Professional Documents
Culture Documents
Abstract: A blast furnace hearth chill can be one of the most serious disruptions in the
steelmaking process, resulting in equipment damage and extended shutdowns. In order to
provide the operators with advance notification of potential chill conditions at Dofasco’s
#4 Blast Furnace hearth, the Blast Furnace Disaster Avoidance System was developed.
The system uses a multivariate statistical model to predict the hot metal temperature two
hours in advance. Results analysis has shown that the system is able to provide advance
notice of 70% of potential chill conditions. Copyright © 2007 IFAC
1. INTRODUCTION 2. BACKGROUND
A blast furnace hearth chill occurs when the 2.1 Process Description
temperature of the hot metal that is tapped from the
furnace is too low. When the hot metal temperature The first process in a steelmaking facility is the blast
is low, the hot metal and slag become more viscous. furnace, which is illustrated in Fig. 1. Iron, coke,
This can cause difficulties with the drainage of the flux (limestone/dolomite), heated air (hot blast), fuel,
hot metal from the furnace. If the temperature is low and other components are combined in the blast
enough, the hot metal may begin to solidify within furnace to produce hot metal, or “pig iron”. The hot
the piping. metal is then used as the raw material in the
steelmaking plant.
Previous chilled hearth conditions at Dofasco have
resulted in shutdowns of approximately 1 to 2 days The blast furnace is a continuous counter-current
to remove the hot metal and slag from the furnace batch operation in which the iron, coke, and flux are
and to replace damaged equipment. The shutdowns added at the top of the furnace while the hot blast and
were followed by recovery periods of several days to fuel are introduced through openings at the bottom of
bring the furnace back up to normal operation. The the furnace. The heated air reacts with the fuel and
cost of such a shutdown can range in the millions of coke to produce the heat required for the
dollars. A system which would detect the hearth reduction/smelting process. The reduced iron melts
chill in an early stage and allow the operator and accumulates in the bottom of the hearth, while
sufficient time to take corrective action would result the by-product of the process, slag, which consists of
in extension of the furnace campaign life, prevention the iron ore impurities and flux, accumulates on top
of unsafe and unhealthy working conditions for the of the hot metal.
operators, and production gains by avoiding lengthy
furnace shutdowns, The lower part of the blast furnace, or hearth, is
operated batch-wise in that hot metal and slag are
This paper describes a multivariate statistical model periodically drained out of the furnace through tap
developed to predict the hot metal temperature two holes. The time between successive furnace
hours in advance at Dofasco’s #4 Blast Furnace. The drainages is termed a cast and is typically 2-3 hours.
system alerts the operator when the predicted hot The residence time of the iron in a blast furnace is
metal temperature is below a threshold value. The approximately 8 hours.
operator can then follow standard operating
procedures to prevent the hearth chill.
3. MODEL DEVELOPMENT
1425
4. ONLINE RESULTS
1400
The online system was modified to provide
predictions every 20 minutes although actual hot
1375
1375 1400 1425 1450 1475 1500 1525 metal temperature measurements are only available
o
Predicted Hot M etal Temperature ( C) once per cast. This increase in frequency allows the
operator to visualize how the hot metal temperature
Fig. 2. Comparison between predicted and actual hot is changing between measurements.
metal temperature.
The system has been implemented online in Furnace. Results have shown that the model is
background mode. In this mode, ironmaking successful in predicting 70% of the near-hearth chill
technology engineers use the system for troubling conditions in which the measured hot metal
shooting purposes; however, operators do not receive temperature is below the critical temperature for two
the alarms and thus can not take corrective action as or more successive casts with at least 1 hour notice.
a result of the alarms. The corrective actions are not
taken until the first measured hot metal temperature 1550
is below the critical limit.
1525
Time
A summary of the online performance is shown in
Table 1. In the table below, a fault is considered a Measured Predicted Active Alarm Period
near-chill incident in which the measured hot metal Fig. 3. Plot of predicted hot metal temperature
temperature is below the critical temperature for two during a near-chill situation in which the
or more casts. measured cast temperature was below the critical
temperature for 3 casts.
Table 1. Performance of Blast Furnace Disaster
Avoidance System. Due to the success of the system in background
mode, a decision was made to proceed with the full
Performance Criteria Value implementation of the system at Dofasco’s #4 Blast
Total number of faults 10 Furnace. The system will also be expanded to
Faults detected with >1 hour notice 7 Dofasco’s #2 Blast Furnace.
Faults detected with <1 hour notice 2
Faults not detected 1
REFERENCES
A plot of one of the near-chill incidents is shown in Burgess, J.M. (1992). Modelling of Ironmaking
Fig. 3. The period in which the alarm is active is Process. Process Technology Conference
shaded on the graph. This alarm period corresponds Proceedings, 10, 23-38.
to the predicted temperatures which are plotted two Geladi, P. and B.R. Kowalski (1986). Partial Least-
hours in the future. In this example, the first alarm is Squares: A Tutorial. Analytics Chimica Acta,
issued 3.5 hours before the first hot metal 185, 1-17.
temperature measurement below the critical Hoskuldsson, A. (1988). PLS Regression Methods.
temperature is taken. The predicted hot metal Journal of Chemometrics, 2, 211-228.
temperature briefly rises above the alarm threshold Jimenez, J., J. Mochon, J.S. de Ayala and F. Obeso
and then falls below once again. The alarm is (2004). Blast Furnace Hot Metal Temperature
subsequently re-issued until the predicted Prediction through Neural Networks-Based
temperature again increases above the alarm Models. ISIJ International, 44 (3), 573-580.
threshold after the near-chill condition in the hearth Kresta, J.V., T.E. Marlin, and J.F. MacGregor
has been corrected. (1994). Development of Inferential Process
Models Using PLS. Computer Chem. Engng, 18
If the Blast Furnace Disaster Avoidance System were (7), 597-611.
fully implemented in the above example, the operator Otsuka, Y., M. Konishi, K. Hanaoka, and T. Maki
would have received 3.5 hours notice of the near- (1999). Forecasting Heat Levels in Blast
chill condition. This would have been sufficient time Furnaces Using Neural Network Model. ISIJ
to follow standard operating procedures (SOPs) to International, 39 (10), 1047-1062.
prevent the potential hearth chill. Singh, H., N.V. Sridhar, and B. Deo (1996).
Artificial Neural Nets for Prediction of Silicon
Content of Blast Furnace Hot Metal. Steel
5. CONCLUSIONS Research, 67 (12), 521-527.