Professional Documents
Culture Documents
1.0 Introduction
1.1 General
The main objective is to provide students with the basic principles and techniques of Labour
based road construction, using the common Road construction equipment. E.g. Hoe , shovel ,
spade, pickaxe, Crowbar, Bush knife, Axe, Bow saw, Grass Slasher, Heavy duty Rake,
Wheelbarrow, Sledge Hammer, Watering Can, Measuring tape ,Line Level, Nylon String.
Most of the works are carried out using local labour and only those activities that labour cannot
manage is done using intermediate equipment, like tractors with trailers, tippers, pedestrian
rollers, etc. The end result of the work is expected to be of high quality as stipulated in the
contract specification.
To achieve this and to be able to carry out the work within the given time frame, good site
management and a structured work approach is required from contractors.
The most demanding task is to manage a large, mainly unskilled labour force. See Fig.1 &2
below.
Fig.1 shows the construction of the road using labour based methods.
.
Fig.2 shows the construction of the road using labour based methods
Background to problems with the road network in Uganda Like many Sub-Saharan African
countries, Uganda finds it increasingly difficult to sustain heavy equipment-based construction
and maintenance of its roads.
This is largely due to
The slow pace of the economy.
The low foreign currency earnings.
The prohibitive (excessively high) rise in the price of equipment (in most of African
countries the foreign component of equipment-based road construction is between 60 -
70% of the total cost).
Because of this, the country cannot expand or maintain its road network to support the
economic activities in the rural areas where the bulk of the population live. Slower economic
performance coupled with rapid population growth has also meant falling real wages for
unskilled labour and acute unemployment.
1.1.2 How can a country deal with such problems?
Countries with these problems need to be innovative, using technically and economically
feasible techniques of road construction and maintenance. These include reorientation (changing
the focus) of public sector expenditure toward the use of more labour-based techniques, which
make use of the abundant labour force and appropriate technologies.
Policy makers and planners need to look at cheaper and local-resource-based alternative
approaches to road construction and maintenance. The labour-based approach is a positive
alternative.
Activities such as
excavation,
loading and offloading,
forming of road,
Masonry and concrete work, can be effectively executed using labour equipped with the
correct hand tools.
Equipment is only required for activities such as hauling (more than 200 m) and compaction, on
which the use of labour is uneconomical and inefficient.
1.1.4 How does the labour based-based approach work in practice?
The labour-based technique has been employed in many countries and experience shows that,
provided it is well organized and managed, it is generally cheaper and produces a well-
engineered road with a speed and quality comparable to that of the conventional machine-based
method
1.1.5 Benefits in using labour-based methods there are many benefits which include:
Eradication of poverty from local communities.
a significantly lower foreign exchange requirement,
the development of local management skills (for construction and maintenance works)
the utilization of abundant local labour resources,
the productive employment generation in rural areas,
a significant portion (more than 50%) of the direct costs being injected directly into the
local community,
the development of the local light industry (supplies of local equipments, tools and
materials, and repair services),
The reduced environmental damage/harm during construction, and ensured sustainability
and self-reliance.
1.1.6 Disadvantages attached to the use of labour-based technique;
The labour-based technique cannot be used for all types of roads; it is management intensive
(requires a great deal of supervision), and it is susceptible (likely to be influenced) to labour
problems.
1.1.7 Application of the labour-based approach;
Like any other engineering works, labour-based technique may work in certain conditions and
may not be economically and/or technically feasible in others. The road engineers must identify
variations in local conditions, determine the type of work required, and choose an appropriate
technology.
1.1.8 The following are some of the indicators in determining suitability of labour-based
methods:
• Population density - it is generally desirable to have a minimum of 25 persons per square
kilometer within reasonable travelling distance of the construction or maintenance site.
• Terrain condition - excessive earth works, rocky outcrops and steep vertical gradients (higher
than 12%) can make labour-based methods comparatively uneconomical.
• Traffic - highly trafficked roads (more than 100 vehicles per day) would generally require a
higher standard of geometric alignment resulting in a lot of cut and fill.
• Availability and proximity (nearness) of suitable road construction materials, eg gravel, water,
etc.
• Availability of local skills, i.e. technical and managerial - these are essential in achieving
efficient labour-based work organization and must be available from the outset.
• Adopted standards - appropriate level of access and corresponding geometric design standards
have to be agreed upon before deciding the technology to be used.
