Government Procurement Law d) System of accountability where both the public

officials directly or indirectly involved in the


THE 2016 REVISED IMPLEMENTING RULES
procurement process as well as in the
AND REGULATIONS OF REPUBLIC ACT NO.
implementation of procurement contracts and the
9184, OTHERWISE KNOWN AS THE
private parties that deal with GoP are, when
GOVERNMENT PROCUREMENT REFORM ACT
warranted by circumstances, investigated and held
(Updated as of 31 March 2021) liable for their actions relative thereto.

RULE I – GENERAL PROVISIONS e) Public monitoring of the procurement process


and the implementation of awarded contracts with
Section 1. Short Title and Purpose the end in view of guaranteeing that these contracts
This Updated 2016 Revised Implementing Rules are awarded pursuant to the provisions of the Act
and Regulations, hereinafter called the IRR, is and this IRR, and that all these contracts are
promulgated pursuant to Section 75 of Republic Act performed strictly according to specifications.
No. (R.A.) 9184, otherwise known as the Section 4. Scope and Application of the IRR
“Government Procurement Reform Act,” for the
purpose of prescribing the necessary rules and  Applies to Procurement of Infrastructure
regulations for the modernization, standardization, Projects, Goods and Consulting services
and regulation of the procurement activities of the regardless of source of funds, whether local
Government of the Philippines (GoP). of foreign, by all branches and
instrumentalities of government, its
Section 2. Declaration of Policy departments, offices and agencies,
The provisions of this IRR are in line with the including government-owned and/or-
commitment of the GoP to promote good controlled corporations and local
governance and its effort to adhere to the principles government units, subject to the provisions
of transparency, accountability, equity, efficiency, of Commonwealth Act No. 138.
and economy in its procurement process. It is the  Any treaty or international or executive
policy of the GoP that procurement of Goods, agreement affecting the subject matter of
Infrastructure Projects and Consulting Services this law to which the Philippine government
shall be competitive and transparent, and therefore is signatory shall be observed.
shall undergo competitive bidding, except as 4.1 This IRR shall apply to all procurement of any
provided in Rule XVI of this IRR. branch, agency, department, bureau, office, or
Section 3. Governing Principles instrumentality of the GoP, including government-
owned and/or -controlled corporations (GOCCs),
The procurement of the GoP shall be governed by government financial institutions (GFIs), state
these principles: universities and colleges (SUCs), and local
a) Transparency in the procurement process and government units (LGUs).
in the implementation of procurement contracts 4.2 Any Treaty or International or Executive
through wide dissemination of bid opportunities and Agreement to which the GoP is a signatory
participation of pertinent non-government affecting the subject matter of the Act and this IRR
organizations. shall be observed. In case of conflict between the
b) Competitiveness by extending equal terms of the Treaty or International or Executive
opportunity to enable private contracting parties Agreement and this IRR, the former shall prevail.
who are eligible and qualified to participate in 4.3 Unless the Treaty or International or Executive
competitive bidding. Agreement expressly provides another or different
c) Streamlined procurement process that will procurement procedures and guidelines, R.A. 9184
uniformly apply to all government procurement. The and this IRR shall apply to Foreign-funded
procurement process shall be simple and made Procurement of Goods, Infrastructure Projects, and
adaptable to advances in modern technology in Consulting Services by the GO. The GoP
order to ensure an effective and efficient method. negotiating panels shall, as its default position,
adhere to R.A. 9184 and this IRR, or at the very
least, selection through competitive bidding, in all d) Hiring of Job Order Workers;
Foreign-funded Procurement. If the Treaty or
e) Joint Venture under the revised NEDA
International or Executive Agreement states
Guidelines (GOCC and Private Entities), and Joint
otherwise, then the negotiating panel shall ensure
Venture Agreements by LGU with Private entities;
that the reasons for the adoption of a different rule
and
or method of procurement are clearly reflected in
the records of discussion. f) Disposal of Property and Other Assets of the
Government. (n)
4.4 This IRR shall not apply to the following
activities: Section 5. Definition of Terms
a) Procurement of Goods, Infrastructure For purposes of this IRR, the following terms or
Projects and Consulting Services funded from words and phrases shall mean or be understood as
Foreign Grants covered by R.A. 8182, as follows:
amended by R.A. 8555, entitled “An Act Excluding
Official Development Assistance (ODA) from the a) Act. Refers to R.A. 9184, entitled “An Act
Foreign Debt Limit in order to Facilitate the Providing for the Modernization, Standardization
Absorption and Optimize the Utilization of ODA and Regulation of the Procurement Activities of the
Resources, Amending for the Purpose Paragraph Government and for other Purposes,” otherwise
1, Section 2 of R.A. 4860, As Amended,” unless the known as the Government Procurement Reform
GoP and the foreign grantor/foreign or international Act.
