Professional Documents
Culture Documents
2
From time to time, it becomes important to carry out
maintenance and repairs in the underwater portion of
the hull.
10
DOCKING AND DOCKING PROCEDURES
– Ships belonging to all flag states cannot apply for the EXTENDED DRY-DOCKING
PROGRAM. The flag administration first needs to approve the type of vessel and
the owner for the extended dry-docking scheme. A ship can apply for the EDD only
if its flag state approves of the program. 13
DOCKING AND DOCKING PROCEDURES
The following ships and ship types are not eligible for the
extended dry-docking scheme described in these
guidelines:
• Passenger Ships;
• Ships subject to the Enhanced Survey Program (ESP)
Extended Hull Survey Program (EHSR); Tankers and Bulk
Carriers
• Ships fitted with propulsion thrusters;
• Ships where the propeller connection
to the shaft is by means of a keyed taper;
• High Speed Craft (HSC).
14
Enhanced Survey Program (ESP) and
Extended Hull Survey Program (EHSR)
The ENHANCED SURVEY PROGRAMME is
applicable for bulk carriers and oil tankers.
A ship undergoes four type of surveys during its
5 yearly cycle of statutory surveys.
Annual Survey
Intermediate Survey
Renewal Survey
Dry Dock Survey
15
Enhanced Survey
Programme-ESP is not a
separate survey.
17
DOCKING AND DOCKING PROCEDURES
Inspection of hull and paint coating is one of the most
important factors considered for EDD. The paint manufacturer
provides the criteria for which the coating will be valid for 7.5 years.
Several factors such as vessel
speed, area of operation, vessel
utilization, and idle time are taken
into consideration while deciding
the validity of the COATING.
High quality hull coating is
an important requirement for
EXTENDED DRY DOCKING.
Corrosion protection is a strict requirement if you want
to be considered for EDD. Only ships with high quality
underwater coating are allowed to this program. 18
DOCKING AND DOCKING PROCEDURES
– ANTI-CORROSION SYSTEM (corrosion protection) is an
absolute must for EDD.
blocks
A graving dock is the traditional form of dry dock. It is narrow basin, usually
made of concrete or stone-built, and closed by caisson/gates
22
Caisson, the dock gate
23
A floating dock is a narrow basin or vessel that can be flooded to allow a load to be floated in,
then drained to allow that load to come to rest on a dry platform. Dry docks are used for the
construction, maintenance, and repair of ships, boats, and other watercraft.
24
Syncrolift
A syncrolift or synchrolift is a
system for lifting boats and ships
out of the water over a submerged
cradle/platform, which is then lifted
by a mechanism.
26
27
DO NOT FORGET.
IT IS A BUDGET ISSUE.
28
29
30
31
32
33
34
Marine Growth Protection System
35
Although modern hull coatings may provide some protection against corrosion,
it is diffucult to reach a complete solution.
37
Marine Growth Protection System (MGPS)
MGPS is based on the electrolytic principle and consists of copper, aluminium
and ferrous anodes which are fed with an impressed electrical current from a
control panel.
The anode are usually mounted in pairs in
the ship’s sea chest or strainer where they
are in direct contact with the flow of water
entering the seawater lines.
39
40
First you must inspect and decide the
PICTORIAL STANDARD Mill scale: Demir oksit katmanı
about SURFACE CLEANLINESS with Flake: Pul pul olmak
ABRASIVE BLASTING Rust away: paslanıp çürümek
Scrape: raspalamak, kazıyarak çıkarmak
Next, you will choose BLAST-CLEANING Pittings: oyuk, delik
degrees
41
SURFACE PREPATION STANDARTS
Sa 1 Light blast-cleaning
Sa 2 Thorough blast-cleaning
Sa 3 Blast-cleaning
to visually clean steel
42
43
44
45
Improve the appearance of the inside coatings by making small
corrections or changes of painting.
46
47
Docking of the vessel
The vessel will dock
when it has achieved the
pre-docking condition.