1.1.9 Misconceptions about labour-based techniques
The following are some of the misconceptions commonly expressed by some engineers:
1) .Labour-based work is sub-standard
Labour-based methods do not result in sub-standard work. Experience in several countries
(including Uganda) shows that there is little or no difference between the quality of roads, in a
similar category, produced by labour-based methods and those built using machine-based
techniques.
2) Speed of construction
Labour-based methods can achieve speed or productivity comparable to that of machine-based
methods. Speed of production in labour-based works is a function of the strength of organization,
management capability and availability of resources. Provided these conditions are met, labour-
based work moves very fast.
Note. labour-based works are less prone to interruptions due to break downs to key equipment,
lack of spares etc.
3) Problems with labour management
It has been suggested by some engineers that one grader is only one problem but one hundred
labourers are potentially one hundred problems. Interestingly experiences in many countries
(Uganda being one of them) have proved that workers cause the least of the problems, provided
they are fairly treated and paid on time. Without exception it is the few items of equipment
needed for the labour units that are the main restraint to progress.
Spare parts Bulldozer Hoe handles, spade Spare parts for Labour based
blade, handles etc tools like Hoe, spade, rake
grader handles are available and cost
clarifier & effective as opposed to those
blade etc of mechanized.
1.2.1 Introduction
A highway (a main road) pavement is a structure consisting of superimposed layers of selected
and processed material whose function is to distribute the applied wheel loads to the sub grade.
This is to ensure that the stresses transmitted to the sub grade do not exceed its support capacity.
The condition and adequacy of the highway is often judged by the smoothness or roughness of
the pavement. Deficient (not having enough of a specified quality) pavement conditions can
result in increased user costs and travel delays, braking and fuel consumption, vehicle
maintenance repairs and probability of increased crashes. The pavement life is substantially
affected by the number of heavy load repetitions applied, such as motorbikes, axle trucks, buses,
tractor-trailers and other equipment
1.2.2 Types of pavements
Different types of pavement are commonly used in the construction of roadways. There are two
major pavement types which include:
a) Flexible Pavement and;
b) Rigid Pavement.
Flexible pavement are flexible in their nature and are typically composed of several layers of
material with better quality materials on top, where the intensity of stress from traffic loads is
high and lower quality materials at the bottom, where the stress intensity is low. Each of these
layers contributes to structural support and drainage.
1.2.2.1 Flexible pavement
A flexible pavement is made up of layers namely: surfacing courses, road base, sub base, and
sub grade.
Gravel surface
Distribution of stresses to the sub grade; as a result the sub base material must be
stronger than the sub grade material;
Acts as a drainage layer in case of poor sub grade. A good drainage layer should be able
to drain very fast if water is logged, but also must be able to retain some moisture in
times of extreme drought;
Serving as a separating layer preventing contamination of the road base by the sub grade
material;
Under wet conditions; it has an important role to play in protecting the sub grade from
damage by construction traffic;
Preventing capillary attraction effect.
NB: The sub-base is omitted when the sub grade is a hard intact rock or if it is granular and has
a CBR greater than 30% and has no high water table
. Road base
The road base is the main load-spreading layer of the pavement. It is structurally the most
important layer of a flexible pavement.
Its main use is:
To distribute the applied wheel load to the sub grade in such a way that the bearing
capacity of the sub grade soil is not exceeded.
This layer requires higher quality material often obtained by stabilizing sub-base materials. It
will normally consist of crushed stone or gravel, or of gravely soils, decomposed rock, sands and
sand-clays stabilised with cement, lime or bitumen.
Surfacing
This is the topmost layer of the pavement. It usually consists of a bituminous surface dressing or
a layer of premixed bituminous material. It is comparatively thin, but resists abrasion and the
impacts caused by wheel loads and the effects of weather condition.
The functions of this layer are:
provision of a safe and comfortable riding surface to traffic,
taking up wear and tear stresses caused by traffic,
provide a water tight surface against infiltration of water,
Provide a hard surface which can with stand tyre pressure.
Where premixed materials are laid in two layers, these are known as the wearing course and
the base course (or binder course) as shown in Figure 3a above.
Fig 5: Geometric and Load Transmission Characteristics of Flexible and Rigid Pavements:
(a) Typical cross section of Flexible Road Pavement;
(b) Load Transmission in Flexible Pavement;
(c) Typical Cross section of Rigid Road Pavement;
(d) Load Transmission in Rigid Pavement.
a) Camber: The road surface which is normally shaped to fall away from the centre line
The camber is necessary:
to shed rain water
To reduce the risk of passing vehicles colliding.