financing institution agree otherwise; b) Approved Budget for the Contract (ABC).
b) Acquisition of real property which shall be Refers to the budget for the contract duly approved
governed by R.A. 107523, entitled “An Act by the HoPE, as provided for in the General
Facilitating the Acquisition of Right-Of-Way Site or Appropriations Act (GAA), continuing, and
Location for National Government Infrastructure automatic appropriations, in the case of national
Projects,” and other applicable laws, rules and government agencies (NGAs); the corporate
regulations; and budget for the contract approved by the governing
board, pursuant to Executive Order (E.O). No. 518,
c) Public-Private sector infrastructure or s. 1979, in the case of GOCCs and GFIs, and R.A.
development projects and other procurement 8292 in the case of SUCs; the budget approved by
covered by R.A. 6957, as amended by R.A. 7718, the Sanggunian through an appropriations
entitled “An Act Authorizing the Financing, ordinance in the case of LGUs. For multi-year
Construction, Operation and Maintenance of contracts, for which a Multi-Year Obligational
Infrastructure Projects by the Private Sector, and Authority (MYOA) or an equivalent document is
for Other Purposes,” as amended: Provided, required, the ABC shall be that incorporated in the
however, That for the portions financed by the GoP, project cost reflected in the MYOA or equivalent
in whole or in part, the provisions of the Act and this document.
IRR shall apply.
For Foreign-funded Procurement, the ABC refers to
4.5 The following are not procurement activities the cost estimate prepared by the Procuring Entity
under R.A. 9184 and this IRR: and approved by the foreign government/foreign or
international financing institution as specified in the
a) Direct financial or material assistance given to
Treaty or International or Executive Agreement.
beneficiaries in accordance with the existing laws,
rules and regulations, and subject to the guidelines c) Bid. Refers to a signed offer or proposal to
of the concerned agency; undertake a contract submitted by a bidder in
response to and in consonance with the
b) Participation in local or foreign scholarships,
requirements of the Bidding Documents. For
trainings, continuing education, conferences,
purposes of, and throughout this IRR, the term
seminars or similar activities that shall be
“Bid” shall be equivalent to and be used
governed by applicable COA, CSC, and DBM rules;
interchangeably with “Proposal” and “Tender.”
c) Lease of government-owned property as
lessor for private use;
d) Bidder. Refers to a contractor, manufacturer, supplies of the growth, production, or manufacture,
supplier, distributor and/or consultant who submits as the case may be, of the Philippines.
a bid in response to the requirements of the Bidding
k) Domestic Entity. Refers to an individual or a
Documents.
sole proprietor who is a citizen of the Philippines or
e) Bidding Documents. Refer to the documents a partnership, corporation, cooperative, or
issued by the Procuring Entity as the basis for bids, association duly organized under the laws of the
furnishing all information necessary for a Philippines and of which at least seventy five
prospective bidder toprepare a bid for the Goods, percent (75%) of the interest or outstanding capital
Infrastructure Projects and/or Consulting Services stock belongs to citizens of the Philippines,
required by the Procuring Entity. habitually established in business and habitually
engaged in the manufacture or sale of the
f) Bids and Awards Committee (BAC). Refers to
merchandise covered by his bid, and the business
the Committee established in accordance with Rule
has been in existence for at least five (5)
V of this IRR.
consecutive years prior to the advertisement and/or
g) Common-Use Supplies and Equipment (CSE). posting of the Invitation to Bid.4
Refer to those goods, materials and equipment that
l) Executive Agreements. Refer to International
are used in the day-to-day operations of Procuring
Agreements except that they do not require
Entities in the performance of their functions. For
legislative ratification.
