You are on page 1of 5

Flexibility Assessment Studies Worldwide-Bridging

With the Adequacy Needs


*Note: Sub-titles are not captured in Xplore and should not be used

Valeri Mladenov Elias Zafeiropoulos


Technical University of Sofia Veselin Chobanov Institute of Communications and
Faculty of Automatics Technical University of Sofia Computer Systems
Sofia, Bulgaria Faculty of Mechanical Engineering Athens, Greece
valerim@tu-sofia.bg Sofia, Bulgaria eagle@central.ntua.gr
vesselin_chobanov@tu-sofia.bg
Vasiliki Vita
Institute of Communications and
Computer Systems
Athens, Greece
vasvita@aspete.gr

Abstract—This paper aims to go forward the literature A. Ramping needs


review of our previous research [1], focusing a bit more on the With the high RES penetration, flexible resources will
existing efforts on improving the adequacy assessment with
become essential to meet the fast change of residual demand
flexibility indices, defining more clearly the
FLEXITRANSTORE WP2 contribution to the on-going
i.e. the steep upward ramp created by the decline in solar
discussion about these topics in Europe and worldwide output due to the sun setting when demand increases in the
evening.
Keywords—component, formatting, style, styling, insert B. Balancing fast reserves
(key words)
The increase of variable generation along with the
I. INTRODUCTION (HEADING 1) forecast error of wind and PV should be overcome with
reserve deployment in order to secure the supply. Modeling
In order to ensure the balance of the energy system, the of balancing reserves in the CAF is performed assuming that
construction of new germination sources must be planned in a fixed amount of supply is kept available at any time.
the long term. The Capacity Adequacy Forecast (CAF) has Despite the considerable improvements in forecasting
been assessing the capacity adequacy of available supply variable power generation, for both wind and solar, in
resources to meet simulated demand scenarios. This annual practice, forecasting can never be perfectly accurate, with
exercise provides an overview of the state of play across a decreasing forecast errors as real-time operation approaches.
ten-year time frame, carried out by national TSOs for each Thus, forecasts are very likely to be updated hours ahead of
country and ENTSOe for the European network. Ten years is real time, and the system will require fast starting and
usually the time frame during which policy makers, investors controllable resources (interconnectors, demand side
and market participants make strategic decisions so as to response, storage and fast response generators). It is easy to
allow the power system to deliver a targeted level of imagine that the larger the ramps the bigger the need for
adequacy. Such forecasting exercises focus on the likelihood flexibility.
of unusual events disrupting supply. The results are derived
from many simulations providing a probabilistic C. Integration of renewables
interpretation of the likelihood of lack of supply. One such Integration of renewables creates ramping needs that
metric explored in the CAF and covered here, is loss of load should be addressed through all available means: fast
expectation (LOLE). It is the average number of hours per generation, interconnections, demand response and/or
year in which it is statistically expected that there is not storage resources. Recent studies in Europe and around the
sufficient power supply in the market to cover demand. Note world confirm that flexibility is becoming gradually a crucial
that this is not translated in a blackout as the analysis keeps point for system adequacy. Flexibility services and products
security margin for unforeseen events near real time, since it are growing in importance and are progressively being
is a probabilistic assessment based on models. integrated into the market.
II. FLEXIBILITY SERVICES There are different approaches to assessing the flexibility
Adequacy is not only related to the total amount of of the electricity system, they can be more general,
capacity being installed in the system, but also to the ability evaluating only the primary resources or could cover a great
of the installed capacity to adjust to the ever-increasing deal of detail. Some of these methods are [9]:
dynamics of dispatch events in the system. The latter is • The operation of the power plants is not taken into
defined as ‘flexibility adequacy’ and it becomes ever more account, only the available physical resources are accounted
important, mainly due to the increasing amount of variable for. [10]-[12]. The operation of the power plants is not taken
renewable energy present in the power system. Several into account, only the available physical resources are
flexibility services will be required in order to ensure a accounted for. The idea is to consider the ability to follow
smooth transition to high RES penetration [5], particularly: the load schedule by considering physical resources. Such