The slope of the camber is called the cross fall. On sharp bends the road surface should fall
directly from the outside of the bend to the inside which is called „super elevation‟
b) Roadway: Full width of the road, including shoulders and carriageway for use by traffic.
c) Carriageway: Paved or unpaved width of the road, excluding the shoulders, normally
used by traffic.
d) Formation Width: is the Full width of the road, including side drains, sidecuts and
embankments
e) Cleared width: is the maximum width of the road to be cleared, it includes the trafficable
lane width. e.g if the trafficable lane width of 3 to 4m is required, then the maximum
desirable cleared width is 5m from the road centre line.
f) Road Centre Line: is a longitudinal axis along the middle of the road.
g) Side Drains: carry water parallel to the road to a mitre drain, where water crossing can
be disposed of. They also help to lower the water table. Side drains should be large
enough to carry all the carriageway water or the run off. Increasing the width of side
drains allows water to flow more slowly with less risk of erosion. Side drains should not
be deep and steep-sided because this can be dangerous to vehicles leaving the
carriageway, whether deliberately or accidentally.
h) Mitre drains: carry water from a side drain and dispose of it at a site away from the road
where it will not flow back to the road
i) Shoulder: is the paved or unpaved part of the highway next to the outer edge of
pavement. The shoulder provides side support for the pavement and allows vehicles to
stop or pass in an emergency
j) Culvert: is a structure constructed under the road and is designed to allow water from
the drains and/or natural water course to safely cross under the roadway.
Head wall
Fig.7 shows Culvert structure and headwalls crossing the road.
k) Headwall (Wing wall): is the Retaining wall at a culvert (or a bridge abutment) to retain
and protect the embankment fill behind the culvert fill (or abutment).
l) Scour Checks: is a small structure placed across the drain on steep gradients and is
designed to slow down the flow of water to prevent erosion of drain invert and slopes.
m) Road Reserve: is the Strip of land legally awarded to the Road Authority in which the
road is or will be situated and where no other work or construction may take place
without permission from the Road Authority. The width of the road reserved is measured
at right angles to the centerline of the road and varies according to the classification of
the road.
n) Paved Road: is a road with a bituminous surfacing.
o) Unpaved Road: is a road with a soil or gravel surface.
1.4 Parts of Roads that are difficult to construct with Labour and those that are difficult to
construct with equipment.
Potential
Activity
Equipment Labour
good good
Ditch cleaning and reshaping
poor good
Minor bridge and culvert repairs
poor good
Building scour checks
poor good
Repair of structures
good poor
Grading un-paved surfaces
poor good
Patching, sanding or local sealing of
Bituminous surfaces
poor good
Filling of unpaved surfaces and slopes
poor good
Grass cutting
poor good
Repairing and replacing traffic signs
good good
Road line markings
good poor
Re gravelling
good poor
Surface Dressing
2.1 Introduction
Setting out: Is the establishment of the marks and lines to define the position and level of the
road for the construction work so that works may proceed with reference to them
Setting out involves two stages.
The use of horizontal and vertical control methods and positioning techniques. The
purpose of this stage is to locate the boundaries of the works in their correct position on
the ground surface and to define the major elements.
Second stage of setting out continues on, from the first stage, beginning at the ground
Sub grade level, road sub-base level etc. Up to this point, all the control will be outside
the main construction, for example, the pegs defining cleared width, Centre lines of
the road will have been knocked out during the earthmoving work and only the original
control will be undisturbed.
Settings out requirements for labour-based road construction vary with the type of work to be
executed. The construction of new roads requires a complete survey by the Engineer to establish
the alignment.
The preliminary route selection for alignment of new road construction involves staking of the
intended road centerline with pegs at 50 metres intervals. The pegs are securely driven down into
the ground in such a way that the tips are left exposed for painting and numbering for ease of
identification.
In performing the preliminary road alignment assessment, where a new alignment is required, the
Engineer shall choose a route in such a way that:
Objects and poor ground conditions such as swamps, boulders, unstable soils, trees,
should be avoided.
There is minimum need for heavy earthworks. The road centerline should be carefully
located to favour cutting of material rather than filling. This strategy will help to reduce
the risk of the fill material sliding down the slope and the need of costly equipment
compaction.
Properties that will attract high compensation are avoided.
