You are on page 1of 12

True or False

1. Option Home -> CIAG -> Return option is used to transfer site to site material

 True

 False

My Answer:False

2. Anti static Wrist should be use once working inside the PowerCube for Cards and Cable
connection

 True

 False

My Answer:True

3. DC low Voltage Alarms need to be test in ATP and its tested by plugging out the PSU
modules.

 True

 False

My Answer:False

4. CPRI cables are grounded only from two points

 True

 False

My Answer:False

5. After BTS/DBS installation is completed : Check whether the DC output voltage of the DCDU
ranges from 57.6 V to 38.4 V.

 True

 False
My Answer:True

6. One UPEU card supports 16 external environment alarms.

 True

 False

My Answer:False

7. Site Engineer should login with the NOC before enter the site.

 True

 False

My Answer:False

8. Huawei TXN Engineer don’t need to log in with NOC when site Engineer is already log in

 True

 False

My Answer:False

9. RTN IDU should not be dismantled until Huawei Engineer give confirmation.

 True

 False

My Answer:True

10. Transmission Cable (E1 / Ethernet) should be directly connected between IDU & BBU

 True

 False

My Answer:False
11. Customers often provide plane coordinates in the East-West direction. Plane coordinates can
be accurately converted into latitude-longitude coordinates without the aid of other information.

 True

 False

My Answer:False

12. During SFP optical modules installatio in UBBP in the BBU, and route the optical fibers into
the cabinet from the left front at the bottom of the cabinet, and connect the optical fibers to the
optical modules. Then, use binding straps to bind the optical fibers at the optical fiber branch and
secure the optical fibers to the subrack.

 True

 False

My Answer:True

13. All types of tools use in Power installation should be insulated and check be Huawei FE.

 True

 False

My Answer:True

14. Grounding test can done with Multi meater.

 True

 False

My Answer:False

15. Shift all sites traffic at same time accordingly MUX plan

 True

 False
My Answer:True

16. The labels of communication cables, feeder cables and jumper should be stuck and tied
according to specifications. The labels should be arranged in an orderly way with same direction.

 True

 False

My Answer:True

17. AISG cable can be connected between 2 RRU‘s

 True

 False

My Answer:False

18. When installed on a tower, only one RRU can be installed in standard mode or reverse mode,
and two RRUs can be installed on a pole in back-to-back mode. RRUs cannot be installed on the
side, and the brackets for more than two RRUs cannot be combined.

 True

 False

My Answer:False

19. After fixing the new Power cabinet first need to connect the AC cable.

 True

 False

My Answer:False

20. DCDU can be powered up from both BLVD & LLVD.

 True

 False
My Answer:False
Single Choice
21. Link configuration on the new IF boards should be according to

 A.New LB shared by Huawei planning team

 B.Old link configuration

 C.Either new LB or old configuration can be used

 D.No link configuration need for IDU swap since ODU used are the same.

My Answer:A

22. To avoid the risk of having the ODU become faulty, you should

 A.Power off the RTN before

 B.Switch off the ODU power from the IF board before removing the IF cable

 C.Remove the IF cable quickly while keeping IF switch ON

 D.Install new IF cable for the new IF board

My Answer:B

23. Which Configuration should be preffer in MDT comissioning

 A.One Click

 B.Mannaul

 C.Auto

 D.All of above

My Answer:A

24. BBU and RRU should be connected to which type of breakers


 A.63/80 Amps LLVD

 B.63/80 Amps BLVD

 C.32Amps LLVD

 D.32Amps BLVD

My Answer:A

25. BBU will always be connected with

 A.BLVD

 B.LLVD

My Answer:B

26. When we set multimeter mode to diode like symbol, it verifies the device‘s

 A.V

 B.A

 C.Continuity

 D.Power

My Answer:C

27. EMU is always powered up from

 A.LLVD

 B.BLVD

 C.Both LLVD & BLVD

 D.BBU
My Answer:B

28. The loss between the active (main) interface and standby interface is ( ).

 A.the same

 B.loss of the main is higher

 C.stochastic

 D.loss of the main is lower

My Answer:D

29. should be used to make grounding connectors

 A.Hammer

 B.Thimble Presser

 C.Cable Cutter

 D.Pliers

My Answer:B

30. IN ICC 500 Cabinet, Transmission equipment is always laid out from

 A.Bottom Up

 B.Top Down

 C.Middle

 D.Both A & B

My Answer:A

31. Which of the following statements are correct?

 A.During activity for installation GND cable should be connected in last


 B.During dismantling activity GND cable should be disconnected first

 C.During activity it is necessary to power on the Huawei Power supplies on batteries

 D.Revert back activities should be take care during cold SWAP only

My Answer:C

32. The function of ODU is ( ) .

 A.Amplification only

 B.decode

 C.transfer signal between RF and IF

 D.Modulation

My Answer:C

33. After resetting NE ID, NE will _________

 A.Log off

 B.Remain log in

 C.stand by

My Answer:B

34. Using WDT : For a new site what IP is used to login the UMPT, before commissioning

 A.192.168.0.1

 B.192.168.0.75

 C.192.168.0.49

My Answer:C

35. For the STM-1 capacity, ( ) is the modulation method.


 A.QPSK

 B.128QAM

 C.16QAM

 D.ASK

My Answer:B
Multiple Choice
36. In SMU03A, which of the following ports are available just underneath LCD display ?

 A.FE

 B.RS485/RS232

 C.COM1

 D.COM2

My Answer:A,B,C,D

37. IP address for RTN is

 A.129.9.0.10

 B.129.9.70.35

 C.172.9.10.35

 D.202.9.0.12

My Answer:A,B

38. Labels can be used

 A.Printed White on inddor cables


 B.Yellow labels on out door cables

 C.yellow for indoor labels

 D.hand written for indoor cables

My Answer:A,B

39. Which of the following are part of WCDMA network architecture

 A.UE

 B.NodeB

 C.RNC

 D.CS&PS

My Answer:A,B,C,D

40. BBU and RRU should be connected to which type of breakers

 A.LLVD

 B.BLVD

 C.DC breakers

 D.AC Breakers

My Answer:A,C

41. CPRI rolls can be made

 A.AT Tower

 B.AT Horizontal ladder

 C.under the cabinet


 D.option B & C are wrong

My Answer:A,B

42. RMT alarm is report due

 A.ODU mute

 B.Co-channel interference

 C.ODU loop back

 D.IF board is faulty

My Answer:A,B,C

43. Which of the following modules can be configured with 1T2R?

 A.RRU3936

 B.WRFUa

 C.RRU3832

 D.RRU3838

My Answer:A,C,D

44. Which of the following component should be grounded?

 A.BU

 B.RFU

 C.IDU

 D.Flexi Waveguide

 E.Antenna
My Answer:A,B,C

45. Which of the following conditions must be met in order to use tools on site ?

 A.Insulation

 B.Taping

 C.Any surface

 D.All of these

My Answer:A,B