the purpose of this IRR, CSE shall be those
included in the Electronic Catalogue of the m) Expendable Supplies. Refer to articles which
PhilGEPS. (a) are normally consumed in use within one (1) year
or converted in the process of manufacture or
h) Competitive Bidding. Refers to a method of
construction, or those having a life expectancy of
procurement which is open to participation by any
more than one (1) year but which shall have
interested party and which consists of the following
decreased substantially in value after being put to
processes: advertisement, pre-bid conference,
use for only one (1) year (e.g., medicines,
eligibility screening of prospective bidders, receipt
stationery, fuel, and spare parts).
and opening of bids, evaluation of bids, post-
qualification, and award of contract. For purposes n) Foreign Bid. Refers to any offer of articles,
of, and throughout this IRR, the terms “Competitive materials or supplies not manufactured or not to be
Bidding” and “Public Bidding” shall have the same manufactured in the Philippines, substantially from
meaning and shall be used interchangeably. articles, materials, or supplies of the growth,
production, or manufacture, as the case may be, of
i) Consulting Services. Refer to services for
the Philippines.
infrastructure projects and other types of projects or
activities of the GoP requiring adequate external o) Foreign-funded Procurement. Refers to the
technical and professional expertise that are acquisition of goods, consulting services, and the
beyond the capability and/or capacity of the GoP to contracting for infrastructure projects by the GoP
undertake such as, but not limited to: (i) advisory which are wholly or partly funded by Foreign Loans
and review services; (ii) preinvestment or feasibility or Grants pursuant to a Treaty or International or
studies; (iii) design; (iv) construction supervision; Executive Agreement. For purposes of, and
(v) management and related services; and (vi) throughout this IRR, the term “foreignfunded
other technical services or special studies. General procurement” shall have the same meaning as and
principles on Consulting Services are provided for shall be used interchangeably with “foreign-funded
in Annex “B” of this IRR. projects” or “foreign-assisted projects.”
j) Domestic Bidder. Refers to any person or entity p) Foreign Grants. Refer to grants with no
offering unmanufactured articles, materials or repayment obligations and are provided in
supplies of the growth or production of the monetary form, goods, works, and consultancy
Philippines, or manufactured articles, materials, or services, among others.
supplies manufactured or to be manufactured in the
q) Foreign Loans. Refer to loans, credits, and
Philippines substantially from articles, materials, or
indebtedness with private foreign banks or with
foreign governments, agencies, or instrumentalities roads and bridges, railways, airports, seaports,
of such foreign governments, foreign financial communication facilities, civil works components of
institutions, or other international organizations with information technology projects, irrigation, flood
whom, or belonging to countries with which, the control and drainage, water supply, sanitation,
Philippines has diplomatic relations, as may be sewerage and solid waste management systems,
necessary and upon such terms and conditions as shore protection, energy/powerand electrification
may be agreed upon, to enable the GoP to finance, facilities, national buildings, school buildings,
either directly or through any government office, hospital buildings, and other related construction
agency or instrumentality or any government- projects of the government. For purposes of, and
owned and controlled corporation, industrial, throughout this IRR, the term “Infrastructure
agricultural or other economic development Projects” shall have the same meaning as, and
purposes or projects authorized by law. shall be used interchangeably with, “civil works” or
“works.”
r) Goods. Refer to all items, supplies, materials
and general support services, except Consulting v) International Agreement. Refers to a contract
Services and infrastructure projects, which may be or understanding, regardless of nomenclature,
needed in the transaction of public businesses or in entered into between the GoP and another
the pursuit of any government undertaking, project government or foreign or international financing
or activity, whether in the nature of equipment, institution in written form and governed by
furniture, stationery, materials for construction, or international law, whether embodied in a single
personal property of any kind, including non- instrument or in two (2) or more related
personal or contractual services, such as, the repair instruments.
and maintenance of equipment and furniture, as
w) Non-expendable Supplies. Refer to articles
well as trucking, hauling, janitorial, security, and
which are not consumed in use and ordinarily retain
related or analogous services, as well as
their original identity during the period of use,
procurement of materials and supplies provided by
whose serviceable life is more than one (1) year
the Procuring Entity for such services. The term
and which add to the assets of the GoP (e.g.,
“related” or “analogous services” shall include, but
furniture, fixtures, transport and other equipment).