Features that will increase maintenance costs and vehicle operating costs (e.g. steep
gradients, sharp curves) are avoided.
The improvement of road drainage should not be expensive.
The technical standards requirements should be easily achieved i.e. the geometry of the
road.
To demarcate the road centre line, the edges of the carriageway, shoulders, side drains
and to show the future levels of base course and gravel surfacing.
Ranging rods
Ranging rods are long poles (usually 2 metres in length and made of metal, wood or hard plastic)
with a pointed metal end for ease of driving into the ground.
For clear visibility they are painted with alternating red and white colours at various intervals
depending on the manufacturer. A standard interval of 0.2m for the alternating red and white
colours is recommended.
A very useful tool to be used with ranging rods is a sliding hammer (or hole hammer) with a
weighted head that fits over the ranging rod, used to drive the ranging rods into the ground.
Ranging rods are used:
For setting out straight lines.
To support profile boards on both straight and curved sections of the road.
They are also used with line level for setting levels.
The line operator moves the string up or down until the bubble is centred in the middle between
the spirit level marks. The string line will then indicate the horizontal line.
The line level can be used to:
transfer the exact level of one profile board to another profile, thereby ensuring that both
are at the same level,
measure up or down from a known horizontal level, and set a new level,
Find the slope between two fixed profile boards, and determine which one is higher.
NB. When using a line level ensure that:
The string used should be a thin nylon fishing line, enabling the line level to easily slide
along the string.
The line level must be placed half-way between the two ranging rods. Use a measuring
tape to find the exact middle point.
Keep the string tight - do not let it sag.
The line level is a delicate instrument, look after it - do not throw it around and treat it
roughly.
Check the accuracy of the line level regularly in the field.
Spirit level
Spirit levels are used for checking levels between short distances. Different lengths of spirit level
exist and each length is suitable for a specific nature of work.
E.g. The 1.2 metres long spirit level is suitable for use with camber boards. Shorter ones are
commonly used in masonry or building work.
Boning rods
Boning rods are made of two seasoned wooden lathes, nailed to each other at right angles in the
shape of the letter “T” with a uniform height of 1 metre.
Boning rods are used for checking levels between two established points.
Profile boards are used for setting out levels of cross sections and vertical alignment of a road.
They are 3mm thick steel plates (40cm x 10cm) welded to a short piece of 40mm diameter metal
pipe equipped with a thumb screw mechanism. They can be fixed or slid up and down the
ranging rod by tightening and loosening the screw. The board is painted on both faces with white
paint for easy visibility.
Before starting setting out works, make sure that you have a sufficient supply of ranging rods
and profile boards. A number of 20 rods and 20 profile boards is considered as a minimum to
carry out the work.
Procedure:
From point A, ranging rods set at points B and C must be visible.
From point D, ranging rods set at points C and B must be visible.
Proceed as follows:
From A, set B and C in a straight line
Sight from D and move C to be in line D-B
Sight from A and move B to be in line A-C
Repeat this procedure until A-B-C and D-C-B show a straight line without further movements.
2.3.2 Setting out straight lines using a string
This method is preferred for intermediate points between two ends on a straight not exceeding
25m.
The procedure for this method is outlined below:
Fix pegs on the two end points which have been identified on the straight line.
Stretch a string and tie it firmly to the two pegs in such a way that the string is not
touching the ground.
The string must be thoroughly stretched to remove any slack that might distort the
straight line.
The string must also be completely free throughout its stretched length.
All the desired points along the straight line should be marked by fixing pegs along the
string line.
METHOD APPLICATION
String Method Only suitable for small curve radii of less or equal than 30m
The area must be flat and free of obstructions
Most suitable for junction curves
Tangent Method Suitable for any curve with deflection angle between 20°
and 90°
The point of intersection of the two straights (PI) and the
area between it and the road must be flat and free of
obstructions.
Tangent Offset Method For curves with deflection angle of less than 20°
The point of intersection of the two straights (PI) and the
area between it and the road must be flat and free of
obstructions.
Table 1a
2.3.2.1 String Method
Procedure:
Determine the edges of the carriageway and the centre line on both straight lines and mark them
with pegs and strings.
Set out lines 1 and 2 parallel road to the inner edge of the road with the selected radius “r” = 30m
from it. Mark the two lines with pegs and strings
The point of intersection is the place where line 1 and line 2 cross each other. Then mark this
point with a strong coloured peg.
