Professional Documents
Culture Documents
1
COREM, 1180, rue de la Minéralogie,
Québec (Québec) G1N 1X7, CANADA
2
Québec Cartier Mining Company, 24, boul. des Îles,
Port-Cartier (Québec) G5B 2H3, CANADA
3. RESULTS
Concentration (% w/w)
Table 1. Linear responses (R²) are excellent over the
concentration spans of each element measured. The 3
relative slope expresses the percentage of change of 2.5
the signal as a reaction to a 1% change in
concentration; it is an indication of the amplitude of 2
the response. It is thus seen that the manganese
response is strong while that of silicon is not. As can 1.5
be expected, this indicator is anti-correlated with the
precision obtained (SDVAC). The relative SDVAC 1
Si LIBS
on the other hand weighs the response of each 0.5
Si Chem
C LIBS
element against its concentration in the ore; on this C Chem
basis, the quality of the silicon measurements is very 0
good compared to the other elements. 9:30 10:30 11:30 12:30 13:30 14:30
Time
Table 1 Results of pilot plant preliminary tests Fig. 2. Tracking of silicon and carbon concentrations
in the iron ore slurry on September 7, 2005.
C Si Mg Ca Mn
Concentration span 0.32 − 2.62 − 0.25 − 0.54 − 0.11 −
(%) 1.12 3.31 0.55 0.87 0.32
One month after start-up, the tracking graph
reproduced in Fig. 2 was obtained. During the trial,
Relative stdev (%) 7.0 2.1 2.2 1.7 1.5 some perturbation of the process promoted the
R² 0.9986 0.9906 0.9981 0.9970 0.9766 variation of the concentrations of carbon and silicon.
The correlation between the LIBS and laboratory
Relative slope 119 19 70 36 273
(% / %)
results scores 0.91 for silicon and 0.96 for carbon.
SDVAC (%) 0.07 0.21 0.09 0.07 0.01 During the first year of operation, the up-time for the
Relative SDVAC 9.7 7.0 21.7 10.0 6.5 instrument was over 90% (excluding those periods
(%) when the system was intentionally stopped). The
most time-consuming problem in the first months
was related to maintaining a steady flow of slurry;
The instrument was shipped and installed at QCM’s pipe clogging and pipe wear were especially
pelletizing plant in August 2005. QCM took charge troublesome; these problems were solved over time.
of the primary sampling of the process; and of the An optics alignment problem and a security failure
transportation and disposal of the slurry after use. occurred which necessitated corrective actions. Apart
The material to be measured was the output of the from these discrete events, the system only needed
ball mills, just prior to the final filtration and regular maintenance (to change laser flashlamps bi-
pelletizing steps, and occurred as a slurry holding yearly among other things). It is concluded that the
some 72% solids. A primary sampling device was instrument needs only minimal supervision – less
installed on the process line to extract slurry at a rate than 10 hours a week on the part of QCM personnel –
of about 150 litres per minute. A secondary sampler in line with prospective specifications.
was inserted after the LIBS measurement head to
extract samples for calibration purposes. On-site performance evaluation of the analyzer was
done once the instrument and sample manipulation
The analyzer was started and set to provide refreshed were mastered. This consisted in determining the
concentration values every three minutes (each one accuracy of the measurements with respect to the
of the three acquisition windows is analyzed for one analyses produced by QCM’s chemistry laboratory.
minute). A connection was established between the The precision (smallest detectable variations in
instrument’s command unit and the plant’s local concentration) determined for the measurements is
control system so that the LIBS data could be comparable to what was obtained in the preliminary
exported, formatted and displayed on the operator’s tests in COREM’s pilot plant. The accuracy though,
control screen. Local personnel was trained to look which was anticipated to hold within the precision
over the instrument on a daily basis; COREM span, was at times not met. The most problematic
remained as backup for servicing instrumental and case was that of silica for which absolute biases
technical issues. exceeding 0.25% were noted when comparing the
LIBS results with daily check tests.
4. DISCUSSION measurements add up statistically to represent tons of
actual material as it flows by, compared to the minute
Calibration of the LIBS instrument is needed in order grams of slurry bleeded off the process line every 15
to maintain the analyzer in a proper working state. minutes and averaged over some 2 to 4 hours.
