TIME SHEET FOR WORK ON SITE

PCP JOB REFERENCE : TESTING &COMMISSIONING


CUSTOMER’ , S REFERENCE : GE T&D INDIA LIMITED
CUSTOMER : TSTRANSCO
SITE : 220/132/33 KV ASWARAOPETA S/S
K REF KXH5
ENGINEER ‘S NAME: ARAVIND P MONTH : FEBRUARY YEAR:2023

WORKING TIME WITNESS AVAILBILTY TIME


ACTIVITY PERFORMED
DATE FROM TO HOURS FROM TO HOURS
8-2-2023 10:00 18:00 8:00 LINE - 1 & 2 FEEDER RELAY
CONFIGURATION WORK DONE
9-2-2023 SETTING FILE CONFIGURED & SCHEME
10:00 18:00 8:00
CHECKED
10-02-2023 LINE 1&2 RELAY TESTED & CHECKED ALL
10:00 18:00 8:00
FUNCTION
11-2-2023 10:00 18:00 8:00 INTERNALLY RELAY TESTED
12-2-2023 10:00 18:00 8:00 SUNDAY LEAVE
13-2-2023 LINE - 1 RELAY WITNESS WORK DONE &
10:00 18:00 8:00 10:00 18:00 8:00
CHARGED
LINE - 2 RELAY WITNESS WORK DONE &
14-2-2023 10:00 18:00 8:00 10:00 18:00 8:00
LINE - 2 CHARGED

SIGNATURE
SIGNATURE

ENGINEER ‘S NAME :ARAVIND P CUSTOMER ‘S REP NAME:


DESIGNATION: T&C ENGINEER
DESIGNATION:
GE T&D INDIA LIMITED