TRS-CN-FRM-0019
General Information
R08-HE4C20 Shura Hotel
Project Name Shura Hotel (HE4) Project Code
(HE4)
Submittal No. TSR-MS-C-02 Date 8-Dec-22
Contract No. R08-HE4C20 Shura Hotel (HE4)
Contract Description Concrete Package
Contractor
Contractor Name TAMEAR Subject MS - TERMITE CONTROL
Specification No. 313116 Drawing Ref. NA
Discipline Civil Other (please specify) NA
Planned Date of Work 15-Dec-22 Submitted For: ☒ Approval ☐ Information
Contractor Authorized Representative
Engineer’s - Comments
Comments:
Status Code
TERMITE CONTROL
Prepared for
Project
REVISION HISTORY
Prepared by
Reviewed by Reviewed by
REV. Date Description Construction
QA/QC Manager Project Manager
Manager
08 Dec. Mohamed
C0 For Approval Mohamed Gad Ali Maarouf
2022 AlTaweel
TSR-MS-C-02, C0 Page 2 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
REVISION RECORD
TSR-MS-C-02, C0 Page 3 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
TABLE OF CONTENTS
SEC. DESCRIPTION
COVER PAGE
REVISION HISTORY
TABLE OF CONTENTS
1. SCOPE OF WORK
2. PURPOSE
3. ACRONYMS & ABBREVIATIONS
4. REFERENCES
5. RESPONSIBILITIES
6. MANPOWER / EQUIPMENT / MATERIAL
7. METHODOLOGY
8. QHSE PROCEDURE
9. ATTACHMENTS
TSR-MS-C-02, C0 Page 4 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
1. SCOPE OF WORK
The scope of this method statement is to define all the procedures and inspections to be followed
during Termite control activity in TAMEAR construction site according to approved drawings,
specifications, data sheet and TRSDC Employer Requirements at Shura Hotel (HE4) – Concrete
Package. This work includes site preparation, cleaning of area, handling and storage, and application
of termite control material.
2. PURPOSE
The purpose of this method statement is to describe the methods to be implemented and the
resources to be utilized for Termite Control and procedure to be followed during the activity at the
mentioned project.
Moreover, to ensure that all the required resources are provided to carry out the activity as stipulated
in the TRSDC Requirements. All works will be in accordance and conformance to TRSDC/ ATKINS
surveillance, witness, and approval.
4. REFERENCES
TSR-MS-C-02, C0 Page 5 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
4.1 PERMITS
Work permits shall be issued as per attached Job Safety Analysis and Safety considerations.
5. RESPONSIBILITIES
5.1.Project Manager
· Ensures that the content of this method statement is understood and implemented at all
times.
· Coordinate with the Construction Manager to ensure that the necessary resources to
implement the approved Method Statement have been allocated to the task.
· Determine all the requirements needed in order to comply with quality and safety standards
and regulations as required.
· The Project Manager is responsible to appoint site supervisory personnel to organize,
coordinate, and oversee the execution of the work detailed in this method statement.
5.2.Construction Manager
· Responsible for the organization and coordination of the work detailed in this method
statement.
· Responsible to provide all resources (Manpower, Materials, and Equipment etc.) to the site
required to execute the job.
5.3.QA/QC Manager
5.4.QA/QC Engineer
· Responsible to assist/advise the construction team to ensure all works comply with specified
quality requirements.
· Monitor implementation of the controls as required.
· Ensure that the surface to receive the application of termite control is prepared and ready as
per manufacturer’s recommendations.
TSR-MS-C-02, C0 Page 6 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· Ensure that the rate of application of termite control material is as per manufacturer’s
recommendations.
· Hold inspections to verify work is implemented properly prior to client inspection.
5.5.Site Engineer
The Site Engineer shall be responsible for the overall civil construction work:
· Become familiar with the method statement and quality & safety requirements for the
activity.
· To ensure all approvals are obtained prior to start the work.
· Ensure that applicator of termite control is qualified person to carry out the application
activity.
· Convey all technical data for execution to personnel related to termite control application and
ensure sufficient understanding of activities to be executed.
· Arrange the required resource to execute the work.
· Control productivity and quality of work.
· Attend risk assessment meeting and follow up implementation of requirements.
· Ensure that Site preparation is done prior to proceed with the application of termite control
to the area of receiving.
· Ensure that the rate of application is as per manufacturer’s recommendations.
· Execute the works in accordance with the approved Drawings, QC requirements, and HSE
plan.
· Protect the area after the application of termite control by appropriate means as per
manufacturer’s recommendations.
· Ensure that all engaged personnel have right PPE, and all equipment are fit and certified to
execute the works.
5.7.HSE Manager
· HSE Manager is responsible to establish and implement an effective HSE management system
in accordance with TRSDC HSE requirements.
· Ensures the HSE management system requirements are implemented and maintained.
· Coordinates with the Site HSE team and the Construction Management team to ensure
effective implementation of the HSE Procedures.
TSR-MS-C-02, C0 Page 7 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· Assist risk assessment team to formulate Method Statement and JSA for specific construction
activities.
