1 CENG5241:HIGHWAY ENGINEERING-III
CHAPTER-1:ROAD
CONSTRUCTION
Instructor: Amare T.
amentilahun23@gmail.com
Lecture Outlines
2
Introduction
Subgrade preparation and Improvement
Sub-Base course construction
Base course construction
Construction of Asphalt Concrete
2
Introduction
3
Road construction covers:
- new construction, re-construction or
rehabilitation, and improvements of an existing
road, overlays,…etc. starting from earthwork
and finishing with top bituminous or concrete
surface.
Highway pavement is a structure composed of:
Subgrade
Sub-base course
Base course
Surface course
3
Introduction
4
Asphalt Concrete (AC) Base Course
Aggregates
Natural Soil (Subgrade)
Sub base Course
Subgrade preparation and Improvement
5
SUBGRADE LAYER
CONSTRUCTION
Subgrade preparation and Improvement
6
The Subgrade prepared by bringing is to desired
grade and chamber and by compacting adequately.
The Subgrade may be either in embankment or in
excavation.
The various operations involved in the preparation
of sub-grade are as follows:
i. Site clearance
ii. Earthwork
iii. Compaction
iv. Checking sub-grade
Subgrade preparation and Improvement
7
Site clearance:
This operation includes: clearing and grubbing
Clearing-is the removal of materials above the existing
ground surface
Grubbing-is the removal of roots, stumps, and similar
objects to a normal depth below the ground surface.
Earthwork
After site clearance, the second step is the earth work
for the preparation of sub-grade. Before starting the
earthwork control pegs are fixed for guidance. The
control pegs include clearing stake, batter pegs,
formation pegs, reference pegs...
Subgrade preparation and Improvement
8
The earthwork for construction of a road
includes:
a. Earthwork in cutting or excavation
b. Earthwork in embankment
Earthwork in cutting or excavation
In cut areas, in addition to the removal of materials
above the ground, specification, generally require that
all stamps and roots should be removed to a depth not
less than 0.3 m below the proposed road. This
requirement usually holds in embankment areas where
the height of the fill is less than about 1.5 m.
Subgrade preparation and Improvement
9
Subgrade preparation and Improvement
10
Subgrade preparation and Improvement
11
Cut Section
Subgrade preparation and Improvement
12
Earthwork
a. Excavation
It is the process of cutting or loosening and
removing earth including rock from its original
position, transporting and dumping it as fill or spoil
bank.
The excavation is needed when the finished
formation level of a road is to be kept lower than
the natural ground level.
Subgrade preparation and Improvement
13
Excavation Equipment
The excavation equipment commonly used in highway
projects include:
Bull dozers
Scrapers
Power shovels
Draglines
Clamshells
Hoes
Subgrade preparation and Improvement
14
Specifications usually classify excavations based on the
type and easy of excavation:
Rock excavation:
Common excavation
Unsuitable excavation
Borrow excavation
Subgrade preparation and Improvement
15
Rock excavation: materials that can not be excavated
without blasting or the use of rippers and all boulders or
other detached stones, each having a volume of 1 cub.
meter or more.
Common excavation: excavation and disposal of all
materials of whatever encountered in the work not
otherwise classified.
Or material which can be efficiently removed or loaded
by equipments.
Subgrade preparation and Improvement
16
Unsuitable excavation: the removal and disposal of
deposit of not saturated or unsaturated mixture of soil
and organic matter unsuitable for embankment materials.
Borrow excavation: excavation of approved material
required for the construction of embankments and other
element of the road.
All excavated materials that are suitable are used in
constructing the elements of the roadway structure
including embankments, shoulder, Subgrade, slopes, and
backfill for structures. Unsuitable or surplus materials are
disposed.
Subgrade preparation and Improvement
17
b. Embankment
When the formation level of the road is above the
natural ground level, embankments are required to
be made.
In embankment sections, when the height is more
than 1.5 m, trees and stumps may be left in place
and cut off at ground level or at a height of 75 to
150 mm above the existing ground surface.
Some agencies require that all large trees 450 mm
or more in diameter be removed, regardless of the
height of the fill.
