Professional Documents
Culture Documents
Introduction
Temporary structure
Can be made of timber (bakau/
mangrove), steel, galvanised metal, metal
alloys, bamboo
Purpose is to provide working platform
Means of material transport
Safe place incorporating safety features
for workers and people passing
underneath
2
1
Types of Scaffolds
Putlogs Scaffolds
Independent Tied scaffolds
Mobiles
Fixed Frame Scaffolds
Suspended
Cantilevered
Putlog Scaffold
Mainly used for constructing or repairing
brickwork structures
Supported in brickworks by putlogs and
ties
Single working platform allowed
Max load on platform is 275 kg/m2 which
is roughly equal to 140 bricks, 25 kg
mortar and 2 men
Maximum safe height of scaffold is 30 m
4
2
Putlog
Putlog Scaffold
End View
3
Putlog Scaffold
4
Independent Tied Scaffolds
The whole load of scaffold are carried to the foundation
resting on the ground
Tied to construction to ensure stability
Can deal with 4 working platforms at one time therefore
greater consideration for design
Classified as:
Light duty (only one working platform, max loading of 73
kg/m2)
General purpose (up to 4 working platform and max
loading of 180 kg/m2 on each platform) and
Heavy duty (2 working platforms of higher loading max
of 290 kg/m2)
10
End View
11
5
Scaffolding parts and terms
Standard – uprights carry total load of
scaffold including man and material on the
platform
Ledger – horizontal tubes connecting the
standard
Putlog – transverse tube with one end
placed in a slot left in the construction
usually a gap in the mortar joint of a brick
wall
13
14
6
Scaffolding parts and terms (cont.)
16
7
Scaffolding parts and terms (cont.)
17
18
8
30
31
9
Mobiles
Self-contained units
Only one working platform of limited size
Used where work needs to be moved
more frequently
For light loads
Used for maintenance, painting, finishing
interior
Height of towers must not exceed three
times the shortest base dimension
32
Mobiles Scaffolding
33
10
34
11
Assembling Fixed Frames
Steps:
1. Start with proper assembling of the 1st row, then base
plates and vertical installation.
2. Test for vertical and horizontal levels; apply bracings.
3. Place the transverse frames on the main frames.
4. All base plates must be fixed on the ground supports.
5. Place all pin connectors, interlocks and wall ties.
6. Check all structures for stability.
37
38
12
41
Suspended Scaffolds
42
13
Suspended Scaffolds
43
46
14
Cantilevered Scaffolds (Truss-out)
puncheon
Standards
47
48
15
Power Scaffolds
49
16
Materials for Scaffoldings
(cont.)
Platform 38, 50, 63mm thick, 225mm
wide, 3.9m long
Mechanical properties – should conform to
the required strength for tensile, yield and
elongation
Approved connectors or couplers
51
Safety Features
(MS 426:1994) – Code of practice for safety and
health at work
17
Safety Features (cont.)
Braced diagonally in both horizontal and vertical
planes to prevent swaying and displacements
After erection of scaffolds the structure be
inspected and certified safe by a trained person
A trained and experienced person must inspect
the scaffold once a week
Inspection is also necessary after a rough or
cold weather
53
Scaffold Hazards
58
18
Scaffolds Hazard
Scaffolds Hazard
60
19
Scaffolds Hazard
61
Scaffolds Hazard
Unstable
Loaded with blocks
Scaffold is not level
because it was erected
without base plates on an
uneven surface.
62
20
Scaffolds Hazard
63
Scaffolds Hazard
This is a great example of
what can happen when
construction workers fail to
investigate the site where
their scaffold is being erected,
and base plates are not used.
The scaffold in question (now
taken down) punched a hole
through the downtown
sidewalk. The workers failed
to realize that the sidewalk
was only made from blacktop,
and it had a basement under
it. EXAMPLE OF POINT
LOADING!!
65
21
Scaffolds Hazard
66
Scaffolds Hazard
Planking on this platform should be six planks wide, instead of only two.
Also, note that the planks are bowing because the bricks are loaded at 67
one point on the platform instead of being evenly distributed.
22
Scaffolds Hazard
Openings between
planks in platform
should not exceed
25 mm
68
70
23
Scaffolds Failure
71
73
24