Use a string of the radius(r =30m) to set out the curve.
Fig. 15. Shows how a circular curve with a 30 m radius can be set out.
2.3.2.2 Quarter Method
Procedure:
1) Establish the ends of the straightsTP1and TP2 ,They should be approximately equal
distances from the IP
2) Establish point C exactly halfway between points TP1 and TP2
3) Establish point MP opposite C on the desired centre line of the road such that the line C-
MP is perpendicular to line TP1- TP2
4) Establish points E and F exactly halfway between TP1-MP and MP- TP2 respectively.
5). Measure out the distance C-MP (b).
6). Set out points QP1 and QP2 at distances ¼b from points E and F respectively.
The line E-QP1 must be perpendicular to TP1-MP and F-QP2 must be perpendicular to MP- TP2
7). Check radius of curve if it is desirable. If the curve radius is insufficient, move points TP1
and TP2 apart and restart from step1.
8). Place intermediate pegs if necessary to form smooth curve with string line.
Establish centre line pegs at 5m or 10m intervals and chainage reference pegs.
IP
Fig. 16. Shows setting out curve using the quarter method
NB: For desirable minimum radius condition.
R= 5000/X; Where: R = radius of the curve. Curve radius (m) Offset distance(m)
X = Offset Distance. 50 100
100 50
Assignment one
1. Explain with clear illustrations the procedures for setting out curves using the following
methods;
a) Tangent Method
b) Off Set Method
c) Deflection angle method
d) Tangent offset method
Step 2:
Step 3:
If the level of the centre line is too deep into the terrain, i.e. involving too much excavation
works, you can move the profile boards up or down to reduce the levelling works, achieving a
balance between the volumes of excavation and fill.
Finally, make sure that the profile boards along the centre line have been correctly placed. All
other levels for the road structure will be set out based on the profiles along the centre line.
2.3.5 Setting out levels and gradients
2.3.5.1 Setting out Levels
The Profile Board Method
Setting out Levels procedure is based on the use of a series of profile boards and a string, line
level giving control of levels during construction.
The basic principle when using profile boards is that when they are set out we are placing a
series of level boards that show the level 1 metre above the completed construction levels.
Imagine that a ditch is to be excavated from A to B at the level shown in by the dotted line
To ensure that the correct level is obtained in the ditch, profile boards are placed at positions A
and B, 1 metre above the level of the planned ditch:
A travelling profile is used to obtain levels between two profile boards. A boning rod or a
profile can be used as a traveller. Along the line from A to B, slots are excavated to the level of
the ditch.
By placing the traveller in a slot and sight from the profile board in position A to the profile
board in position B,
We can see if the traveller lines up with the two fixed profile boards. If the traveller is too low,
the slot has been dug too deep. If the traveller sticks up above the sight line, the slot needs to be
dug deeper.
To provide good guidance, slots are dug at regular intervals, say at every 4 to 5 metres along the
sight line.
When sufficient slots have been dug, the workers can start excavating the ditch by joining up the
slots. The traveller can then be used to check that the finished work is to the correct level and
that there are no high or low spots.
Tie the string line at the 1 metre mark of the ranging rod at the higher point of the slope.
Fix the string line at the lower ranging rod, hook the line level at the middle point
between the two ranging rods and move the string line at the lower point ranging rod up
or down until the level bubble is exactly in the middle. Mark this level at the lower
ranging rod, turn the line level around and mark the level again. Measure the middle of
the difference of the two marks = this is the exact horizontal level transferred from the
higher to the lower ranging rod.
Now measure the difference between your horizontal level mark and the one metre mark
at the ranging rod (= D).
Measure the exact distance (length) between the two ranging rods (= L).
Calculate the percentage of the slope.
The distance between the two ranging rods represents 100%. The calculation is therefore as
follows:
D divided by L multiplied by 100% = the percentage of the slope.
Adopt either Metres or Centimeters for all measurements.
Now add D to 1m and measure the distance (D+1m) from the level mark downwards.
You will see that in order to be able to measure this new height, you need to dig a small
slot next to the ranging rod. Dig the slot in small steps until you can measure the exact
height (D + 1 m). The bottom of this slot is now at the required level.
In order to transfer the gradient uniformly you have to use boning rods or profile boards
applying the method described below = set a boning rod at each end point, every few
metres dig a small slot, set the boning rod at the bottom of the slot and deepen the slot
until all three boning rods are in line with one another.
