/ Installation of equipment in water treatment plant 7.5 6 8 7.33
H1// Station piping 19 16.3 19.3 18.6
W1/ Fabrication and erection of fuel oil tanks 13 10.5 15 12.92
Electrical Works
K Installation of generators and transformers 5 4.3 6 5.05
L Installation of HT switch gear 5.5 5 6.7 5.05
M Installation of LT switch gear 5.5 5 6.8 5.63
N Installation of cable tray and high tension cables 12 11 13.6 12.10
O Installation of cable tray and low tension cables 12 11 13.6 12.10
Source: The Author, using the data collected from project sites of NTPC (National Thermal Power Corporation).

Table 5.  Computation of Critical Path

Earliest Starting Latest Starting Slack Project Earliest Starting Latest Starting Slack
Project Activities Time (ES) Time (LS) (LS–ES) Activities Time (ES) Time (LS) (LS–ES)
C1(1–2) 10.55 20 9.45 H3 (1–24) 22.12 58.49 36.37
C2(2–3) 21.93 31.38 9.45 B1(1–25) 5.68 22.05 16.37
C3(3–4) 27.48 36.93 9.45 B2(25–26) 20.06 36.43 16.37
C4(4–5) 30.91 40.36 9.45 B1/(1–27) 9.35 58.49 49.14
C5(5–6) 36.38 45.83 9.45 A1(1–28) 4.37 38.15 33.78
C6(6–7) 38.81 48.26 9.45 A2(28–29) 11.79 45.57 33.78
C2//(7–45) 38.81 49.04 10.23 G1(1–30) 20.33 51.86 31.53
D1(1–8) 12.37 12.37 0 G2(1–31) 14.40 15.26 0.86
D2(8–9) 27.32 27.32 0 J5(1–32) 39.03 39.89 0.86
E2(9–11) 29.22 32.25 3.03 I1(1–33) 15.18 42.26 27.08
E5(10–12) 38.89 38.89 0 G1/(33–34) 28.83 55.91 27.08
D1/(12–13) 41.46 41.46 0 J1(1–35) 24.12 53.17 29.05
D2/(13–14) 44.79 44.79 0 J2(1–36) 24.12 52.79 28.67
D3/(14–15) 55.97 55.79 0 J3(1–37) 26.37 54.99 28.62
E1(9–16) 35.47 38.89 3.42 J4(1–38) 24.58 54.91 30.33
E3(9–10) 32.22 32.22 0 E4(10–11) 36.69 36.69 0
F1(1–17) 21.27 52.33 31.06 J6(1–39) 17.57 51.16 33.59
F2(1–18) 17.55 53.16 35.61 K(1–40) 5.50 58.49 52.99
F3(1–19) 12 58.49 46.49 L(1–41) 5.05 58.49 53.44
F4(1–20) 30.66 55.91 25.25 M(1–42) 5.63 58.49 52.86
H4(1–21) 26.13 51.38 25.25 N(1–43) 12.10 58.49 46.39
H1(1–22) 22.12 58.49 36.37 O(1–44) 11.20 58.49 47.29
H2(1–23) 26.12 58.49 32.37
Source: The Author, using the data collected from project sites of NTPC (National Thermal Power Corporation).

the above information and the bid value of lowest bidder, lowest bidder whom they have much trust than the first
that is, `230 lacs, NTPC awarded the contract to Stewarts lowest bidder when the second lowest bidder agrees to
and Lloyds of India Ltd. The comparison between the match the prices quoted by the first lowest bidder. The
prices quoted by the first lowest and second lowest bidders evaluation done by using decision tree gives the impression
shows the difference of `7 lakhs only. Whereas the difference that awarding of contract to the second lowest bidder just
between expected monetary value of the first and second by considering the quoted prices is not justified, if the
lowest bidders, as evaluated above using decision tree, impact of factors such as SWEC, MRC, EMRC, FC, and
comes out to be `43.03 lakhs which is quite substantial. The FPC and probability of completing the work in time are not
PSU companies sometimes award the contract to the second considered. It is recommended that the expected monitory
Choudhury 15

