Description Qty Unit Rate Amount

Barricading along the operational railway line with railway


supplied rail for safety purpose with contractors
New NS Item-2 manpower and machineries.
For 11.75 MT rail excluding concrete work.
1 Shifting of rails:
Hydra charges 3 Day 5000.00 15000.00
Trailer charges 3 Day 5000.00 15000.00
2 Excavation of pits(31 nos.)
Labour:
Unskilled 7.75 Each 595.00 4611.25
3 Welding:
Highly Skilled labour 6 Day 866.00 5196.00
4 T & P:
Welding machine charges 3 Day 750.00 2250.00
Welding rods 2 Pack 1250.00 2500.00
Total 44557.25
Electricity charges 1 % 445.57
Total 45002.82
Contractors Profit and O.H 15% 6750.42
Total 51753.25
Labour cess 1% 517.53
Cost for 11.75 MT rail welding excluding concrete works Total 52270.78
GST 18% 9408.74
Cost for 11.75 MT rail welding excluding concrete works Total 61679.52