Professional Documents
Culture Documents
PART 1 GENERAL
1.01 DESCRIPTION:
C. The areas of concrete repair shall be determined by the Contractor and the CM/CS
and shall include any location where acidic attack of the concrete surfaces has
reached a depth of [12 mm] or deeper and at any air voids, bugholes or
poorly consolidated concrete areas where the specified filler/surfacer materials
cannot be used for filling or surfacing of the concrete.
E. The repair work specified herein is intended to cover the requirements for repair
of concrete only, to a maximum depth of approximately 1-1/2 [38 mm]. If after
blasting and cleaning, an area is discovered that requires a repair greater than 1-
1/2 [38 mm] deep, or an area is discovered that requires repair or replacement of
reinforcing steel, notify the CM/CS so that details may be provided to the
Contractor to complete the repair.
1.03 REFERENCES:
4. ASTM C882: Test Method for Bond Strength of Epoxy Resin Systems.
10. ASTM E337: L.R. Standard Practice Test Method for Measuring Humidity
with a Psychrometer.
C. Use new epoxy, cement base coating, and protective coating materials and use
within the shelf life limitations set forth by the manufacturer. Clearly mark the
shelf life limitations of each container.
F. The Contractor is ultimately responsible for the concrete repair work. Inspections
by the CM/CS or others do not limit the Contractors responsibility.
G. Make all parts of the work accessible for inspections by the CM/CS or others.
Any conditions found to not be in conformance with the specifications shall be
corrected when notified by the CM/CS at no additional cost to the Owner.
I. Any changes in the specified repair mortar work methods shall be allowed only
with the written approval of the CM/CS.
1.05 SUBMITTALS:
B. Submit the following prior to commencing any phase of the work covered by this
section:
12. Manufacturers current printed recommendations and product data sheets for
all repair mortar system products including performance criteria, surface
preparation, ambient condition requirements and applications, volatile
organic compound (VOC) data, and safety requirements.
13. Material Safety Data Sheets (MSDS) for any materials brought on-site
including all repair mortar system materials, solvents and abrasive blast
media.
14. A list of five reference projects where the repair mortar system has been
installed for at least two years including customer names and current
telephone numbers.
16. Certified copies of laboratory test reports, including all test data shall be
submitted for protective coating and epoxies.
17. Design Mixes: Provide concrete and cement mortar in conformance with
Section 03300 and as specified herein.
B. Provide shelter to store materials in area or areas designated by the Owner solely
for this purpose. Confine mixing, thinning, clean-up and associated operations
and storage of repair mortar materials debris before authorized disposal, to these
areas.
C. Mix all specified materials in the sheltered mixing operation and materials from
direct sunlight and inclement weather. Protect facilities from staining and
damage.
F. Deliver all materials to the job site in new, unopened containers. Each container
shall bear the manufacturers name and label.
a. Name of product.
d. Manufacturers name.
g. Shelf-life date.
2. Clearly mark all containers indicating any safety hazards associated with the
use of or exposure to the materials.
A. Environmental Requirements:
B. Protection:
1. Cover or otherwise protect finish work or other surfaces not being repaired.
C. Ventilation:
PART 2 PRODUCTS
A. The cementitious repair mortar system shall meet the following requirements:
1. Compressive Strength:
3. NonSag Thickness:
5. Flexural Strength:
d. Or approved equal.
1. Tensile Strength:
3. Flexural Strength:
5. Compressive Strength:
6. Compressive Modulus:
7. Bond Strength:
B. Products:
d. Or approved equal.
F. Chemical Grout: Chemical grout for sealing water leaks in cracks or holes to be
rapid expanding and fast curing. Chemical grout to be Scotch-Seal Brand
Chemical Grout 5600 (Foam) by Minnesota Mining and Manufacturing
Company, Minneapolis, MN; Sikafix Polyurethane Chemical grout by Sika
Chemical Corp., Lyndhurst, NJ; Durigel 120 by Avanti Products Company,
Houston, Texas; or approved equal.
G. Cement Mortar:
1. Portland Cement, Type II: Provide in accordance with ASTM C150. One
brand from only one source to be used throughout the work.
2. Provide fine aggregate in conformance with ASTM C33 and with Section
03300.
H. Surface Seal:
A. Obtain blast material, primers and other products required by the concrete repair
system manufacturers to complete the repair work at no additional cost to the
Owner.