978-1-7281-2697-5/19/$31.00 ©2019 IEEE


approaches are likely to overestimate the availability of The second level aims to determine the flexibility of the
resources to provide flexibility and, therefore, the results electricity system, taking into account: startup time of
from such studies can only be seen as a “screening”-type generators, operating ranges, static characteristics of
analysis. This type of analysis takes into account the "real generators.
life" of the electricity system, including minimum and
maximum loads, or sets other specific features of the load The third part analyzes the annual hourly dispatching by
schedule to be considered. FAST analysis presented the comparing forecast and actual measurements. Thus
following sections belongs in this category, however in determines the ability of the system to ensure a balance
FLEXITRANSTORE the data used are more accurate than in between production and consumption of electricity.
the reference [10], since the national TSOs are involved in In summary, EPRI uses its own indicators to assess the
the modelling and calculation process. overall flexibility of the electricity system. The EPRI tool
• There are also so-called interim assessment methods. actually calculates four flexibility adequacy metrics as part
These methods are used on a detailed justification, but they of the functionality in Levels 3 and 4. In particular, in this
also do not cover all the features of the generating sources, SPP report only Level 3 of the EPRI-developed tool is
such as time for technical support, possibility of dispatch, considered, which includes analyses of the flexibility
available from the resources once they have been dispatched,
etc. [13]-[16].
and the flexibility required by the system at that time.
• Precise Assessment Methods: The information they Environmental limits are enforced through constraints in the
need to estimate how the system may operate, such as how scheduling process1. Dedicated flexibility adequacy metrics
commitment and dispatch is performed, how transmission is are calculated at this point. The goal of this level is to assess
modelled, how energy forecasting is used and how markets the flexibility that the resource fleet is technically capable of
will operate. In general, the work schedule of the power offering at each period, and measuring the adequacy of that
plants is detailed and economic optimization model is capability relative to the flexibility required in the system.
applied [17]-[19], therefore, significant modelling effort and This is achieved with the implementation of the flexibility
computational resources are needed. If detailed data are not metrics described below, the periods of flexibility deficit
available and various key operational issues are not known in (PFD), expected unreserved ramping (EUR), insufficient
advance, then simulations of this type are difficult to be ramp resource expectation (IRRE), and a flexibility well-
carried out with a degree of certainty. This problem may be being assessment.
solved by executing several scenarios, considering possible
values of the stochastic parameters (e.g. system load, fuel The first one, described as PFD is a measure of the
prices, CO2 prices, etc.). number of periods when the available flexible resources were
less than the required flexibility for a given time horizon and
FLEXITRANSTORE methodology developed in the direction. The PFD is calculated for a range of user selected
current WP2 augments from intermediate to detailed time horizons in the chosen direction based on the flexibility
assessment methods, finally taking under consideration full available from simulated production time series. As well as
unit commitment and network topology and constraints. identifying the number of periods of flexibility shortages, the
Furthermore, the WP2 studies will link these flexibility PFD helps to identify the time horizons associated with the
studies with a decision-making method proposing smart grid shortages.
solutions for flexibility inadequacies based on the
demonstrated technologies in FLEXITRANSTORE. In this The PFD is used as a conservative indicator that takes
way, WP2 aims to channel the innovative functionalities of into account the likelihood of an event occurring. This metric
the FLEXITRANSTORE innovation technologies into the should not be associated with an actual occurrence. For its
transmission system planning process. calculation, the flexibility of the system is analyzed in the
order of one hour to 12 hours. When the value of zero for
There are significant efforts of assessing flexibility available flexibility is reported in the analyzed periods, the
‘adequacy’ related with our FLEXITRANSTORE work, that indicator increases. It is important to keep in mind that a
we will mention briefly in the following paragraphs, in order comparison is made between the actual system flexibility
