Engineer Aravind P worked on relay configuration, testing, and commissioning at the 220/132/33 kV Aswaraopeta substation from February 8-14, 2023. He configured the line 1 and 2 feeder relays on February 8th and checked the setting file and scheme on the 9th. On the 10th, he tested and checked all functions of the line 1 and 2 relays internally. On the 13th and 14th, witness testing was performed on line 1 and line 2 relays with the customer representative present and the lines were charged.
Engineer Aravind P worked on relay configuration, testing, and commissioning at the 220/132/33 kV Aswaraopeta substation from February 8-14, 2023. He configured the line 1 and 2 feeder relays on February 8th and checked the setting file and scheme on the 9th. On the 10th, he tested and checked all functions of the line 1 and 2 relays internally. On the 13th and 14th, witness testing was performed on line 1 and line 2 relays with the customer representative present and the lines were charged.
Engineer Aravind P worked on relay configuration, testing, and commissioning at the 220/132/33 kV Aswaraopeta substation from February 8-14, 2023. He configured the line 1 and 2 feeder relays on February 8th and checked the setting file and scheme on the 9th. On the 10th, he tested and checked all functions of the line 1 and 2 relays internally. On the 13th and 14th, witness testing was performed on line 1 and line 2 relays with the customer representative present and the lines were charged.
CUSTOMER’ , S REFERENCE : GE T&D INDIA LIMITED CUSTOMER : TSTRANSCO SITE : 220/132/33 KV ASWARAOPETA S/S K REF KXH5 ENGINEER ‘S NAME: ARAVIND P MONTH : FEBRUARY YEAR:2023
WORKING TIME WITNESS AVAILBILTY TIME
ACTIVITY PERFORMED DATE FROM TO HOURS FROM TO HOURS 8-2-2023 10:00 18:00 8:00 LINE - 1 & 2 FEEDER RELAY CONFIGURATION WORK DONE 9-2-2023 SETTING FILE CONFIGURED & SCHEME 10:00 18:00 8:00 CHECKED 10-02-2023 LINE 1&2 RELAY TESTED & CHECKED ALL 10:00 18:00 8:00 FUNCTION 11-2-2023 10:00 18:00 8:00 INTERNALLY RELAY TESTED 12-2-2023 10:00 18:00 8:00 SUNDAY LEAVE 13-2-2023 LINE - 1 RELAY WITNESS WORK DONE & 10:00 18:00 8:00 10:00 18:00 8:00 CHARGED LINE - 2 RELAY WITNESS WORK DONE & 14-2-2023 10:00 18:00 8:00 10:00 18:00 8:00 LINE - 2 CHARGED
SIGNATURE SIGNATURE
ENGINEER ‘S NAME :ARAVIND P CUSTOMER ‘S REP NAME:
DESIGNATION: T&C ENGINEER DESIGNATION: GE T&D INDIA LIMITED