INSTITUTE OF TECHNOLOGY GOPESHWAR

Class Test I (BTech Civil IIIrd yr.)


BCET 504 Quantity Surveying and Costing
Roll No: ………………...

Maximum Marks: 30 Duration: 1 hour

Part-A (Short Answer Type)


1) What are the general rules to be followed while taking the measurements? 4
2) Write the unit of measurement of 2
i) Damp Proof course using water proofing compound
ii) Dismantling of Brickwork
iii) Plastering/Pointing
iv) Iron Railing
3) What are different types of estimates? Briefly explain about Detailed estimate. 4
4) Explain 5
i) Bill of quantities
ii) Work charged establishment
iii) Specifications
Part- B
5) The internal dimensions of a single roomed building are 5.75 × 3.75 m. Find 5
i) The Center line and long wall-short wall length of room and parapet if the wall
thickness of room and parapet are 300mm and 250mm respectively.
ii) Also find the quantity of sand filling in basement for same building if the height of
basement is 750mm and Plinth wall thickness is 400mm.
(Explain with diagram)
6) Prepare the rough estimate for a proposed commercial complex for a municipal
corporation for following data. 5
2
Plinth area = 500 m
Floor Ht of each storey = 3.5 m
No. of storey’s = G + 2
Cubical content rate = Rs. 1000/m 3
Provided for a following as a percentage of structured cost-
a) Water supply and sanitary arrangement – 8%
b) Contractors Profit – 10%
c) Electrification – 6%
d) Fluctuation of rates – 5%
e) Petty supervision and contingencies – 3%

7) Analysis the Unit rate for 12 mm cement plastering in ceiling 1:3 with coarse sand.
Take quantity as your roll No. Sq m. (i; g if your roll no. is 15 take quantity as 15 sq
m). Note that Sand is provided by client. 5
(If any data is assumed please mention it separately before solving for it)
End of Paper