to introduce the FLEXITRANSTORE flexibility assessment available for this period and the worst statistically possible
approach for the SEE. case for the same period.
III. FLEXIBILITY ASSESSMENT
A. Southwest Power Pool Study [2]
The goal of the NGP, as one of nine U.S. grid operators,
is to provide security and reliability in the delivery of
electricity. These operators are not the owners of the grid,
and care only for its dispatching in real time.
The general approach used in SPP conducted study is to
analyse the variability on three major levels. The simulation
tools used for the studies have been developed by EPRI [16].
This type of analysis is performed where the wind farm
electricity production is suspended to cover the load
schedule. Various calculations are made, taking into account Fig. 1. Changes in the need for flexibility in the time interval of one to
both the maximum loads during the year and the maximum twelve hours (U: upward, D:downward).
loads for each day. This can determine what the discrepancy
between them is.
consulting company and addresses the long term flexibility
adequacy of the Greek power system with detailed hourly
The EUR is an indicator which takes into account the simulations. The objective is to calculate the long-term
lack of flexibility for the period reported by the PFD. In flexible capacity needs of the Greek interconnected power
addition to the frequency of flexibility deficits, the system for the next 10-years (2018-2027). To do this a lot of
magnitude of any shortage is important. The EUR is the total details are taken into account as load forecast, price of
magnitude of the deficit of net flexibility. The EUR is similar emissions, operational time unknit commitment etc., RES
but not identical to the expected unserved energy metric in other power plans. In ECCO’s study, the following flexibility
capacity adequacy planning. needs are identified:
1. The needs for flexible capacity
2. The hourly and 3-hour variability of the residual load
3. Forecast errors
4. The need for balancing reserves
To determine the power system flexible capacity needs,
the study followed the deterministic methodology adopted by
the California ISO [22]. In general, the flexibility need of the
power system is simulated separately for each month m of
the year using:
Upward Flexibility Needp,m = Max [Net System Load
Rampp,t,m] + Max (MSCCm, 3,5% * E(PLm)) + ε
Fig. 2. EUR - needs for flexibility in the time interval of one to twelve
hours (U: upward, D:downward) where,
Flexibility Needp,m = System flexibility need for
The third metric used in the analysis is IRRE. The ramping product p, in month m
Insufficient Ramp Resource Expectation (IRRE) is a second
measure of the frequency of flexibility shortfalls over a Net System Load Rampp,t,m = Net system load ramp
variety of time horizons. The key difference between the regarding product p, in time interval t, in month m.
PFD and IRRE is that the IRRE uses a probabilistic approach
MSCCm = Most Severe Single Contingency in month m
to determine the likelihood of meeting each net load ramp
drawn from a distribution at each period in time. In order to E(PLm) = Expected system peak load in month m
directly compare the available flexibility and the net load
ramps, a distribution of available flexibility is created. Using ε = Annually adjustable error term to account for load
this, the probability of meeting each ramp, as well as the forecast errors and variability methodology.
expected value over a time series, can be calculated. Similarly:
Figure 3 shows the probability of inability to cover the Downward Flexibility Needp,m = Max [Net System Load
load. It has been calculated using the time intervals for the Rampp,t,m]
two indicators above for the necessary flexibility and
available flexibility. Calculations show that problems with Three different ramping ‘products’, namely 15-min, 1-h
insufficient flexibility are more likely to occur at longer and 3-h ramping where calculated for the year 2016 (real
intervals. Up to two hours are not likely to be sufficient measurements provided by IPTO with 15min granularity).
flexibility, both up and down. The results poisoning and the Hourly time resolution was used in all simulation runs for the
real work of wind farms for the respective region. future study period (years 2018-2027) and the respective
system-wide flexible capacity needs for the period 2018-
2027 were calculated for 1-h and 3-h ramping intervals only.
The simulation runs of the hourly values were performed
for fourteen combinatorial scenarios with: a) ‘high’ and
‘base’ scenarios for system load, b) ‘high’ and ‘low’
scenarios for gas and CO2 emissions prices, c) additional
assumptions of interconnections availability and
commissioning/decommissioning of specific generation
plants.