value of the first and second lowest bidders based on the erent conglomerate of workers were used, so the critical
above-mentioned factors should be considered in the path estimated was accepted as the standard critical path.
evaluation process. The present study reveals that the length of the standard
For standardizing the critical path for construction of a critical path of a thermal power plant of 500 MW capacity
thermal power plant, the construction data of five construc- was found to be 58.89 months. The study also indicates
tion projects such as NTPC Korba, NTPC Talcher, NTPC that the activities such as levelling of turbo-generator main
Rihand, NTPC Sipat, and NTPC Simhadri were consid- plant area, piling and foundation of turbo-generator plant,
ered. The project completion time get delayed mainly for precast slab for turbo-generator control bay, roof clad floor
wrong selection of contractor, late release of construction of turbo-generator control bay, balance civil work of turbo-
drawings to contractors, late release of work front to con- generator plant, erection and commissioning of overhead
tractor, and late release of payment to the contractor. cranes, erection of condenser, turbo-generator box up, and
In case of the above-mentioned projects, the best contrac- flushing of entire piping system lie on the critical path,
tor was selected by NTPC taking into consideration their and these activities will have to be taken care of for the
resourcefulness and past performance. The release of con- construction of power plant to avoid any time and cost
struction drawings and payments to the contractor, accord- overrun.
ing to NTPC, was in time. But despite all these standard The outcome of this study will help project managers to
practices, the completion time of all the activities differed make use of decision tree to select good contractors for the
from project to project and this is quite obvious. Therefore, construction of thermal power plant. The present study will
to standardize the critical path, the average time of a par- also assist project managers to make use of PERT network
ticular activity of all the five projects was considered as for the execution of the project. The length of the critical
most likely time, the highest observed time of an activity path provides information on the longest time that is required
out of all the five projects was considered as most pessi- to complete a thermal power plant of 500 MW capacity.
mistic time, and the lowest observed time of an activity out The present study did not include the comparative anal-
of all the five projects was considered as most optimistic ysis of contractors of the above-mentioned projects with
time. Thus, the estimated longest time of 58.89 months has respect to equipment and manpower resources deployed
been accepted as the standard critical path for constructing by them vis-à-vis their time of completion of each activity
a thermal power plant. of those projects. This exercise is left to be done by future
researchers to select more realistic time for completion of
activities. Moreover, further study may be conducted to
Conclusion find out how the length of critical path may be minimized
In this study, the operations research tools have been used using technology.
effectively to select the best alternative in decision-making
process. By and large, in all PSUs, the decision for selecting Declaration of Conflicting Interests
construction contractor is taken on the basis of prices quoted The author declared no potential conflicts of interest with respect
by the contractors against a particular tender floated by to the research, authorship and/or publication of this article.
the organization. It has been explained above under dis-
cussion of result that there may be substantial difference Funding
between the quoted price differential and the differential The author received no financial support for the research,
of expected monetary value of the first lowest and second authorship and/or publication of this article.
lowest bidders. Based on this fact, the decision tree approach
was found justifiable to select appropriate contractor where
References
important factors such as SWEC, MRC, EMRC, FC, and
FPC were considered along with probability of timely   1. Hamed ZS, James PK, Charlote CG, Shalamu A. Statistical
completion of the job by contractors. This consideration and analytical comparison of multi-criteria decision-making
techniques under fuzzy environment. Oper Res Perspect.
provides good impetus on the selection process leading to
2016; 3:92–117.
more accurate result.
 2. Hulett DT. Use decision tree to make important project
For computing critical path, the construction data from decisions, Cost Engineering. 2014 Jul/Aug; 6–21.
NTPC Korba, NTPC Talcher, NTPC Rihand, NTPC Sipat,   3. Emanuele B, Massimo M. Decision analysis under ambigu-
and NTPC Simhadri were considered. These power plants ity. Eur J Oper Res. 2015; 244:823–836.
were constructed by reputed and resourceful contractors   4. Jingjing D, Wei D, Gongbing B, Liang L. A decision model
of India. For standardizing the critical path, the most likely for supplier selection in the presence of dual-role factors.
time, optimistic time, and pessimistic time were found J Oper Res Soc. 2015; 66(5):737–746.
out from the construction data of the above-mentioned  5. Howard RA. Decision analysis: Applied decision theory.
five power plants. Since, the completion data of different In: Hertz DB, Melese J, editors. Proceedings of the Fourth
activities of five projects at different geographical locations International Conference on Operations Research. New
with different climates, different site conditions, and diff- York, NY: Wiley-Interscience; 1966. pp. 55–71.
16 Metamorphosis

