Method Statement Submittal Form: TRS-CN-FRM-0019
Method Statement Submittal Form: TRS-CN-FRM-0019
TRS-CN-FRM-0019
General Information
R08-HE4-C20-3050-Shura
Project Name Shura Hotel (HE4) Project Code
Hotel (HE4)
Submittal No. R08-HE04-C20-3050-TSR-MS-C-03 Date 8-Dec-22
Contract No. R08-HE4-C20 Shura Hotel (HE4)
Contract Description Concrete Package
Contractor
Contractor Name TAMEAR Subject MS - Blinding Concrete
Specification No. 031000 & 033000 Drawing Ref. NA
Discipline Civil Other (please specify) NA
Planned Date of Work 15-Dec-22 Submitted For: ☒ Approval ☐ Information
Contractor Authorized Representative
Engineer’s - Comments
Comments:
Status Code
BLINDING CONCRETE
Prepared for
Project
REVISION HISTORY
Prepared by
Reviewed by Reviewed by
REV. Date Description Construction
QA/QC Manager Project Manager
Manager
08 Dec. Mohamed
C0 For Approval Mohamed Gad Ali Maarouf
2022 AlTaweel
TSR-MS-C-03, C0 Page 2 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
REVISION RECORD
TSR-MS-C-03, C0 Page 3 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
TABLE OF CONTENTS
SEC. DESCRIPTION
COVER PAGE
REVISION HISTORY
TABLE OF CONTENTS
1. SCOPE OF WORK
2. PURPOSE
3. ACRONYMS & ABBREVIATIONS
4. REFERENCES
5. RESPONSIBILITIES
6. MANPOWER / EQUIPMENT / MATERIAL
7. METHODOLOGY
8. QHSE PROCEDURE
9. ATTACHMENTS
TSR-MS-C-03, C0 Page 4 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
1. SCOPE OF WORK
The scope of this method statement is to define all the procedures and inspections to be followed
during Blinding Concrete Works in TAMEAR construction site according to Approved Drawings and
TRS Requirements at Shura Hotel (HE4) – Concrete Package. This work includes all the activities
pertaining to the execution of Blinding Concrete that includes surface preparation, erection of
formwork, placement and finishing of the blinding concrete.
2. PURPOSE
The purpose of this method statement is to describe the methods to be implemented and the
resources to be utilized for Blinding Concrete Works and procedure to be followed during the activity
at the mentioned project.
Moreover, to ensure that all the required resources are provided to carry out the activity as stipulated
in the TRS Requirements. All works will be in accordance and conformance to TRS / ATKINS
surveillance, witness, and approval.
4. REFERENCES
TSR-MS-C-03, C0 Page 5 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· ACI 347.
· ASTM C94.
· Approved Drawings.
4.1 PERMITS
Work permits shall be issued as per attached Job Safety Analysis and Safety considerations.
5. RESPONSIBILITIES
5.1.Project Manager
· Ensures that the content of this method statement is understood and implemented at all
times.
· Coordinate with the Construction Manager to ensure that the necessary resources to
implement the approved Method Statement have been allocated to the task.
· Determine all the requirements needed in order to comply with quality and safety standards
and regulations as required.
· The Project Manager is responsible to appoint site supervisory personnel to organize,
coordinate, and oversee the execution of the work detailed in this method statement.
5.2.Construction Manager
· Responsible for the organization and coordination of the work detailed in this method
statement.
· Responsible to provide all resources (Manpower, Materials, and Equipment…etc.) to the site
required to execute the job.
5.3.QA/QC Engineer
· Responsible to assist/advise the construction team to ensure all works comply with specified
requirements.
· Ensure that the materials being delivered and used are in accordance with the project
specifications and approved material submittals.
· Ensure that all related instruments used to put levels for the concrete have valid calibration
date, and the activity is carried out as per approved ITP.
· Hold inspections to verify work is implemented properly prior to TRS inspection.
TSR-MS-C-03, C0 Page 6 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· Responsible for the inspection, preparation of all documents and compiling them for the
inclusion in the final documentation packaged.
5.4.Site Engineer
· Shall be directly involved in the planning and execution of the activities contain formwork and
concrete pouring.
· Monitor and coordinate activities of concrete pouring to ensure compliance with quality,
schedule, and sequence requirements.
· Coordinate inspection requests to QC Engineer.
· Ensure that all relevant inspections are completed and approved.
· Ensure that release for concrete pouring is secured.
· Arrange with the batch plant in-charge for the location required for concrete pouring, timing,
quantity, and specifications.
5.5.Site Foreman
5.7.HSE Manager
TSR-MS-C-03, C0 Page 7 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· He may lead the entire team, maintaining HSE awareness and to create safe culture and
working environment through innovative ideas.