· He may lead the entire team, maintaining HSE awareness and to create safe culture and
working environment through innovative ideas.
· Planning and coordinating the HSE Trainings for the project.
· Issue necessary directives to Safety Officer / Supervisor and render advice to the Project
Manager, as required.
· Prepare and submit HSE reports to, Client's / TRSDC Safety Executives whenever required.
· Carryout HSE inspections at construction sites with reference to all HSE issues
· Liaise with Client and Consultants HSE Departments.
· Take part in incident investigation and reporting of all Incidents.
· Take part / attend in Client's HSE meetings.
· Monitor and assess HSE measures on visits to sites.
5.8.HSE Officer
· He will ensure that all the activities related to the specified task followed safely and all
workers are wearing PPE.
· Identify hazards and take measure control those hazards and follow JSA/risk assessment.
· He is responsible for monitoring and assessing hazardous and unsafe condition / situations.
· Developing measures to assure personnel safety.
· Correct unsafe acts or conditions through the regular line of authority.
· May exercise authority to prevent or stop unsafe acts when immediate action is required.
· Participate in planning meetings to identify any health and safety concerns inherent in the
operations daily work-plan.
· Inspects the site to ensure it is a hazard-free environment.
· Conduct toolbox meetings.
· Verify that all tools and equipment are adequate and safe for use.
· Promote safe practices at the job site.
· Enforce safety guidelines.
· Trains and carries out drills and exercises on how to manage emergencies.
· Watches out for the safety of all workers and works to protect them from entering hazardous
situations.
· Respond to employees’ safety concerns.
· Advise and instruct on various safety-related topics (noise levels, use of machinery etc.).
· Conduct risk assessment and enforce preventative measures.
· Initiate and organize OHS training of employees and executives.
TSR-MS-C-02, C0 Page 8 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· Inspect premises and the work of personnel to identify issues or non-conformity (e.g., not
using protective equipment)
· Stop any unsafe acts or processes that seem dangerous or unhealthy.
· Prepare reports on occurrences and provide statistical information to HSE Manager.
· Carry out PTW Monitoring and review.
6.1.Manpower
1. Site Engineer.
2. QC Engineer.
3. Applicator.
6.2.Equipment
1. Spraying equipment.
6.3.Materials
7. METHODOLOGY
7.2.Site preparations
· Ensure that area to receive the application of termite control is cleaned from any foreign matters
which can affect the application process.
· Ensure that area to receive the application of termite control is well compacted and levelled.
TSR-MS-C-02, C0 Page 9 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
· The Termite control sub-contractor should be qualified and approved by TRSDC / ATKINS.
· The rate of application should be as per manufacturer’s Recommendation in attached TDS to
produce the horizontal / vertical barriers and it should cover all the area of receiving.
· The termite treatment shall be provided for the area below the blinding concrete and wherever
as per drawings.
· The anti-termite treated surface shall be protected by approved polyethylene sheet placed over
the soil surface.
· The blinding concrete should be placed within time duration as referred in manufacturer’s
recommendations in attached TDS.
· Application shall be made by a low-pressure spray.
· The area to receive the anti- termite treatment will be barricaded to prevent the people from
entering during or after the application treatment.
8. QHSE PROCEDURE
8.1.QUALITY
8.1.1. General
· All works will be undertaken in compliance with the quality requirements of the Contract, and the
Quality Management Plan.
· Site inspections will be based on approved ITPs and approved drawings.
8.2.SAFETY
TSR-MS-C-02, C0 Page 10 of 11
METHOD STATEMENT
TERMITE CONTROL
PROJECT NAME: Shura Hotel (HE4) – Concrete Package
It is important that everyone involved in the project is aware of the environmental policy and
environmental plan and bound by their requirements. Approved documents should make clear the extent
and standard of environmental performance and assessment that is required as well as requirements for
monitoring and reporting. These requirements need to be cascaded down throughout the entire Project
management.
9. ATTACHMENTS
· TDS.
· MSDS.
· ITP & Checklist.
· JSA.
TSR-MS-C-02, C0 Page 11 of 11
APPROVED
INSPECTION & TEST PLAN ITP NO
DATE
DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE
TSR TRS ATKINS
MATERIAL
2.0
RECEIVING
3.0 INSTALLATION
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by TRSDC/Consultant Site Inspection Personnel. After this
1 period, TRSDC/Consultant Inspection may adjust the levels of TRSDC/Consultant participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as
3 scheduled if the QA/QC organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC
4 organization representative in attendance.
5 If TSR delegates the assigned responsibility to the Subcontractor, then the TMR will have the same degree of responsibility as assigned to TRSDC.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% contractor's Inspection
Page 1 of 1
CHECKLIST Checklist No. Approved Date WIR NUMBER
TSR-TRSDC-IC-02 CIVIL-
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
LOCATION
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP.
ACCEPTED
REJECTED
ITEM
ACCEPTANCE CRITERIA REFERENCES PASS FAIL N/A Comments
No.