is not limited to, lease of office space, media
For this IRR, the term non-expendable supplies
advertisements, health maintenance services, and
shall include semi-expendable property. (a)
other services essential to the operation of the
Procuring Entity. (a) x) Philippine Government Electronic
Procurement System (PhilGEPS). Refers to the
s) Government Procurement Policy Board
electronic System as provided in Section 8 of this
(GPPB). Refers to the Body created in accordance
IRR. For purposes of, and throughout this IRR, the
with Rule XX of this IRR.
term “PhilGEPS” shall have the same meaning as,
t) Head of the Procuring Entity (HoPE). Refers to: and shall be used interchangeably with, “G-EPS”
(i) the head of the agency or body, or his duly referred to in the Act.
authorized official, for NGAs and the constitutional
y) Philippine National. Refers to an individual or a
commissions or offices, and other branches of
sole proprietor who is a citizen of the Philippines or
government; (ii) the governing board or its duly
a partnership, corporation, or association organized
authorized official, for GOCCs, GFIs and SUCs; or
under the laws of the Philippines of which at least
(iii) the local chief executive, for LGUs: Provided,
sixty percent (60%) of the capital or interest is
however, That in an agency, department, or office
owned by citizens of the Philippines, or
where the procurement is decentralized, the head
cooperatives registered with the Cooperative
of each decentralized unit shall be considered as
Development Authority.(a)
the HoPE, subject to the limitations and authority
delegated by the head of the agency, department, z) Portal. Refers to a website that integrates a wide
or office.(a) variety of contents for the purpose of attracting and
aggregating multiple users together in a central
u) Infrastructure Projects. Include the
virtual space.
construction, improvement, rehabilitation,
demolition, repair, restoration or maintenance of
aa) Procurement. Refers to the acquisition of o Procuring unit that is mainly
goods, consulting services, and the contracting for responsible for the procuring
infrastructure projects by the Procuring Entity. In process of the government
case of projects involving mixed procurements, the o IRR allows the HoPE to create a
nature of the procurement, i.e., Goods, secretariat (support unit)
Infrastructure Projects or Consulting Services, shall  Functions:
be determined based on the primary purpose of the a) Advertise and/or post the invitation to
contract. Procurement shall also include the lease bid
of goods and real estate. With respect to real b) Conduct pre-procurement and pre-bid
property, its procurement shall be governed by the conference
provisions of R.A. 10752 and other applicable laws, c) Determine the eligibility of prospective
rules and regulations. (a) bidders
bb) Procuring Entity. Refers to any branch, d) Receive bids
constitutional commission or office, agency, e) Conduct the evaluation of bids
department, bureau, office, or instrumentality of the f) Undertake post-qualification
GoP (NGA), including GOCC, GFI, SUC and LGU proceedings
procuring goods, infrastructure projects and g) Recommend award of contracts to the
consulting services. Head of the Procuring Entity of his duly
authorized representative
cc) Treaties. Refer to international agreements h) Recommend the imposition of sanctions,
entered into by the GoP which require legislative and perform such other related functions
ratification after executive concurrence. as may necessary, including the
creation of a Technical Working Group
dd) Universal or Commercial Banks. Refer to
from a pool of technical, financial and/or
universal or commercial banks duly authorized
legal experts to assist in the
under R.A. 8791, otherwise known as “The General
procurement process.
Banking Act of 2000.”
PHILGEPS
COMPETITIVE BIDDING
 Philippine Government Electronic
 General Rule: All Procurement shall be
Procurement System
done through Competitive Bidding
 A single portal that shall serve as the
 Competitive Bidding refers to a method of
primary source of information on all
procurement which is open to participation
government procurement.
by any interested party and which consist of
 The PhilGEPS shall serve as the primary
the following processes: advertisement, pre-
and definitive source of information on
bid conference, eligibility screening of bids,
government procurement.
evaluations of bids, post qualification, and
 The PhilGEPS shall have a centralized
award of contract, the specific requirements
electronic bulletin board for posting
and mechanics of the law.
procurement opportunities, notices, awards,
 Exception: When Alternative Modes of
and reasons for award. All Procuring
Procurement applies
Entities are required to post all procurement
BIDS AND AWARDS COMMITTEE opportunities, results of bidding and related
information in the PhilGEPS bulletin board.
