NEWREST WORKSCHEDU

S/N ACTIVITIES No of days


0 1 2 3
1 80% MOBILIZATION Day 0
2 REMOVAL OF ALL EXISTING PASTING 3
3 RESPRAYING OF TRUCKS 5
4 PANEL BEATER WORK ON PICK UPS 5
PRODUCTION OF SIGNAGES 14
5 INSTALLATION OF RECEPTION SIGNS 1
6 INSTALLATION OF INDOOR SIGNAGES
5
7 SPRAYING OF CONTAINERS 5
8
20% BALANCE PAYMENT UPON
COMPLETION
NEWREST WORKSCHEDULE FOR LAGOS OFFICE

Days
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19