Subgrade preparation and Improvement
18
Methods of embankment construction on marshy area
Convectional construction is unsatisfactory and
special procedures are necessary to construct
embankments through marshy areas. These include:
Removal and replacement method: suitable where the
undesirable soil is of shallow depth say up to 2.4 to
3.7m and is under laid by a soil of satisfactorily
character or rock. Sometimes, partial excavation and
replacement is practiced for secondary roads when
encountered deep swampy deposits.
Subgrade preparation and Improvement
19
Subgrade preparation and Improvement
20
Displacement method: this is a method by which the
unsuitable muck is displaced by the weight of the fill and
possibly a surcharge or by this weight supplemented by
explosives water jetting. The blast serves to displace the
material by the force of the explosions and by liquefying
the remaining unsuitable material so that it is displaced
more readily by the weight. The process of jetting involves
the pumping of water into the underlying soil layer in
order to liquefy and ease the displacement of the layer by
the weight of the embankment. The surcharge is
uncompacted fill added over the compacted fill to
accelerate the displacement.
Subgrade preparation and Improvement
21
Vertical sand method: this is a method by which vertical
columns of sand from 450 to 600 mm in diameter, spaced
from 2 to 6m a part on centres beneath the embankment
section carried completely through the compressible soil to
accelerate consolidation.
A sand blanket 1to1.5 m thick is generally placed at the top
of the drain extending across the entire width of
embankment section. The embankment is then constructed
by normal methods on top of the sand blanket.
Subgrade preparation and Improvement
22
Fabric Reinforcement : this is the use of engineering
fabrics such as geotextiles or geotechnical fabrics placed on
weak foundation (to increase the bearing capacity) and
over laid with the embankment fill.
Subgrade preparation and Improvement
23
Subgrade preparation and Improvement
24
The following types of material shall be considered
unsuitable for embankment:
Peat and other organic materials from swamps, marshes and
bogs that contain compressible soils and excessive amount of
degradable organic matter such as decomposing wood and
other vegetation.
Materials with more than 5% by weight of organic materials
Materials with a swell of more than 3% (e.g. black cotton
soils)
Clay having liquid limit exceeding 90 and plasticity index
exceeding 45;
Expansive clay exhibiting marked swell & shrinkage properties
Subgrade preparation and Improvement
25
The design elements in highway embankments
are :
Height
Fill Material
Settlement
Stability of Foundation
Stability of Slopes
Subgrade preparation and Improvement
26
Compaction
Compaction of the fill is carried out to achieve the required
density.
Table 1.1: ERA recommendation for Subgrade compaction
Light compaction Heavy compaction
Type of work
MDD MDD
the upper 250 mm of soil
immediately
Minimum of 100% 93%
beneath the sub-base or
capping layer
lower layers of an 95-100% 90-93%
embankment
Subgrade preparation and Improvement
27
Typical Roadway Cross Sections
Subgrade preparation and Improvement
28
Subgrade preparation and Improvement
29
Subgrade preparation and Improvement
30
Checking of the Subgrade
Trueness of the Subgrade is checked after its
preparation. Surface levels of the sub-grade along
the road alignment is checked by using a levelling
instrument.
Sub-Base course construction
31
GRANULAR SUB-BASE
(GSB)
Sub-Base course construction
32
GRANULER SUB-BASE (GSB)
It is an intermediate layer provided between sub
grade and granular base course.
The function of this layer is to serve as a drainage
layer of the pavement system to avoid excessive wetting
and weakening of sub grade.
