SINGAPORE SULFUR DISPOSITION PROJECT

CENTRIFUGAL PUMP CHECK LIST Page

EQUIPMENT NO: FW CONTRACT NO : 1-PD-0376A

SYSTEM: DWG NO: REV:

The following items have been inspected and verified:- YES N/A NO
1. There is no visual damage to the equipment.
2. Equipment foundation/support steelwork has been released.(By FW)
3. Temporary shipping items removed.
4. Mechanical seal / packing installed as per G.A. and P&ID.
5. Equipment has been aligned and levelled.
6. Primary cold alignment completed.
7. Equipment has been released for grouting.
8. Inspection, maintenance record cards completed.
9. All vendor installation acitvities completed and reports submitted.(By FW)
10. The item is clean and free from debris internally and externally.
11. Equipment installed in accordance with G.A./P&ID.
12. Client Asset Numbers verified.
13. Equipment Tag number verified
14. Piping interfaces completed.(By FW)
15. Electrical terminations completed.(by FW)
16. Instrument terminations/Hook-ups completed.(By FW)
17. Pump vents and drains fitted.
18. Temporary suction strainers fitted
19. Electrical motor inspection 'Care and Protection'(FW 3404).
20. Final cold alignment completed.
21. Coupling installed.
22. Coupling guard fitted.
23. Preservation covers removed.
Remarks* / No Remarks* (*Delete as applicable)

COMPLETED BY WEC Foster Wheeler Client (if applicable)

COMPANY

SIGNATURE

NAME

DATE
FW3315