  6. Clemen RT. Making hard decision: An introduction to deci- 16. Mazlum M, Ali F, Guneri. CPM, PERT and project man-
sion analysis. Pacific Grove, CA: Duxbury Press; 1997. agement with fuzzy logic technique and implementation on
 7. Howard RA. Decision analysis: Practice and promise. a business. Proc Soc Behav Sci. 2015; 210:348–357.
Manage Sci. 1988a; 34(6): 679–695. 17. Remon FA. RPERT: Repetitive-projects evaluation and
 8. Howard RA. The foundations of decision analysis revis- review technique. Alexandria Eng J. 2014; 53(1):81–93.
ited. In: Edwards W, Miles RF, Jr, von Winterfeldt D, edi- 18. Soroush HM. The most critical path in a PERT network.
tors. Advances in Decision Analysis: From Foundations J Oper Res Soc. 2017; 45(3):287–300.
to Applications. NY. USA: Cambridge University Press; 19. Sharma JK. Operations research theory and application.
2007. pp. 32–56. Delhi: Macmillan Publishers India Ltd; 2009.
  9. Dillon RL, Pate-Cornell ME, Guikema SD. Programmatic 20. Podgorelec V, Kokol P, Stiglic B, Rozman I. Decision trees:
risk analysis for critical engineering systems under right An overview and their use in medicine. J Med Syst. 2002;
resource constraints. Oper Res. 2003; 51(3): 354–367. 26(5):445–463.
10. Russell JS, Hancher DE, Skibniewski MJ. Contractor pre- 21. Vohra ND. Quantitative techniques in management. New
qualification data for construction owners. Constr Manage Delhi: Tata McGrow Hill Education Pvt. Ltd; 2011.
Econ. 1992; 10: 117–129. 22. Chelsea CW, Shigeru DZ. A generalized model of sequen-
11. Merna A, Smith NJ. Bid evaluation for UK public sector tial decision making under risk. Eur J Oper Res. 1984; 18:
construction contracts. Proc Inst Civ Eng, 1990; 88(1); 19–26.
91–105.
12. Manoliadis OG, John-Paris P, Symeon EC. Improving qual-
ification based selection by use of the fuzzy Delphi method. Computation of Critical Path
Constr Manage Econ. 2009; 27:373–384.
Using the expected completion time as computed and
13. Severson GD, Jaselskis EJ, Russell JS. Trends in construc-
tion contractor financial data. J Constr Eng Manage. 1993;
furnished in Table 4, the earliest starting time, latest starting
119(4):854–858. time and slack for each activity have been computed and
14. Severson GD, Jaselskis EJ, Russell JS. Predicting contract presented in Table 5. From Figure 5 and the slack computed
surety bond claims using contractor financial data. J Constr in Table 5, it is evident that the critical path is 1–8–9–10–
Eng Manage. 1994; 120(2): 405–420. 11–12–13–14–15–45 and the length of the critical path is
15. Saaty TL. How to make a decision: The analytic hierarchy 58.89 months. The critical path is shown in Figure 5 by
process. Eur J Oper Res. 1990; 48:9–26. “double arrow”.

You might also like