You are on page 1of 8

▣ Factory Acceptance Tests ( FAT )

Item
Description SUPPLIER Remarks
no.

1. DOORS

Metal LEC STEEL


Glass PHIL ASIA
FAST CLAD Inc. &
2. WINDOWS
FILASIA
3. LOUVERS TO BE ADVISE No identified supplier yet as per HCC
4. Roll Up Doors LEC STEEL
5. SIGNAGES TO BE ADVISE No identified supplier yet as per HCC

Note : This is Tentative Schedule


11-Jan-23

TENTATIVE FAT
Acceptance Date Location
SCHEDULE

BALAGTAS
MARCH 30, 2023
BULACAN,PHILIPPINES
APRIL 3, 2023 TAYTAY, RIZAL PHILIPPINES
TAYTAY RIZAL & QUEZON
APRIL 3, 2023
CITY,PHILIPPINES
MARCH 27, 2023
BALAGTAS
MAY 4, 2023
BULACAN,PHILIPPINES
APRIL 5, 2023
▣ Factory Acceptance Tests ( FAT )

SYS/EQUIP NAME SUPPLIER FAT SCHEDULE


1-Apr-23
Structural Steel Members (fabricated) HILMARCS
13-Nov-23
STRUCTURE
LRS
WORKSHOP