2.04 MIXES
A. Epoxy Mortar and Epoxy Grout: Mix with Ottawa silica sand or an aggregate
mix recommended or supplied by the epoxy manufacturer.
2.05 EQUIPMENT:
A. Equipment for application of the epoxy must be portable and consist of positive
displacement type pumps with interlock to provide positive ration control of
exact proportions of the two components at the nozzle.
B. Pumps must be electric or air powered and shall provide an in-line mixing and
metering system and must contain drawback plugs.
PART 3 EXECUTION
2. The compressed air used for blast cleaning shall be filtered free of
condensed water or oil. Clean moisture traps at least once every four
hours or more frequently if required to prevent moisture from entering the
supply air to the abrasive blasting equipment. Air compressors shall
comply with all applicable federal, state, and municipal codes and
regulations.
5. Use abrasive blast nozzles of the venturi or other high velocity type
supplied with a minimum of 100 psig [700 KPa] air pressure to obtain the
specified degree of cleanliness.
7. Provide ground fault interrupters on all electrical equipment used for the
work covered by this Section.
B. Degreasing.
1. Saw cut the perimeter of the repair area to a minimum depth of [12
mm] below the surface of the concrete. Chip all loose concrete in the
repair area to remove loose and degraded concrete until a sound substrate
is reached.
5. Vacuum clean all surfaces to remove all loose dust, dirt, and debris.
B. Work a wet scrub coat of the mortar per the manufacturers recommendations
into the pores and voids in the substrate, and over the substrate prior to mortar
application by trowel.
C. Apply the cementitious repair mortar using gunite, trowel or castable methods
and using a steel trowel work the material into the surface. Fill voids from
deepest to shallowest areas as the application work proceeds. Strictly follow the
manufacturers application requirements.
D. Once the repair areas are filled with repair mortar, strike off the mortar level
with the surrounding concrete substrate. Do not leave a broom finish. Finish
with a steel trowel until closed up at the surface and flat.
E. Cure the repair mortar in strict accordance with the manufacturers instructions.
A. Perform, verify, and record the inspection functions listed below for each work
shift, and submit to the CM/CS as specified in Part 1.05 of this Section in the
form of a daily inspection report. Comply with the following acceptance
criteria and include the following information in each report:
2. Measure and record the ambient air temperature twice each shift (at least 4
hours apart) using a thermometer and measure and record substrate
temperature twice each shift using a surface contact thermometer.
4. Verify that the pot life of repair materials is not exceeded during
installation. Retempering of the repair mortar will not be permitted.
Provide sign-off by the Contractors Project Manager.
B. Rework unacceptable areas until the CM/CS determines that the work is in
compliance with these specifications at no additional cost to the Owner.
A. Pressure inject all indicated cracks with a continuous in-line meter and mix
device, capable if injection pressure up to a maximum of 300 psi [2.1 MPa] to
develop at least a 90% penetration of all cracks without the inclusion of air
pockets in the epoxy, and to achieve the specified bond-strength of the cracked
sections. Achieve 100% penetration of the vast majority of cracks.
B. Entry Ports: Space entry ports at a distance along the seal not greater than the
thickness of the cracked member. Space ports so that the injected material
travels between ports and the cracks are filled to specified requirements.
A. Contractor must supply equipment and materials, and adjust the application
procedure to achieve at least a 90% filing of all cracks without drainout and
without the inclusion of air pockets or voids in the epoxy, and to achieve
structural bonding of the cracked section. Achieve 100% penetration in the
majority of the cracks.
B. Inject epoxy under pressure by use of a rubber tipped nozzle held tightly against
the port, or by the use of entry port fittings. Injection to begin at the lower entry
port and continue until there is a show of adhesive material at the entry port
directly adjacent to or above the port being pumped.
C. When adhesive travel is indicated at the next port, discontinue the injection on
the port being pumped and sealed, and transfer injection to the next adjacent
port. Injection must be continuous until the crack is completely filled. Fill all
small radiating cracks at the same time as filling prime cracks.
D. Report any condition which prevents penetration of the crack to the CM/CS.
F. Apply epoxy bonding agent to all existing concrete surfaces which are to
receive new cast-in-place concrete and as indicated. Mix and apply compound
in accordance with the epoxy manufacturers current printed recommendations.
END OF SECTION