· Planning and coordinating the HSE Trainings for the project.
· Issue necessary directives to Safety Officer / Supervisor and render advice to the Project
Manager, as required.
· Prepare and submit HSE reports to, TRS's / TRS Safety Executives whenever required.
· Carryout HSE inspections at construction sites with reference to all HSE issues
· Liaise with TRS and ATKINSs HSE Departments.
· Take part in incident investigation and reporting of all Incidents.
· Take part / attend in TRS's HSE meetings.
· Monitor and assess HSE measures on visits to sites.
5.8.HSE Officer
· He will ensure that all the activities related to the specified task followed safely and all
workers are wearing PPE.
· Identify hazards and take measure control those hazards and follow JSA/risk assessment.
· He is responsible for monitoring and assessing hazardous and unsafe condition / situations.
· Developing measures to assure personnel safety.
· Correct unsafe acts or conditions through the regular line of authority.
· May exercise authority to prevent or stop unsafe acts when immediate action is required.
· Participate in planning meetings to identify any health and safety concerns inherent in the
operations daily work-plan.
· Inspects the site to ensure it is a hazard-free environment.
· Conduct toolbox meetings.
· Verify that all tools and equipment are adequate and safe for use.
· Promote safe practices at the job site.
· Enforce safety guidelines.
· Trains and carries out drills and exercises on how to manage emergencies.
· Watches out for the safety of all workers and works to protect them from entering
hazardous situations.
· Respond to employees’ safety concerns.
· Advise and instruct on various safety-related topics (noise levels, use of machinery etc.).
· Conduct risk assessment and enforce preventative measures.
· Initiate and organize OHS training of employees and executives.
· Inspect premises and the work of personnel to identify issues or non-conformity (e.g., not
using protective equipment)
TSR-MS-C-03, C0 Page 8 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
5.9.Laboratory Technician
6.1.Manpower
1. Land Surveyors.
2. Assistant Surveyor.
3. Site Engineer.
4. Site Foreman (Civil).
5. QC Engineer.
6. Laboratory Technician.
7. Equipment Operator.
8. Safety Personnel.
9. Labor.
6.2.Equipment
1. Vibrator.
2. Total Stations.
3. Auto Levels.
4. Concrete Pump.
5. Concrete Mixer Truck.
6. Hand Tools.
7. Tower Lights (in case of night work).
8. Testing Equipment for Concrete Slump & Temperature.
6.3.Materials
TSR-MS-C-03, C0 Page 9 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
7. METHODOLOGY
7.1. Ordering
· Once the initial requirement of concrete has been assessed by site engineer, a preliminary order
will be sent to the batchplant production engineer with all necessary information including the
mix design.
· The order will state the date required, approximate start time, approximate quantity and pour
location. These will be recorded on the batch plant daily shipping sheet.
· The concrete will be batch mixed in accordance with the relevant approved mix design and
requirement of TRS specifications.
· Once the first truck mixer has departed and dependent on the requested delivery rate, the batch
plant foreman will decide as per the given time interval on the start time for the batching of the
subsequent loads of concrete to commence, unless otherwise instructed by TSR site engineer.
· Once the mixer arrives at site / designated testing area, QC Engineer will ensure that the
concrete of the correct specifications has been delivered.
· Concrete slump and temperature must be recorded on ACES record sheet.
· Rejected concrete shall be taken out of site and disposed of as per local laws and regulations.
7.3.General
· The area to receive the blinding concrete shall be well compacted and field density should not be
less than the required percent as per Specification for Earthwork specifications.
· Site engineer shall ensure the termite control is applied and protected with polyethylene sheets
as indicated on drawings.
· All benchmarks and control points shall be properly established and secured throughout the
entire duration of works.
· Based on these established data, control points Surveyor with the supervision of Site Engineer
shall locate the exact coordinates of the area for Blinding Concrete base on the approved
drawings.
· For verification of coordinates, TSR shall raise WIR to ATKINS.
TSR-MS-C-03, C0 Page 10 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· Prior to the placing of blinding concrete, Site Engineer & QC Engineer must ensure that the area
to receive the concrete is clean and free from foreign matters.
7.4.Formwork
· Prior to the placing of concrete, the Site Engineer & QC Engineer must ensure that the forms are
clean and placed in accordance with relevant approved drawings.
· Surveyor should set the location of formwork as per drawings.
· Surveyor shall mark the level for top of concrete on the formwork.
· The concrete mixer must be stopped at the designated testing area for inspection of slump and
to obtain samples of concrete testing specimens for compressive strength.
· Cast the concrete within 90 minutes (ASTM C94 Clause 11.7) from the batch plant loading time.