 Composition: The Head of Procuring  The PhilGEPS shall have a centralized
Entity (HOPE) shall designate at least five electronic database of all manufacturers,
more than seven (7) members to the BAC of suppliers, distributors, contractors, and
unquestionable integrity and procurement consultants registered under the system.
proficiency.
o Term: at least 1 year but they will OVERVIEW OF THE PROCUREMENT PROCESS
continue to serve their function until
makahanap sila ng kapalit
circulation, the PHILGEPS and the website
of the Procuring Entity, if available
o Contains: description of the general
matter of the procurement, general
statement for the criteria to be used,
time, place, deadlines for the
submission of the bid, approved
budget of the contract, source of
 Notice to proceed  Contract funds, availability of bidding
implementation documents, duration of contract
o New amendment: okay lang kahit
I. PREPARATION OF BIDDING DOCUMENTS
hindi na sa newspaper of general
 Bidding Documents refer to documents circulation
issued by the Procuring Entity as the basis c. Pre-bid conference – For contracts with an
for Bids, furnishing all information necessary Approved Budget Contract (ABC) of
for a prospective bidder to prepare a bid for 1,000,000 or more, the BAC shall convene
the Goods, Infrastructure Projects, and at least one (1) pre-bid conference to clarify
Consulting Services to be provided. and/or explain any of the requirements,
o Includes: approved budget for the terms, conditions, and specifications
contract, instructions to bidders (who stipulated in the Bidding Documents.
is eligible to bid?), when is the pre- o Must be held at least 12 calendar
bid conference, when is the deadline days before the deadline for the
for the submission of bids, when ma- submission of the receipt of bids but
oopen, the technical specifications not earlier than 7 calendar days from
needed, form of bid, delivery time, the posting of the PHILGEPS of the
form of bid security that is accepted invitation to bid
o Binibili ang bidding documents o Hindi pa nagstastart sa pre-bid
o It is allowed for the procuring entities conference ang pagreceive ng bid
to sell the documents at a cost for
III. RECEIPT AND OPENING OF BIDS
them to recover the cost in
preparation of the documents  Amendment: allowed the submission of 2
separate sealed envelopes (Technical and
II. INVITATION TO BID
Financial) and the submission of password-
a. Pre-procurement Conference – assess protected bidding documents in compressed
the readiness of the procurement in terms of folders
confirming the certification of availability of  Technical: eligibility requirements,
funds, as well as reviewing all relevant certificate of registrations, PHILGEPS
documents and the draft Invitation to Bid, as certification, statement of all ongoing
well as consultants hired by the agency government and private contracts, licenses,
concerned and the representative of the statement of single largest completed
end-user. contract (Procurement of goods: 50% of
o Kailangan ng pre-procurement the approved budget of the contract ay
process if your procurement meron ka na dati pa at natapos mo,
exceeds: expendable supplies: 25%, NFCC
 Goods: P2,000,000 computation or committed line of credit
 Infrastructure: P5,000,000  Financial: how much yung bid mo,
 Consulting Services: confidential until the day of bidding
P1,000,000  Bids shall be received by the BAC on the
b. Advertising and Contents of the date, time, and place specified in the
Invitation to Bid – posting in the Procuring Invitation to Bid/Request for Expression of
Entity's premises, in newspapers of general Interest. The following periods from the last
day of posting of the Invitation to
Bid/Request for Expression of Interest up to the lowest calculated responsive bid
the submission and receipt of bids shall be or the highest rate of responsive bid
observed: in case of consultants as the case
a) For Goods, a maximum period of may be has signed the contract and
forty-five (45) calendar days. furnished the performance security
b) For Infrastructure Projects, the (yung nanalong bidder ay nakapirma
following maximum periods: na ng contract and ng performance
security)
o Attach a sworn statement disclosing
o With ABC of 50M and below relations with the procurement entity
– 50 calendar days or other bidders (no conflict of
o With ABC above 50 million interest)
– 65 calendar days o If no disclosure of relations = bid is
c) For Consulting Services, a maximum invalid
period of seventy – five (75)  Bid Validity
calendar days. o Bids and Bid securities shall be valid
 Modification and Withdrawal of Bids for such reasonable period of time
o A bidder may modify his bid, indicated in the Bidding Documents.