Sub-Base course construction
33
Functions of a sub-base layer are:
To provide additional help to the base and surface
courses in distributing the loads
To prevent intrusion of fine-grained road-bed soils
into the base
To minimize the damaging effects of frost action
To facilitate drainage of free water that might get
accumulated below the pavement
Sub-Base course construction
34
GRANULAR SUB-BASE MIX
The material to be used for the work shall be
Natural Weathered Crushed Cinder Recycle
gravel Rock stone Gravel pavement
material
Sub-Base course construction
35
Construction of sub-base layer
1. Design of JMF
2. Transportation of GSB mix from plant to construction site
3. Dumping of GSB mix with the help of tipper or truck
4. Laying of GSB mix with the help of mechanical paver (If machine laid)
5. Spreading of GSB mix to the desired line, level and grade
6. Checking moisture content prior to compaction with suitable apparatus
7. Rolling operation (if moisture content is found ok) otherwise re-
watering & recompaction should be done till desired degree of
compaction is achieved
8. Determination of degree of compaction
9. Checking of surface irregularity with the help of 3 m straight edge
Sub-Base course construction
36
BEFORE LAYING GSB LAYER
Sub-Base course construction
37
Finished Subgrade Top Should be Checked For the Following:
Camber or slope of the road bed
Undulation
Firmness of the compacted surface ( if found in
loose condition, re-watering and recompaction is
sought)
Sub-Base course construction
38
Sub-Base course construction
39
LAYING OF GSB LAYER WITH MECHANICAL PAVER
Sub-Base course construction
40
SPREADING OF GSB LAYER USING GRADER (MANUAL
CONSTRUCTION)
Sub-Base course construction
41
Sub-Base course construction
42
WATERING OF GSB MATERIAL
Sub-Base course construction
43
Sub-Base course construction
44
ROLLING OPERATION
Sub-Base course construction
45
Sub-Base course construction
46
Sub-Base course construction
47
Sub-Base course construction
48
ERA Recommendation for material requirements
Materials with requirements
Test Type Gravel sub-base Crushed stone sub-base
As the requirements
Grading limits As the requirements
Grading
> 1.5 (with exception > 1.2) > 1.5 (with exception > 1.2)
modulus
PI Max.6 or 12 Max.6
CBR ≥30% ≥30%
Compaction >95% OF Modified AASHTO Min.95%
LAA <51 <45
FI <35 -
Sub-Base course construction
49
Test Frequency for checking
Frequency (one Minimum number of
Test test every) tests/lot
Material
Field density and OMC 200 m 4
Atterberg limits and
1km 4
Gradings
Construction tolerances
Surface levels 20 m 3 points/cross-section
Thickness 20 m 3 points /cross-section
Width 20 m
Cross section 20 m
Sub-Base course construction
50
Base course construction
51
Base Course
Base course construction
52
Functions of the base course are:
To act as the structural portion of the
pavement and thus distribute the loads
If constructed directly over the sub-grade,
to prevent intrusion of Subgrade soil into
the pavement
Base course construction
53
According to the method of
construction, the various
types of base courses of
flexible pavements are:
Crushed rock or stone
Naturally occurring
granular materials,
boulders, weathered rock
Dense bitumen macadam
(DBM)
Base course construction
54
CONSTRUCTION STEPS:
1. Specification of materials
to obtain the following parameters:
(a) physical requirements of aggregates
(b) grading requirements
2. Construction operations
Preparation of base
Preparation of mix
Spreading of mix
Compaction
Setting and drying
Base course construction
55
Base course construction
56
Base course construction
57
Base course construction
58
Base course construction
59
Base course construction
60
Construction of Asphalt Concrete
61
CONSTRUCTION OF
BITUMINOUS LAYERS
Construction of Asphalt Concrete
62
Construction of Asphalt Concrete
63
Typical layers of a flexible pavement
Seal Coat: Seal coat is a thin surface treatment used to
water proof the surface and to provide skid resistance
and to seal the surfacing against the ingress of water.
Tack Coat: Tack coat is a very light application of asphalt,
usually asphalt emulsion diluted with water. It provides
proper bonding between two layer of binder course. It is
generally applied on impervious surface.
Prime Coat: Prime coat is an application of low viscous liquid
bituminous material over an existing porous or absorbent
pavement surface like WBM.
Construction of Asphalt Concrete
64
Construction of Asphalt Concrete
65
Transportation of HMA material
Construction of Asphalt Concrete
66
PAVING IN FULL WIDTH
Construction of Asphalt Concrete
67
Construction of Asphalt Concrete
68
IF NOT PROPERLY CONSTRUCTED
THEN WHAT HAPPEN?
Construction of Asphalt Concrete
69
Rutting + Bleeding
Construction of Asphalt Concrete
70
71