17-Jun 23-Jun 30-Jun 7-Jul 14-Jul

Total Piping Quantity 50.00 3.5 3.5 4.5


Actual Piping 52.80 2.780 4.470 6.450

Eid Holidays
Total Equipmet+ Non Standard 428.13 10.0 15.0 20.0
Actual Equipmet+ Non Standard 459.65 34.1 27.7 16.0
Total Erection Quantity 478.13 0.0 13.5 18.5 24.5
Actual Work done Quantity 512.45 0.00 36.88 32.17 22.45
Plan % (Weekly) 0.00% 2.82% 3.87% 5.12%
Plan % (100) 0.00% 2.82% 6.69% 11.82% 11.82%
Actual % (Weekly) 0.00% 7.71% 6.73% 4.70% 0.00%
Actual% (107.18%) 0.00% 7.71% 14.44% 19.14% 19.14%

Bottlenecks:

120.00%

100.00%

80.00%
Axis Title

60.00%

40.00%

20.00%

0.00%
17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-A
21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep
4.5 5 5.5 6 6.5 6 5
7.250 8.230 6.750 5.670 3.500 4.500 3.200
20.0 25.0 25.0 30.0 30.0 25.0 25.0 15.0 15.0 15.0
50.7 15.5 16.0 4.3 24.5 13.9 18.7 11.0 5.1 12.8
24.5 30.0 30.5 36.0 36.5 31.0 30.0 15.0 15.0 15.0
57.95 23.73 22.75 9.97 28.00 18.40 21.90 11.00 5.10 12.80
5.12% 6.27% 6.38% 7.53% 7.63% 6.48% 6.27% 3.14% 3.14% 3.14%
16.94% 23.22% 29.59% 37.12% 44.76% 51.24% 57.52% 60.65% 63.79% 66.93%
12.12% 4.96% 4.76% 2.09% 5.86% 3.85% 4.58% 2.30% 1.07% 2.68%
31.26% 36.22% 40.98% 43.06% 48.92% 52.77% 57.35% 59.65% 60.72% 63.39%

Wall Putty Plant Fabrication Works


Plan % (100) Actual% (107.18%)

l 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-O
Axis Title
29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec

15.0 20.0 23.1 30.0 20.0 20.0 15.0 15.0 0.0 0.0
16.7 13.5 14.7 15.0 21.58 26.54 40.00 39.87 11.60 2.22
15.0 20.0 23.1 30.0 20.0 20.0 15.0 15.0 0.0 0.0
16.70 13.50 14.70 15.00 21.58 26.54 40.00 39.87 11.60 2.22
3.14% 4.18% 4.84% 6.27% 4.18% 4.18% 3.14% 3.14% 0.00% 0.00%
70.06% 74.25% 79.09% 85.36% 89.54% 93.73% 96.86% 100.00% 100.00% 100.00%
3.49% 2.82% 3.07% 3.14% 4.51% 5.55% 8.37% 8.34% 2.43% 0.46%
66.89% 69.71% 72.78% 75.92% 80.43% 85.98% 94.35% 102.69% 105.12% 105.58%

on Works
(107.18%)

30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
8-Dec 15-Dec 22-Dec 29-Dec

0.0 0.0 0.0 0.0


2.85 2.09 2.70 0.00
0.0 0.0 0.0 0.0
2.85 2.09 2.70 0.00
0.00% 0.00% 0.00% 0.00%
100.00% 100.00% 100.00% 100.00%
0.60% 0.44% 0.56% 0.00%
106.18% 106.61% 107.18% 107.18%

Dec 16-Dec 23-Dec 30-Dec


PROGRESS SUMMARY
Column C Column D

MECHANICAL WORKS
Total Quantity Earned Quantity

459.65
428.13
52.8
50
Piping E r e c ti o n

Total Quantity Earned Quantity


Piping 50 52.8
Erection 428.13 459.65
RY

AL WORKS
Earned Quantity
459.65
428.13
52.8

ng E r e c ti o n
Total DirectMan Power
Present
Craft
(No's)
Foreman 0
Supervisor 2
Fabricator 2
Mill Wright 0
Fitter 10
T. Welder 1
Welder 4
Rigger+ Scafolder 7
Helper 3
Crane operator 0
Painter 2
Electrician 1
Total 32
Erection Quantity Erection
(Tons) Start Date
478.13 16-Jun-22

Weekly Progress (WEEK#29)

Earned till Last


Erection Quantity
Week
(Total Scope) (Tons)
(Tons)
478.13 512.45
Earned Quantity to
Erection
date % Complete Remarks
Finish Date (Tons)
512.45 107.18%

Earned This Week Earned To date


(Tons) (Tons)

0 512.45