CALCULATION SUMMARY

Project Name : Hala Altrade obiectivul 3 Project Location: Str. Balastierei FN

Contract No. : City: com. Gilău jud. Cluj, Romania

Design Areas
Design Area Calc. Mode Occupancy Area of Total Water Pressure @ Min. Min. Min. Calculated Hose Margin To
Name (Model) Application Source Density Pressure Flow Heads Streams Source

(m2) (l/min) (bar) (l/min/m2) (bar) (l/min) # (l/min) (bar)

Required
DA1 D Demand (HW) 105 9748,04 90,6 3,5 679,65 14 0 1,36
7,68

Required
DA1 F Demand (HW) 90 8194,84 90,6 3,5 679,65 12 0 3,27
5,98

Required
DA2 D Demand (HW) 105 9775,12 90,6 3,5 679,65 14 0 1,43
7,6

Required
DA2 F Demand (HW) 90 8192,71 90,6 3,5 679,65 12 0 3,34
5,91

Required
DA3 D Demand (HW) 105 9760,01 90,6 3,5 679,65 14 0 0,61
8,42

Required
DA3 F Demand (HW) 120 11080,41 90,6 3,5 679,65 16 0 0,8
8,03

File: E:\Alina Kemp\K-15-2020 Hala Altrade obiectiv 3\06_Faza PT+DDE\04_Stingere incendiu\02_Documente


Date 11.11.2020 desenate\CH\Calcul 23.tyc3
Page 1