Fig. 3. IRRE for SPP for test period

B. “Long-Term Flexibility Assessment of the Greek Power


System”, Prepared by ECCO International [21]
In 2017, at the launch of FLEXITRANSTORE
consortium, this study was assigned by the Greek NRA to a
C. ELIA flexibility assessment
In 2016, ELIA published a detailed study on the
‘adequacy’ and flexibility needs of the Belgian power
system, putting side by side these two concepts on a high
level of the 10-year power systems planning. The basic idea
of this study is the definition of the ‘structural block’, which
is the volume of capacity between the estimated electricity
consumption and the generation capacity present in a given
scenario i.e. nuclear, RES, CoGEN, pumped hydro,
interconnections, demand response. This ‘structural block’
includes CCGT and OCGT units (tanked below in the ‘merit’
order} and pumped hydro, demand response, new storage
capacity, and new interconnections. The basic tool used in
Fig. 4. Gas Units 1-h Ramp-up Contribution, for the 14 scenarios studied these studies is Monte Carlo simulation and economic
during the following decade [ECCO study]. Similar graphs were presented dispatch scenarios
for the Lignite and Hydro plants
The study also addresses the flexibility needs of the
Studying the 1-h Ramp-up Contributions as in the market and those for balancing purposes, i.e. the balancing
previous figure, it was concluded that, in all simmulations, reserves:
the increase of RES power plants over time results in an
increased upward ramping provision by conventional coal (i) Primary Reserve R1 (FCR - Frequency
and hydro power plants to compensate for the increased net Containment Reserve): stabilization of the frequency within
load variability. Furthermore the 3h contribution was a range between 49.8 and 50.2 Hertz, increasing/decreasing
examined: the 3-h upward ramping contribution for each unit generation capacity in less than 30 seconds in the event of a
technology was not only considerably higher (around 2.5-3 decrease/rise in frequency,
times higher) but also presented much higher variation across (ii) Secondary Reserve R2 (aFRR - automatic
the examined scenarios as compared to the respective 1-h Frequency Restoration Reserve): reduction the frequency to
upward ramping contribution. This was attributed to the fact 50 Hz (‘pressure relief’ on R1) and assurance of
that 3-h net load ramps are normally higher (and present import/export balance of nearby control areas according to
much higher variation across different scenarios) than the 1-h contractual agreements. R2 setpoint signal is also based on
net load ramps, mainly on the hours preceding or following ongoing measurements and transmitted to all power plants
the morning and evening peak load hours, where the highest participating in R2 every 10 secs.
net load ramps are usually observed.
(iii) Tertiary Reserve R3 (mFRR – manual Frequency
The ECCO study has been used by the NRA to provide Restoration Reserve): R3 is activated and controlled
indications for formulating the Transitory Electricity manually by dispatchers to overcome insufficiency of R2,
Flexibility Remuneration Mechanism (TFRM) and the stemming from on-line generation or demand response,
flexibility resources to be asked by candidate market during a period ranging from a few minutes to a maximum of
participants through auctions. This has been presented in quarter of an hour
Deliverable 2.1. As previously mentioned, in WP2 the
FLEXITRANSTORE consortium aims to study the The results of the study regarding flexibility are very
flexibility needs and resources of SEE countries and provide much dependent on the initial assumptions made for the
a platform to introduce the effect of technology innovations evolution of the RES generation, intraday and balancing
into the system planning, improving the TSO portfolio of markets, active demand management, decentralised storage,
solutions. Storage solutions play an important role in and international cooperation between grid operators. In this
FLEXITRANSTORE and they are linked with a cost benefit way the study estimates the required capacity for R1, R2 and
study and various business models and market R3 for the next decade for the Belgian power system.
reimbursement mechanisms, which are coming out of the Especially, the ELIA flexibility assessment reveals that for
work in WP3 scope. secondary control (aFRR)a few CCGT units (2 up to 4)
might be necessary in next four years to cover the load.