To this purpose, periodic calibration campaigns are
to be performed (a few times a year) by intentionally Any steady variation of the LIBS signal can readily
upsetting the process. This is done by slowing down be interpreted as a deviation from a prior state. In this
slurry pumps, altering mill throughputs, temporarily manner, the process operator can bring down his
modifying additives feed, or by any other means that reaction time from hours to some 15 minutes or so,
will induce a sizable variation of the concentrations thereby gaining timely and tighter control over the
of the components in the slurry solids. Taking a process. This advantage, in turn, translates in
number of samples during the event provides data to products of higher and consistent quality.
compute a new calibration curve for each element
measured. Afterwards, daily checks serve to follow Furthermore, the on-line analyzer turned out to be a
the instrument’s routine level of performance; in this very sensitive detector of various process upsets, like
case, only one sample is taken to establish the tuning mill failures, occasional use of recycled water, etc.
between the LIBS and the lab. Also, the instrument is a powerful tool to study the
process itself. For example, establishing the grinding
The accuracy problem observed (i.e. the fit to the kinetics of the ore (around 20 minutes) with respect
laboratory results) is limited to the comparison of to the additives coke (15 minutes) and dolomite (18
LIBS results with routine checks performed on a minutes) was merely a straightforward task with the
daily basis. Indeed, when specific calibration on-line instrument.
campaigns are run by intentionally perturbing the
process, the quality of the calibration curves and the
precisions obtained are very good (similar to results 5. CONCLUSION
from preliminary tests). It was observed though, that
daily check results line up on a slightly different An on-line analyzer based on Laser-Induced
calibration slope. It is thus concluded that provoked Breakdown Spectroscopy was designed, assembled
process upsets are not truly representative of real and installed in an iron ore pellet plant. The field
process dynamics. This situation may arise from the application consists in measuring elements C, Si, Mg,
fact that over the short period during which a Ca and Mn in the solids embedded in a slurry; the
perturbation occurs, long term variables such as objective is to check compliance with prescribed
particle grain size and ore matrix composition remain concentration levels. Tracking of these elements in
essentially constant; conversely, significant intervals of 3 minutes is a considerable enhancement
excursions may be experienced on longer time relative to the pre-existing situation (hours). The
scales. Based on this reasoning, it was proposed that precision achieved is sufficient to enable plant
practicable calibration curves should be constructed operators to detect any process upsets and apply
by accumulating daily check results rather than corrective measures in a timely manner. The on-line
relying on calibration curves derived from analyzer can also be used to study the process itself
intentionally perturbed process situations. by performing tests to determine process dynamics or
the response to some deliberate action. The LIBS
In addition, it was found that calibration (for silica analyzer is up and running in the pellet plant since
especially) must be tailored to the current pellet type September 2005.
in production in order to correctly account for the
different yields observed as a function of the pellet
composition. (Iron ore pellet plants produce pellets ACKNOWLEDGEMENTS
of different “recipes”, varying in silicate content,
notably, to meet customer specifications.) It is A commitment for quality and close collaboration
argued that the dual nature of the silicon-bearing between the research and industrial partners are two
minerals in the slurry (silica in the native ore and factors that have significantly contributed to make
silicates in the additives) is responsible for this this project a success. The authors wish to thank
situation. Indeed, indications to the effect that silica Steeven Dubord and Stéphane Morin from QCM for
yields less than silicates under LIBS excitation have their technical implication in looking over the
been accumulated but remain to be verified. installed instrument. The devoted involvement in the
project of COREM’s Éric Proulx, Luc Tardif,
In spite of the slight bias in accuracy, the instrument Frédéric Michaud, Pierre Laprade, Rémi Leclerc,
remains a very capable trend monitor for following Daniel Mainville and Jean-Guy Chartrand is also
the chemistry of the ore in quasi real-time (three- gratefully acknowledged.
minute intervals between measurements). The on-
line measurements display a clear advantage over
conventional average-sampling and delayed
chemical assaying. Indeed, the continuous
REFERENCES