provided that this is done before the The duration for each undertaking
deadline for the receipt of bids. The shall take into account the time
modification shall be submitted in a involved in the process of Bid
sealed envelope duly identified as a evaluation and award of contract.
modification of the original bid and
IV. BID EVALUATION
stamped received by the BAC.
o A bidder may, through a letter,  The BAC will evaluate the bids on equal
withdraw his bid or express his footing to ensure a fair and competitive bid
intention not to participate in the comparison
bidding before the deadline for the  BAC will open first the technical envelope
receipt of bids. In such case, he then it will be evaluated based on a pass or
shall no longer be allowed to submit fail criteria
another Bid or the same contract o Based on the requirements
either directly or indirectly. o Complete = passed
 Bid Security o Incomplete = failed
o All Bids shall be accompanied by a  All passed: will open the financial envelope
Bid security, which shall serve as o How much yung bid mo
guarantee that, after receipt of the o Abstract of bids: summary of the
Notice of Award, the winning bidders bidders, how much yung bid, lowest
shall enter into contract with the calculated bid, sign
Procuring Entity within the stipulated
time and furnish the required V. POST QUALIFICATION
performance security.
 The stage where the bidder with the Lowest
o Cash, check, irrevocable letter of
Calculated Bid, in the case of goods and
credit, surety bond, bid security
Infrastructure Projects, or the Highest Rated
declaration
Bid, in the case of Consulting Services,
 Cash/Letter of Credit: 2% of
undergoes verification and validation
ABC
whether he has passed all the requirements
 Surety bond: 5% of ABC
and conditions as specified in the Bidding
 Bid security declaration:
Documents.
undertaking under oath,
 If the bidder with the Lowest Calculated Bid
affidavit
or Highest Rated Bid passes all the criteria
o Natalo sa bid: the bid security is
for post-qualification, his Bid shall be
refundable only after the bidder with
considered the "Lowest Calculated which it submits a bid, which is found to be
Responsive Bid," in the case of Goods and responsive to the bidding requirements;
Infrastructure or the "Highest Rated b. If after the advertisement, more than one
Responsive Bid," in the case of Consulting prospective bidder applies for eligibility
Services. check, but only one bidder meets the
 However, if a bidder fails to meet any of the eligibility requirements or criteria, after
requirements or conditions, he shall be which in submits a bid which is found to be
"post-disqualified" and the BAC shall responsive to the bidding requirements; or
conduct the post-qualification on the bidder c. If after the eligibility check, more than one
with the second Lowest Calculate Bid or bidder meets the eligibility requirements, but
Highest Rated Bid. only one bidder submits a bid, and its bid is
 In all cases, the contract shall be awarded found to be responsive to the bidding
only to the bidder with the Lowest requirements.
Calculated Responsive Bid or Highest
Rated Responsive Bid.
IV. AWARD, IMPLEMENTATION, AND
FAILURE OF BIDDING
TERMINATION OF CONTRACT
There shall be a failure of bidding if:
a) No bids are received;
b) No bid qualifies as the Lowest Calculated
Responsive Bid; or,
 All prospective bidders are declared
ineligible
 All bids fail to comply with all the bid
requirements or fail post qualification, or,
in the case of Consulting Services, there
is no successful negotiation;
c) Whenever the bidder with the highest
rated/lowest calculated responsive bid
refuses, without justifiable cause to accept
the award of contract, as the case may be.
 Under any of the above instances, the
contract shall be re-advertised and re-bid.
BAC shall observe the same process and
set the new periods according to the same
rules followed during the first bidding. After
the second failed bidding, however, the
BAC may resort to negotiated
procurement.
