You are on page 1of 3

Q) Target =?

No. of operators in line = 50


Line eff% = 75%
GARMENT SAM = 30
Answer – A) 300 B) 500 C) 400 D) 600

Q )RAM’S BOTTOM FOLD


LINE EFF = 75%
OPERATION SAM = 1MIN
TARGET = A) 360 B) 400 C) 300 D) 500

Q)
RAM EFF%
UNIT PRODUCED = 480
OPERATION SAM = 1MIN
EFF% = A) 100% B) 50% C) 80% D) 70%
Q)
LINE OUTPUT = 600
GARMENT SAM = 20 MIN
NUMBER OF OPERATORS = 50
LINE EFF% = A) 70% B) 60% C) 50% D) 80%

Q ) Machine Productivity =?
Line Output = 400
No. of Machine = 40
Machine Productivity = A) 10 B) 20 C) 30 D) 40

Q ) Labour productivity =?
Line Output = 50
No. of Operator = 40
No. of Helper = 10
Labour Productivity = A) 1 B) 1.5 C) 2 D) 0.5

Q)
Total pieces loaded till date = 500
Total Piece out till date = 400
WIP = A) 100 B) 150 C) 50 D) 200

Formula#8:  Standard Time = (Observed time X observed rating) +


Allowances

Allowances – Relaxation allowance, contingency allowance

Q)
M/C UTILIZATION % =?
Actual m/c running time = 420 min
Time Available = 480 min UTILIZATION % = A) 87.5% B) 90% C) 80%
D) 75%
Q)
Total available working minute in a day - 480 min
No. of labours – 50
Cost/min – A) 8.33 B) 9.33 C) 7.33 D) 6.33

Q)
Production Cost per unit =?
Total cost incurred in a day – 10 lakh
No. of garment produced in a day – 20000
Production cost per unit = A) 50 B) 40 C) 30 D) 20

Q)
MMR =?
Total manpower of the factory = 2000
Total number of sewing machines = 1000
MMR = A) 2 B) 1 C) 3 D) 4

You might also like