The document describes 7 different types of estimates:
1. Preliminary estimates provide approximate costs quickly based on similar past projects.
2. Detailed estimates calculate exact quantities and costs of all items from drawings and specifications.
3. Revised estimates update original estimates when costs increase more than 5% due to rates or deviations.
4. Supplementary estimates cover additional works needed due to structural changes from original designs.
5. Annual maintenance estimates budget for regular repairs and replacements.
6. Extension estimates cover non-routine changes to old works.
7. Complete estimates incorporate all associated costs from land to supervision.
The document describes 7 different types of estimates:
1. Preliminary estimates provide approximate costs quickly based on similar past projects.
2. Detailed estimates calculate exact quantities and costs of all items from drawings and specifications.
3. Revised estimates update original estimates when costs increase more than 5% due to rates or deviations.
4. Supplementary estimates cover additional works needed due to structural changes from original designs.
5. Annual maintenance estimates budget for regular repairs and replacements.
6. Extension estimates cover non-routine changes to old works.
7. Complete estimates incorporate all associated costs from land to supervision.
The document describes 7 different types of estimates:
1. Preliminary estimates provide approximate costs quickly based on similar past projects.
2. Detailed estimates calculate exact quantities and costs of all items from drawings and specifications.
3. Revised estimates update original estimates when costs increase more than 5% due to rates or deviations.
4. Supplementary estimates cover additional works needed due to structural changes from original designs.
5. Annual maintenance estimates budget for regular repairs and replacements.
6. Extension estimates cover non-routine changes to old works.
7. Complete estimates incorporate all associated costs from land to supervision.
2. Detailed Estimate 3. Revised Estimate 4. Supplementary Estimate 5. Annual Maintenance Or Repair Estimate 6. Extension and Improvement of Estimates 7. Complete Estimate 1.Preliminary Estimate or Approximate • This is an estimate to find out an approximate cost in a short period of time • The authority concerned to consider the financial aspects of the scheme, for according sanction. • Approximate estimate is calculate from a similar construction already complete in the nearby area • Preliminary estimate is required for studies of various aspects of work • For commercial projects, whether the net income earned justifies the amount invested or not. • The approximate estimate is prepared from the practical knowledge and cost of similar works. • A percentage 5 to 10% is allowed for contingencies. Methods used for preparation of approximate estimates A) Unit base method. • According to this method the cost of structure is determined by multiplying the total number of units with unit rate of each item. • In case schools and colleges, the unit considered to be as 'one student' and in case of hospital, the unit is 'one bed'. the unit rate is calculated by dividing the actual expenditure incurred or cost of similar building in the nearby locality by the number of units. Methods used cont… B) Plinth area method • The cost of construction is determined by multiplying plinth area with plinth area rate. The area is obtained by multiplying length and breadth (outer dimensions of building). • In fixing the plinth area rate, careful observation and necessary enquiries are made in respect of quality and quantity • Aspect of materials and labour, type of foundation, height of building, roof, wood work, fixtures, number of storey's etc. • P/A=carpet area + area of wall+ circular area + area of Kitchen and Bathroom Methods used cont… C) Cubical Contents Method: • This method is generally used for multistoried buildings. • It is more accurate that the other two methods viz., plinth area method and unit base method. • The cost of a structure is calculated approximately as the total cubical contents (Volume of buildings) multiplied by Local Cubic Rate. • The volume of building is obtained by Length x breadth x depth or height. The length and breadth are measured out to out of walls excluding the plinth off set. • The cost of building= volume of buildings x rate/ unit volume. Methods used cont… D) Approximate Quantity Method: • Quantities are worked out in linear measurement, • Foundation work (excavation, wall, concrete, brick work) up to Plinth computed as per running length Example:1 Prepare an approximate estimate of building project with total plinth area of all building is 800 sqm. and from following given data. i) Plinth area rate Rs. 6000 per sqm ii) Cost of water supply @7%of cost of building. iii) Cost of Sanitary and Electrical installations @ 10% of cost of building. iv) Cost of architectural features @1% of building cost. v) Cost of roads and lawns @5% of building cost. vi) Cost of Supervision and contingencies @4% of building cost. Determine the total cost of building project. Example 1 Soln: • Given plinth area =800m2 and plinth area rate=6000 per m2 • Building cost=800*6000=4,800,000 Cost of w/s and sanitation=7.5% Preliminary estimation of building project = Example:2 Prepare a preliminary estimate of a four storied office building having total carpet area of 1500.sq.m for obtaining the administrative approval of the government, given the following data. i) 40% of the built up area will be taken up by corridors, verandah, lavatories, staircase etc. ii) Plinth area rate is Rs. 20,000/- per Esq. Extra for special architectural treatment 0.5% of building cost. iii) Extra due to deeper foundation at site 1% of building cost. iv) Extra for water supply and sanitary installation 8% of building cost. v) Extra for internal electrical installation 12.5% of building cost. Vi) Extra for other services 5% of building cost. Vii)Contingencies - 2.5% Example 2 solution Given ; total Carpet area=1500sqm 40% of the built up area will be taken up by corridors, verandah, lavatories, staircase etc. Let, X=Plinth area of the building We have , P/A=carpet area + area of wall+ circular area + area of Kitchen and Bathroom So, X =40%of X+1500sqm X=0.4X+1500 X=(1500/0.6)sqm= qm= plinth area Example:3 Prepare the rough estimate for a proposed commercial complex for a municipal Corporation for the following data. • Plinth Area = 500m2/floor • Ht of each storey = 3.5m • No. of storey’s = G+2, • Cubical content rate = Rs. 1500/m3 • Provided for a following as a percentage of structured cost a) Water supply & Sanitary arrangement -15% b) Contractors profit - 10% c) supervision & contingencies - 3% Given, PA=500m2, Cubical contain rate=1500m3 No of story= G+2=3 Building height=3.5m Building cost=building volume X cubical rate =(500x3x3.5)X1500=7,875,000.0 Now extra cost, i)W/S=15%of building cost=15%7,875,000=1,181,250.0 ii)Contractor profit=10% of building cost=787,500.0 Total building cost=building cost(civil)+W/s+Con. Profit =7,875,000.0+1,181,250.0+787,500.0 =9,843,750.0 Petty supervision & contingencies = 3% of total building cost =3% X 9,843,750.0 Rough estimate for a proposed commercial complex for a municipal =9,843,750.0+295,312.5= 10,139,062.50 Example:4 • Prepare the preliminary estimate for administrative approval of a four storied building having carpet area of 1 floor 250 sqm and floor height 2.8m each. The area required for circulation and wall is 32% of total area. • If the cubic rate of the building for civil works assumed to be Nrs: 8000 per cubic meter. The masonry provision of electrification, water supply and sanitation works is 20% of civil work. contingencies – 2.5% Given, four storied building having carpet area of 250 sqm and floor height 2.8m each. The area required for circulation and wall is 32% of total area cubic rate of the building for civil works assumed to be Nrs: 8000 per cubic meter The masonry provision of electrification, water supply and sanitation works is 20% of civil work. contingencies – 2.5% Now, total plinth =X X=250+32%of X X=367.64m2 We know volume of building=Plinth area X building height=367.64*(4*2.8)cum=4117.64m3
Building Civil cost = 32,941,176.47
Mansonary provision and Electric, W/s sanitary =20% of civil cost 6,588,235.29
Now total Building Cost = 39,529,411.76
Contingencies= 988,235.29 Now , Rough estimate of the four story Building = 40,517,647.06 2. Detailed Estimate: • Most accurate estimate of any work • Quantities of all items of work are calculated from their respective dimensions on the drawings on a measurement sheet. • Abstract of cost is prepared by multiplying the quantities of item by their rate. • A detail estimate is accompanied by- – Report – Specifications. – Detailed drawings showing plans and sections. – Design data and calculations. – Basis of rates adopted in the estimate. Preparation of Detail Estimate: – Details of measurement and calculation of quantities – Abstract of estimate cost – Rate analysis (Material rate and labour rate) Details of measurement and calculation of quantities Item no Description/Particulars no L B H/D quantity unit remark
Abstract of estimate cost
Item no Description/Particulars quantity unit Rate Amount Remark 3. Revised Estimate: • A revise estimate is the detail estimate or list of quantities and rates of items of works originally provided in the estimate without material deviations of a structural nature from originally approved for a project • It is required under any one of the following circumstances – When the original approve estimate is exceed or likely exceed by more than 5% either by in sufficient rate or any cause – Even though the cost maybe made from the approve amount , there is material deviation from the initial detail estimate – When the expenditure on the work exceed or likely exceed the amount of administrative approve by more than 10% (for work more than 5 lakhs) • Also submit variation report. 4. Supplementary Estimate: • While a work in progress, some changes or additional works due to material deviation for a structural nature from the design originally approved may be thought necessary for development of a project. • Detail estimate of additional work in addition to original estimate. • It is required to get approval from the concerned authority. 5. Annual Maintenance Or Repair Estimate • After completion of a work it is necessary to maintain the same for its proper function • The same and estimate is prepared for the items which required renewal, replacement and repairs. • Example:- White washing, Color washing, Painting of doors and windows etc 6. Extension and Improvement of Estimates • When some change and extension are required to made the old work the cost of which cannot be made out in Annual Maintenance Or Repair Estimate 7. Complete estimate: • Consist cost of all items including land cost to supervision cost (Consultant cost: Surveying, design , Drawing, Estimation, tender document) Split up of cost of building work: General break-up of conventional buildings : 1. Labour component : 30 to 35% of total cost 2. Material component: 65 to 70% of total cost Stagewise break-up of conventional buildings : 1. Foundation and beams upto plinth level : 10 to 15% of total cost 2. Construction above plinth level : 85 to 90% of total cost Activitywise break-up of conventional buildings : Foundation work : 17-18% Brickwork/blockwork : 20% Concreting and reinforcement steel : 15% Doors,windows and ventilators : 12% Roof water proofing and finishing with tiles: 5% Plastering : 5-6% Flooring : 5% Painting : 2-3% Water supply,electrification,sanitary works : 12-13% Other works : 4-5% This may vary slightly depending on the type of finishes/doors and windows/sanitary fittings etc. According to Materials: Cost of Brick 22 to 25% Cost of steel bars 10 to 12%
Handbook on Construction Techniques: A Practical Field Review of Environmental Impacts in Power Transmission/Distribution, Run-of-River Hydropower and Solar Photovoltaic Power Generation Projects