SINGLE CALCULATED/RATED AND
RESPONSIVE BID  HoPE approves the recommendation of
BAC
A single calculated/rated and responsive bid shall
 Within 15 calendar days:
be considered for awar under of the following
o Disapproval is based on valid,
circumstances:
justifiable, and reasonable grounds
a. If after advertisement, only one prospective o Disapproved bidder may file an
bidder submits a Letter of Intent and/or appeal or request for reconsideration
applies for eligibility check, and meets the within 3 calendar days from receipt
eligibility requirements or criteria, after of the decision or notice of
disapproval
o After receipt of request for  Grounds for termination of contracts:
reconsideration, HoPE will resolve o In case of procurement of goods,
within 7 calendar days and will failure to deliver at least 10%
furnish their decision to the bidder contract price
and BAC o In case of infrastructure, due to
o What if disqualified talaga? contractor's fault, negative slippage
 BAC will proceed to the of 15% of the or more while project
second lowest calculated bid is ongoing, or 10% or more in the
 If okay naman pala edi for da go sa notice completion of work, neglect,
of award negligence, sublets any part of the
 Bid Security vs. Performance Security contract without approval
o Bid Security: kapag nanalo ka, o In contracts for Consulting
magproproceed ka sa contract Services, failure deliver or perform
o Performance Security: guarantee on the Outputs and Deliverables within
the part of the government that the the period(s) specified in the
bidder will faithfully perform the contract, unable to deliver or perform
obligations under the contract a material portion of the Outputs and
 Cash, irrevocable notice of Deliverables for a period of not less
credit, surety than sixty (60) calendar days after
 Notice to proceed: go na accla deliver ka the Consultant's receipt of the notice
na raw ng goods. from the Procuring Entity stating that
o Through BAC the circumstance of force majeure is
o Notice to proceed & approved deemed to have ceased or fails to
contract: need to be published in the perform any other obligation under
website of PHILGEPS and sa the contract
website mismo ni bidder o For convenience (not economical or
 From the opening of the bid up to the not practical)
awarding, it should not exceed 3 months or o Insolvency of the supplier, contractor
maybe shorter as determined by the or consultant
procuring entity o Unlawful acts
o Termination by contractor/consultant
VII. CONTRACT IMPLEMENTATION AND
TERMINATION ALTERNATIVE METHODS OF PROCUREMENT

 The guidelines for contract implementation  These are subject to approval by HoPE
differs depending on the type of  Must satisfy the conditions
procurement.
 SPLITTING OF GOVERNMENT
CONTRACTS
o Splitting of Government Contracts is
not allowed. Splitting of Government
Contracts means the division or
breaking up of contracts into smaller
quantities and amounts, or dividing
contract implementation into artificial
phases or sub-contracts for the
purpose of evading or circumventing
the requirements of the law,
particularly the necessity of
competitive bidding and the
requirements for the alternative
methods of procurement.
 DBM-PS – personal shopper ng
government

EMERGENCY PROCUREMENT PROCEDURE


 The BAC or the End-user unit or any other
appropriate bureau, committee, support or
procuring unit shall request for the approval
of the Annual Procurement Plan (APP) from
the Head of Procuring Entity (HoPE) to
cover the Procurement Project. The APP
may only be approved by the HOPE upon
confirmation of the existence and veracity of
the ground(s) relied upon in resorting to
Negotiated Procurement (Emergency
Cases) and the existence of funds for the
purpose. Thus, by approving the APP, the
HOPE effectively confirms the existence of
the grounds for emergency procurement,
thereby dispensing with the previous
requirement for a written confirmation from
the HOPE prior to the approval of contract.
 The BAC or the End-user unit or any other
appropriate bureau, committee, support or
procuring unit, authorized by the HOPE
shall then directly negotiate with a legally,
technically, and financially capable supplier,
contractor, or consultant.
 Upon recommendation of the BAC or End-
user unit or any other a bureau, committee,
support or procuring unit duly authorized by
the HOPE, the contract shall be immediately
awarded to the legally, technically, and
financially capable supplier, manufacturer,
distributor, contractor, and consultant,
contractor, or consultant.
 Except for contracts with ABC of Fifty
Thousand Pesos (PhP50,000.00) and
below, the BAC, through the Secretariat
shall post for information purposes the
Notice of Award, contract or purchase order,
including the Notice to Proceed, if
necessary, in
I. the PhilGEPS website;
II. the website of the PE or its electronic
procurement service provider, if any;
III. any conspicuous place in the premises
of the PE.

OTHER KINDS OF NEGOTIATED


PROCUREMENT

 Take-Over of Contracts – the previous


contract awarded was rescinded
 Adjacent or Contiguous – subject contract
is adjacent or contiguous to an ongoing
infrastructure, consulting services, etc.