Expired concrete will not be used.
· Concrete will be placed at its locations by direct pouring or concrete pump depending on the
access and as decided by TSR Site Engineer.
· Allowable drop height of concrete is 1.0 m.
· The thickness of blinding concrete shall be as per approved drawing.
· The blinding concrete shall be protected from external damages once the placement is finished.
· The placed blinding concrete shall be levelled properly to achieve neat and smooth finish.
· Curing of Blinding Concrete will be by water or by approved curing compound.
8. QHSE PROCEDURE
8.1.QUALITY
8.1.1. General
· All works will be undertaken in compliance with the quality requirements of the Contract, and the
Quality Management Plan.
· Site inspections will be based on approved ITPs and approved drawings.
8.2.SAFETY
TSR-MS-C-03, C0 Page 11 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
TSR-MS-C-03, C0 Page 12 of 13
METHOD STATEMENT
BLINDING CONCRETE
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
It is important that everyone involved in the project is aware of the environmental policy and
environmental plan and bound by their requirements. Approved documents should make clear the extent
and standard of environmental performance and assessment that is required as well as requirements for
monitoring and reporting. These requirements need to be cascaded down throughout the entire Project
management.
9. ATTACHMENTS
TSR-MS-C-03, C0 Page 13 of 13
APPROVED
INSPECTION & TEST PLAN ITP NO
DATE
DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE
TSR TRS ATKINS
MATERIAL
2.0
RECEIVING
3.0 INSTALLATION
PRE-
4.0
COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by TRS/Consultant Site Inspection Personnel. After this
1 period, TRS/Consultant Inspection may adjust the levels of TRS/Consultant participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as
3 scheduled if the QA/QC organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC
4 organization representative in attendance.
5 If TSR delegates the assigned responsibility to the Subcontractor, then the TMR will have the same degree of responsibility as assigned to TRSDC.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% contractor's Inspection
Page 1 of 1
CHECKLIST Checklist No. Approved Date WIR NUMBER
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP.
ACCEPTED
REJECTED
A General
A1 Surveyor shall set out the points for the location of work area Approved Drawing
B Formwork Inspection
C4 Highest freely drop height for concrete not more than 1.0 m Method statement
REMARKS:
REFERENCE DOCUMENTS:
ASTM
Approved Drawing
Specification for Cast in Place Concrete
QC Manager
Page 1 of 1
Job Safety Analysis
TRS-HS-FRM-0001
Section I -Enter general information about the site and job task.
Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment
requirements.
Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.
1. Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between
steps in case you need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate
all job steps.
2. Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking
about different types of hazards and energy sources.
3. List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy
provided to trigger your thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective
at minimizing the severity and/or likelihood of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4.
Otherwise, repeat steps 2-3 for each of the job steps identified, then proceed to step 8.
4. Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step.
Use the severity table provided. Write the severity number in column D (Severity).
5. Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood
table provided. Write the likelihood number in column E (Likelihood).
6. Multiply the severity number by the likelihood number and enter the product in column F (Risk).
7. Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
i. Very low and low risk ratings of 1-3. This level is generally considered acceptable provided that all control measures are applied.
ii. Medium risk ratings of 4-6. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be
documented on the risk assessment form.
iii. High and Very High-Risk ratings of 8-24. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk to
a medium or low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager must
personally review the activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA.
8. Repeat steps 2-7 for each of the job steps identified.
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or
facility Manager must review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided
for crew members to sign the JSA if desired.
Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
Biological & Environmental Electrical Chemical Gravity/Height Mechanical & Motion
Altitude Arc Flash Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under
Animal Bite/Sting Buried Utilities Chemical Products Excavation/Trench Equipment
Blood-Borne Pathogens Damage to Leads/Cables · Carcinogenic Falling Objects Disintegration of Moving
Contaminated Food/Water Damage to Switches · Combustible/Flammable Floor Openings/Edges Components
Insect-Borne Disease Energized Circuits/Conductors · Explosive Grating Removed Driving/Vehicle Traffic
Pests Inadvertent Energization · Toxic Inadequate Support Ejection of Workpiece/Debris
Poisonous Plants Lack of Isolation/Grounding · Corrosive Lack of Access Ladders/Stairs Entanglement
Precipitation Missing/Damaged Insulation · Reactive Suspended Load Friction
Temperature/Humidity Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Movement/Shifting
Unsanitary Conditions Overload of Circuits Lack of Containment Work Above/Below Others Moving Parts
Weather Stored Energy Leakage/Spills Work at Height/Fall Hazards Pinch/Crush Points
Wind/Turbulence (Batteries/Capacitors) Material Incompatibility Walking/Working Surface Projectiles
Pressure Water Near Electrical Produced/Disturbed by Work · Slippery Rotating Equipment
Abrasive Blasting Conductors · Asbestos · Uneven Sharp Edges, Corners, or Points
Compressed Gases Work Environment
· Lead · Obstructed Shearing
High Pressure Fluid Cluttered
· Silica · Steep Stored Energy
Pressure Testing Confined Space · Moving/Swaying/Pitching (Springs/Accumulators)
· Welding Fumes
Pressure Washing/Blasting Damaged Tools/Equipment · Insufficient/Unstable Striking
Radiation Entrapment · Dust Trapped Between Equipment and
Water Discharges Ergonomic
Intense Light Erosion Awkward Postures/Movement Fixed Structures
Lasers Hazardous Atmosphere Wastes Generated Unexpected/Uncontrolled
· Hazardous Excessive Force/ Exertion
Microwaves · Oxygen Rich/Deficient Heavy/Awkward Load Movement
Naturally Occurring · Contaminants · Non-Hazardous
Sound Repetitive Motion
Radioactivity Radioactive Ignition Sources Same Position
Material Inadequate Ventilation Continuous Noise
Intermittent Noise Vibration
X-Rays Poor Lighting/Glare
Restricted Access/Egress Extreme Noise
Runoff Impact Noise
Reference Table in completing Section III – Job Safety Analysis (Column C – Control Measure)
Most Effective Controls Examples
Elimination Ø Make connections at ground level before erecting Ø Remove a dangerous machine from service
(Remove the hazard altogether) a structure to eliminate work at height Ø Provide power outlets to avoid trailing cords
Substitution Ø Use latex rather than oil-based paints
(Replace the material/process Ø Reduce energy, such as speed, force, amperage, pressure, and temperature
with a less hazardous one) Ø Use water-based detergents instead of organic solvents
Engineering/Isolation Ø Ventilation Ø Isolate hazardous energy sources
Ø Secondary containment
(Design effective control Ø Machine guarding Ø Interlocks
Ø Barriers
measures to protect people and Ø Enclosures Ø Platforms and guardrails
Ø Improve lighting
the environment) Ø Circuit breakers Ø Exclusion zones
Warning Ø Signs Ø Horns Ø Labels
Ø High visibility paint
(Alert people to the hazards) Ø Backup alarms Ø Beepers Ø Tags
Administrative Ø Work rotation to minimize exposure
(Provide training, procedures, Ø Inspect safety equipment Ø Training and supervision
etc.) Ø Good housekeeping practices
PPE Ø Safety glasses Ø Fall harness and lanyards Ø Respiratory protection
Least Effective
(Personal protective equipment) Ø Hearing protection Ø Gloves Ø High visibility vests
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Critical - 6 6 12 18 24
Minor - 1 1 2 3 4
Section III – Job Safety Analysis Risk Assessment (Post Control Measures)
(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)
Activity/Step Hazards Control Measures Severity Likelihood Risk Additional Control measures Severity Likelihood Risk
Provide Induction to all site
personnel, safety briefing before start
Un-familiar to site rules
of job to be ensured, Awareness 1 2 2
and regulations
trainings on routine basis to be
conducted
Ensure provision of basic site
Preparation for Concrete
Lack of site facilities facilities, drinking water, rest 1 2 2
shelters, toilets & etc.
Wear PPE, Ensure provision of first
kit, arrange lighting arrangement if
Insects bite 2 2 4
there will need to work in dark time,
do not work in the darkness
Adopt safe/buddy manual lifting
practices; Mechanical lifting shall
be used for heavy lifts.
Formwork shall be adequately
constructed.
Inspect formwork prior to pouring.
Lifting formwork may
Keep continuous watch during
cause back pain
pour also
Formwork may strike
Wear appropriate PPE and no
personnel and cause
Form Work Personnel shall are allowed to work 2 2 4
injury while de-shuttering
below while shuttering activities
Nails left in formwork
are in be removed after use.
leading to injury
Designated de-nailing area to be
Use of Damaged Tools
deployed.
Do not use damaged or
homemade tools
Use appropriate tools.
Damage tools to be removed from
site.
Wear required PPE, brief people
Contact to Chemical before activity, follow TRSDC 1 2 2
Instructions
Use drip Trays or resistant sheet
Testing of concrete
underneath, ensure provision of spill
Concrete Spill kits, personnel to be trained for to 1 2 2
control and use of emergency spill
kit,
Job Safety Analysis (TRS-HS-FRM-0001)
Revision 01, Rev. Date 29-July-2020 Page 4 of 9
Job Safety Analysis
TRS-HS-FRM-0001