BILLS OF QUANTITIES FOR THE PROPOSED FREINDS CHURCH

OFFICE BLOCK LUGULU


ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ELEMENT NO 1
FIRST FLOOR WORKS
INTERNAL FINISHES FLOOR

A Hack the existing floor screed to provide the key. 144 Sm 100 14,400
Clean to receive the ceramic floor tiles
B 300x300x8mm ceramic floor tiles 144 Sm 2000 288,000
C CEILINGS 150 Sm 300 45,000
Prepare the suspended slab soffits and sloping
soffits of stairs apply 12mm thick plaster
D DOORS 2 No 16,000 32,000
Standard steel casement door as double leaf with
50x45mm framing size 1200x2400mm high
E Clean the door frames and re-fix 45mm solid flush 12 No 1,000 12,000
doors
F Supply 100mm brass butt hinges 24 No 300 7,200
G WINDOWS 4 No 12,000 48,000
Steel casement windows size 1800x 1800mm high

H Glazing clear sheet glass 4mm to match with putty 14 Sm 1,000 15,000
i.e. replace the broken and fix to new windows
I PAINTING 20 Sm 300 6,000
Prepare and apply super gloss paint to steel general
surfaces
J Prepare and supply undercoats Steiner and 45 Sm 300 13,500
finishing coats of vanish to general surfaces of
timber doors
K Prepare and apply undercoat and finishing coats of 144 Sm 300 43,200
first quality silk vinyl paints to plastered surfaces of
beam ,and suspended soffits of slab
L Prepare the wall surfaces and apply paint as vinyl 300 Sm 300 90,000
silk
M BALUSTRATING AND RAILING 20,000
I. Rails to detail size 75 by 50 mm
II. Handrails supporters size 50 by 50mm

N Supply and fix 2NO Water closets [WC] 20,000

TOTALS CARRIED TO SUMMARY PAGE 654,300


BILLS OF QUANTITIES FOR LUGULU FRIENDS CHURCH OFFICE BLOCK
ITEM DESCRIPTIONS QTY UNIT RATE AMOUNT
ELEMENT NO 0
2ND FLOOR WORKS
INTERNAL FINISHES

FLOOR 144 Sm 300 43,200


A Cement and sand (1:3) screed
B 300 x 300 x 8mm floor tiles 144 Sm 200 18,800
CEILING
C Branding size 75x 50 mm 600 Lm 150 90,000
D 12mm thick chipboards soffits ceiling with 144 Sm 1,200 172,800
“v” joint
E Extra over soffits for forming trap door size 3 No 1,000 3,000
1000 x 1000mm
F Molded cornice plugged size 50 x 50mm 200 Lm 100 20,000
WALLS
G Lime plaster to walls, beams and slopping 600 Sm 300 180,000
soffits of stairs
H DOORS
Standard steel casement door as double leaf 2 No 16,000 32,000
with 50 x 45mm framing size 1200 x 2400
mm high
I 45mm solid core flush door faced both sides 8 No 6000 48,000
with mahogany renewed with and including
sunlight overall size 900 x 2400mm
J Frames to details size 150 x 50 mm 62 Lm 600 37,200
k Architrave to details size 50 x25 62 Lm 100 6,200
L Quadrant bead diameter 25mm 62 Lm 100 6,200
M Supply 100mm brass butt hinges 16 No 300 4,800
N Three lever mortice lock 8 No 3,000 24,000
WINDOWS
O Steel casement window size 1800 x 1800 4 No 12,00 48,000
high
P Ditto size 1200x 1500 12 No 7,500 90,000
Q Glazing clear sheet 4mm to metal with putty 23 Sm 1200 27,600
PAINTING
R Prepare and apply one undercoat and 600 Sm 300 180,000
furnishing coats of 1st quality silk vinyl paint
to general plastered surfaces internally
S Chipboard ceiling surfaces 144 Sm 300 43,200
T Prepare and apply oil paint to steel surfaces 20 Sm 300 6,000
of windows and doors
FASCIA BOARD
U Fascia board size 225 x 25 mm 100 1m 250 25,000

RAIN WATER DISPOSAL


V Allow a sum of Ksh100,000/ for the
following Rain water goods PVC gutters , 100,000
down pipes, brackets , outlets , bends ,
stoppers, clips and swen neck offsets
BALUSTRATING AND RAILING
w III. Rails to detail size 75 by 50 mm 20,000
IV. Handrails supporters size 50 by 50mm

ELEMENTS NO 2 0
EXTERNAL FINISHES

A Cement and sand (1:3) Rendaring to brick 180 Sm 300 54,000


walls and beam and columns
B 50mm thick paving size 600 by 600 all around 70 Sm 1,000 70,000
the structure
EXTERNAL PAINTING
C Prepare and apply one undercoat and two 500 Sm 300 150,000
furnishing coats of crown emulsion paints
to ; rendered surfaces externally
SUB WALLING IN THE ENTRANCE
D 150mm thick block walling in cement and 30 Sm 1,500 45,000
sand (1:3) mix
F Allow a sum of ksh 20,000 for scaffolding i.e. 20,000
(props)
TOTAL CARRIED TO SUMMARY PAGE 1300
BILLS OF QUANTITIES FOR THE PROPOSED FREINDS CHURCH
OFFICE BLOCK LUGULU

SUMMARY PAGE
Item Description Qty Unit Rate Amount
Total summary from page 1 654,300
Total summary from above 654300
Sub Total for 1st and 2nd floor finishes 1308600
Allow Ksh 200,000 electrical works 200,000
GRAND TOTAL 2,419,300

N/B:
- 16% VAT is exclusive in the above amount
- 30% labour of above amount is = KSh. 725,790