In this condition, vessel
will have least ballast to
achieve the required
trim.
It will all depend upon the location, tidal current, and local factors.
49
The pilot will bring the ship parallel to the
dock. When the stern (or bow whichever is
entering first) is close to the dock knuckle,
docking master will take over from the
pilot.
50
When the ship is inside the dock, ship’s crew
need to pass the mooring lines as agreed on
mooring arrangement. Usually forward and
aft will have two lines on each side and one
on each side can be shore line. But this can
be different and mooring arrangements will
be advised by the dock master.
51
Vessel on the blocks, once entered in floating or graving dock,
Before dock master starts to remove dock water, divers will make an underwater inspection. The
diver will ensure that echo sounder and log sensors are clear and not sitting under the blocks
according to DRY DOCK PLAN. He will also ensure physically that vessel’s centerline is in line
with the blocks. It is a good practice to switch off the echo sounder and speed log now.
After the diver has made his inspection, dock master will start pumping out dock water.
52
53
As the dock water is being
pumped out, at one point the
water will go down from the
generator cooling water sea
chest. So you won’t be able to
get sea water for cooling,
56
CRITICAL PERIOD
•The time from “when Stern touches the blocks” to
when “full ship is on the blocks” is the critical period.
64
DRY DOCK BLOCK ARRANGEMENT
65
DRY DOCK BLOCK ARRANGEMENT
66
The docking procedure is
subjected to many stresses on the
hull from the shores placed in
accordance with
Incorrect placing of shores
DRY DOCK PLAN.
may cause damage to the
vessel hull when she ‘TAKES
THE BLOCKS’
We may have
azimuth thrusters,
Long bilge keels
Prominent condencer scoops
Rudder, propeller,
Transducers,
67
68
SEA CHEST
TRANSDUCER
69
SEA CHEST
70
Once the dock is dry
and ship sitting on the
blocks, you can
71
The Ship repair manager will now request the chief officer to witness the
removal of the bottom plugs.
As you know, each tank which forms part of the hull has a bottom plug to drain
the water in dry dock.
Removing bottom plugs
ensure that the tanks
are empty and dry.
72
Before Departure from Dry Dock
Echo sounder, log and drain plugs are tested for air and
water tightness. Testing involves first putting soap solution
around the drain plug. Then we create the vacuum around
drain plug and look for any bubbles.
73
Departure from Dry Dock
When it comes to leave dry dock. We need to be very
attentive in leaving the dry dock in the same
condition as we were while entering into the dry dock.
- standard items
- repair items
- modification items
76
SHIPBOARD MAINTENANCE
REPAIR AND DRYDOCK LISTS
(a)Standard Items:
- Hull cleaning, surface preparation, painting.
- Inspection and overhaul of anchors and cables,
including marking.
- Inspection, cleaning and painting of cable lockers.
- Plugs to be taken from all bottom and peak tanks.
- All sea valves and sea chests to be inspected,
overhauled and painted.
77
SHIPBOARD MAINTENANCE
REPAIR AND DRYDOCK LISTS
(a) Standard Items:
- Inspection and overhaul of rudder and propeller.
- Inspection, overhaul and load test of all lifting
appliances.
- All tanks, holds, compartments, and their closing
appliances to be inspected and overhauled.
- All anodes to be inspected, the location and weight
or size to be ascertained.
- Survey of ship's bottom to be conducted.
78
SHIPBOARD MAINTENANCE
- Renewal of piping.
- Cargo-handling equipment.
- Hatch-closing arrangements.
- Bulkhead leaks.
- Hull structure damage.
79
REPAIR AND DRYDOCK LISTS
(b) Repair Items:
- Replacement of ship's hatch cover side rails.
- Electric cables.
- Heavy weather damage.
- Overhaul of fire-fighting and life-saving appliances.
80
SHIPBOARD MAINTENANCE
REPAIR AND DRYDOCK LISTS
81
DOCKING AND DOCKING PROCEDURES
82
83
84
85
86
87