Fig. 5. Gas Units 3-h Ramp-up Contribution for the 14 scenarios studied Fig. 6. Capacity of the ‘structural block’ resulting from the adequacy and
during the following decade [21]. Similar graphs were presented for the flexibility assessment form the ‘base case’ scenario
Lignite and Hydro plants in the study
D. Joint Research Center study “Assessment of underlying REFERENCES
capacity mechanism studies for Greece” [4]
This report of Joint Research Center [4] presents a [1] L. Wu, M. Shahidehpour et al., “Stochastic security-constrained unit
thorough evaluation of the IPTO capacity adequacy studies’ commitment,” IEEE Trans. Power Syst., vol. 22, no. 2, pp. 800 – 811,
May 2007.
methodology in comparison with international practices
(ELIA study, NREL study as in [25]) and mainly ENTSOe [2] “2016 Wind Integration Study”, Southwest Power Pool, Inc, USA
2016.
[5, 7]. However, extra focus is given to the flexibility
[3] .A. Tuohy, P. Meibom et al., “Unit commitment for systems with
assessment approaches being elaborated by research centers significant wind penetration,” IEEE Trans. Power Syst., vol. 24, no. 2,
and TSOs in order to assess whether the power system has an pp. 592 – 601, May 2009.
adequate level of flexibility resources to face the [4] Antonopoulos G; Chondrogiannis S; Kanellopoulos K; Papaioannou
aforementioned technical challenges and/or to evaluate I; Spisto A; Efthimiadis T; Fulli G., Assessment of underlying
future flexibility needs in a qualitative and quantitative capacity mechanism studies for Greece, EUR 28611 EN, Publications
manner. JRC stresses that the actual availability of these Office of the European Union, Luxembourg, 2017, ISBN 978-92-79-
68878-2, doi: 10.2760/51331, JRC106307.
resources is not only a technical matter, but also a subject of
[5] ENTSOe (2019): ENTSO-E Powerfacts Europe 2019.
the regulatory framework of electricity markets which play a
decisive role. [6] IPTO, “Handbook of Capacity Adequacy Calculation Mechanism /
Version 3 (in Greek),” Athens, 2013.
Furthermore, in this report the JRC is providing insights [7] ENTSO-E, Mid-term Adequacy Forecast 2018 Edition, Brussels,
on the flexibility assessment approaches addressing pros and 2018
cons: [8] Huang, Yuping, P. M. Pardalos, and Q. P. Zheng. Electrical power
unit commitment: deterministic and two-stage stochastic
1) The ECCO study does not provide a quantification of programming models and algorithms. Springer, 2017.
the reserves requirements of the System in order to cope with [9] Bonneville Power Administration, EPRI and Northwest Power and
residual load variability and forecast errors. An extension of Conservation Council, “Flexibility Assessment Methods DRAFT”,
the stydy should provide a robust quantification of the Greek January 2015.
System reserve (FCR, aFRR, mFRR) requirements based on [10] International Energy Agency, “Grid Integration of Variable
Renewables, phase 2”, 2011, available from IEA.
the statistical analysis of the above parameters at hourly and
[11] Portland General Electric, “2009 Integrated Resource Plan: 2012
intra-hourly steps . Integrated Resource Plan Update”, Nov 2012. Online].
2) Market simulations could determine whether the Available:http://www.portlandgeneral.com/our_company/energy_stra
tegy/resource_planning/docs/irp_nov2012.pdf
Hellenic system has adequate resources to cope with hourly
[12] Ma, J.; Silva, V.; Belhomme, R.; Kirschen, D.S.; Ochoa, L.F.,
and 3-hour ramping requirements. "Evaluating and planning flexibility in sustainable power systems,"
3) Outcomes of the flexibility assessment analysis and Power and Energy Society General Meeting (PES), 2013 IEEE , vol.,
no., pp.1,11, 21-25 July 2013
their relation to the long-term planning process of the Greek
[13] M.Schilmoeller, “Imbalance Reserves: Supply, Demand, and
Power System Sufficiency”, Northwest Power and Conservation Council report,
2012
[14] S. Müller, “Evaluation of Power System Flexibility Adequacy - The
IV. CONCLUSIONS Flexibility Assessment Tool (FAST2)”, presented at the 12th
International Wind Integration Workshop, London, October 2012.
Finally, an overall improvement of the simulation [15] Lannoye, E.; Flynn, D.; O'Malley, M., "Assessment of power system
approach is recommended that will incorporate the revision flexibility: A high-level approach," Power and Energy Society
of cross-border interconnector assumptions to account for General Meeting, 2012 IEEE , vol., no., pp.1,8, 22-26 July 2012
seasonality and operational constrains, use of flow-based [16] Electric Power Research Institute, “Power System Flexibility Metrics:
market methods, and advanced sequential Monte Carlo Framework, Software Tool and Case Study for Considering Power
System Flexibility in Planning”. EPRI, Palo Alto, CA: 2013.
simulations that will incorporate day-ahead, intraday and 3002000331.
balancing markets. [17] J. Hargreaves, E. K. Hart, R. Jones and A. Olson, Energy and
Environmental Economics, “REFLEX: An Adapted Production
ACKNOWLEDGMENT Simulation Methodology for Flexible Capacity Planning”, 2013.
This project has received funding from the European Online].
Union’s Horizon 2020 research and innovation programme [18] California Independent System Operator, “Flexible Resource
Adequacy Criteria and Must-Offer Obligation”, Draft proposal
under grant agreement No 774407. available at www.caiso.com, March 2014.
[19] "Methods to model and calculate capacity contributions of variable
generation for resource adequacy planning", Tech. Report, North
American Electric Reliability Corporation (NERC), Mar. 2011.
[20] “Study regarding the ‘Adequacy’ and Flexibility Needs of the Belgian
Power System: Period 2017-2027”, ELIA, Brussels 2016.
[21] “Long-Term Flexibility Assessment of the Greek Power System”,
ECCO International, San Francisco CA USA, 2017.

You might also like