B Site Preparation
The area to receive the application of termite control is cleaned from any Manufacturer's
B1
foreign matters which can affect the application process Recommendations
The area to receive the application of termite control is well compacted Manufacturer's
B2
and levelled. Recommendations
C Anti-Termite Application
The anti-termite treatment shall be provided for the area below the Manufacturer's
C1 blinding concrete Recommendations
REMARKS:
REFERENCE DOCUMENTS:
British Standards
ASTM
Approved Drawing
QC Manager
Page 1 of 1
Job Safety Analysis
TRS-HS-FRM-0001
Section I -Enter general information about the site and job task.
Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment
requirements.
Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.
1. Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row
between steps in case you need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to
accommodate all job steps.
2. Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking
about different types of hazards and energy sources.
3. List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy
provided to trigger your thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more
effective at minimizing the severity and/or likelihood of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue
to step 4. Otherwise, repeat steps 2-3 for each of the job steps identified, then proceed to step 8.
4. Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job
step. Use the severity table provided. Write the severity number in column D (Severity).
5. Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the
likelihood table provided. Write the likelihood number in column E (Likelihood).
6. Multiply the severity number by the likelihood number and enter the product in column F (Risk).
7. Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
i. Very low and low risk ratings of 1-3. This level is generally considered acceptable provided that all control measures are applied.
ii. Medium risk ratings of 4-6. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be
documented on the risk assessment form.
iii. High and Very High-Risk ratings of 8-24. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk
to a medium or low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager
must personally review the activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA.
8. Repeat steps 2-7 for each of the job steps identified.
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or
facility Manager must review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided
for crew members to sign the JSA if desired.
Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
Biological & Environmental Electrical Chemical Gravity/Height Mechanical & Motion
Altitude Arc Flash Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under
Animal Bite/Sting Buried Utilities Chemical Products Excavation/Trench Equipment
Blood-Borne Pathogens Damage to Leads/Cables · Carcinogenic Falling Objects Disintegration of Moving
Contaminated Food/Water Damage to Switches · Combustible/Flammable Floor Openings/Edges Components
Insect-Borne Disease Energized Circuits/Conductors · Explosive Grating Removed Driving/Vehicle Traffic
Pests Inadvertent Energization · Toxic Inadequate Support Ejection of Workpiece/Debris
Poisonous Plants Lack of Isolation/Grounding · Corrosive Lack of Access Ladders/Stairs Entanglement
Precipitation Missing/Damaged Insulation · Reactive Suspended Load Friction
Temperature/Humidity Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Movement/Shifting
Unsanitary Conditions Overload of Circuits Lack of Containment Work Above/Below Others Moving Parts
Weather Stored Energy Leakage/Spills Work at Height/Fall Hazards Pinch/Crush Points
Wind/Turbulence (Batteries/Capacitors) Material Incompatibility Walking/Working Surface Projectiles
Pressure Water Near Electrical Produced/Disturbed by Work · Slippery Rotating Equipment
Abrasive Blasting Conductors · Asbestos · Uneven Sharp Edges, Corners, or Points
Compressed Gases Work Environment
· Lead · Obstructed Shearing
High Pressure Fluid Cluttered
· Silica · Steep Stored Energy
Pressure Testing Confined Space · Moving/Swaying/Pitching (Springs/Accumulators)
· Welding Fumes
Pressure Washing/Blasting Damaged Tools/Equipment · Insufficient/Unstable Striking
Radiation Entrapment · Dust Trapped Between Equipment and
Water Discharges Ergonomic
Intense Light Erosion Awkward Postures/Movement Fixed Structures
Lasers Hazardous Atmosphere Wastes Generated Unexpected/Uncontrolled
· Hazardous Excessive Force/ Exertion
Microwaves · Oxygen Rich/Deficient Heavy/Awkward Load Movement
Naturally Occurring · Contaminants · Non-Hazardous
Sound Repetitive Motion
Radioactivity Radioactive Ignition Sources Same Position
Material Inadequate Ventilation Continuous Noise
Intermittent Noise Vibration
X-Rays Poor Lighting/Glare
Restricted Access/Egress Extreme Noise
Runoff Impact Noise
Reference Table in completing Section III – Job Safety Analysis (Column C – Control Measure)
Most Effective Controls Examples
Elimination Ø Make connections at ground level before erecting Ø Remove a dangerous machine from service
(Remove the hazard altogether) a structure to eliminate work at height Ø Provide power outlets to avoid trailing cords
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Critical - 6 6 12 18 24
Minor - 1 1 2 3 4
Section III – Job Safety Analysis Risk Assessment (Post Control Measures)
Conduct TBT
Use of proper PPEs
Follow waste management
procedure
Provide adequate waste
Slip , trip fall Dust
bins at site.
Being hit by falling
Clear the waste on regular
objects
inter wells from the site.
Striking against
House keeping Clean up during the shifts 2 1 2
projecting poorly
Day to day clean before
stacked items or
entering the work
misplaced
removal of unused
materials
materials
Inspections to ensure cleanup
is complete walk
ways should be neat and
tidy
Note: Insert additional rows or print additional sheets as necessary to accommodate all job steps.