1A (Standard) 15 13
CLASS 1
1B (Black soil) 20 18
1C (Embankment) 11 + (2 x embankment 9 + (2 x embankment
height) height)
1D (Super elevation) 17 15
2A (Standard) 13 11
CLASSII
2B (Black soil) 16 14
2C (Embankment) 10+(2 x embankment 8 + (2 x embankment
height) height)
2D (Super elevation) 14 12
3A (Standard) 11 9
CLASSIII
3B (Black soil) 12 10
3C (Embankment) 10 + ( 2 x embankment 8 + (2 x embankment
height) height)
3D (Super elevation) 12 10
The bush clearing widths for the various cross sections are shown in table 3.0
The bush is cut as close to the ground level as possible and the cuttings are deposited outside the
cleared width.
In certain cases, workers may execute this task in small teams with one or two workers cutting,
and an extra worker disposing off the debris.
This is normally the case when the bushes are very thick and the disposal area is a distance away.
The debris must be thrown outside the cleared width on the lower side of the road.
In some situations the debris may also be piled and burnt in a controlled manner.
At any point along the road centre line, the cleared width shall comply with the values
shown in table 3.0.
The debris from this activity should be dumped and spread at locations where it will not
be washed back into the road reserve during the rains. (i.e on the lower side outside the
road)
Environment, health and safety
Ensure that:
The debris is evenly spread at the dumping site to avoid trapping and channeling rain
water there by causing stagnant pools and erosion.
Where the ground is too dry and prone to raising a lot of dust, water shall be sprinkled to
minimize dust being inhaled by the workers. Also, breathing masks should be supplied to
the workers.
Workers must be well spaced out to ensure safety.
A First Aid kit should be readily available on site in case of an emergency.
2.4.4 Tree and stump removal
Defn: In road construction, a tree is a plant having a girth greater than 0.3m. The girth of a tree
is measured as the circumference of the tree at a height of 1 m above the ground level.
The work done includes felling the tree, uprooting its stump, cutting it up and disposing of the
debris at an appropriate location. All trees are to be removed completely (including the entire
root system) from within the bush cleared width.
Trees are removed to:
facilitate the drying effect of wind and sun on the wet road
provide good visibility to the traffic on the road
avoid traffic hazards
avoid structural damage of the road by expansion of roots
Have a strong sub grade free from rotting roots.
Tools required.
Axe ,Bow saw , Hand saw , Pick axe, Shovel ,Wedges , Crow bars ,Rope
Labour:
Sufficient labour must be available to ensure that the trees can be felled depending on workload.
Equipment:
Chain saws may be used where it is necessary to increase the rate of cutting, in order for the
activity to keep up with other activities.
In situations where the extraction of stumps is difficult, a tractor may be used to help pull out the
stump and roots.
Work method:
For small to medium size trees (girth of 0.3m to 1m), one of the easiest ways of felling these
trees is by attaching a rope at least halfway up the tree and after excavating the ground from
around the stump, have the gang (or tractor) pull on the rope. This will cause the tree to be
uprooted with the advantage that the stump and most roots will come out of the ground
simultaneously.
This method is more efficient than cutting the tree first and digging the roots later. The
remaining roots should be dug out of the ground.
In the case where boulders are buried, check to ensure that they are buried well below
0.2m of the intended sub grade level.
Environment, health and safety:
When splitting rocks using hand tools, labourers must wear boots, eye protection goggles
and gloves to protect against bruises on the skin.
For blasting, only specially trained and licensed people can be allowed to take charge of
the activity. These trained people will be able to implement all the necessary safety
procedures.
If pneumatic drills are to be used, then the labourers working with this equipment must be
supplied with ear and eye protection gear including boots.
Stones and boulders from this activity should not be disposed of in such a way that it
blocks any natural waterways or diverts them.
When boulders are to be buried, care must be taken so that the boulder does not roll into
the pit while workers are still digging or working inside the pit.
3.0 EARTHWORKS
Earthworks involve the loosening, removal, disposal and handling of earthen materials in the
construction process-excavation of cutting and construction of embankment.
OR
Earthworks involves digging drains and using the material to build up the camber, excavating cut
to fill to form the road and building up the road on embankments in flat areas with poor drainage.
The earthworks activities include:
Measuring and calculation of volumes
Excavation including cutting and borrowing to fill and/or cutting to spoil
Loading, hauling and unloading (if required)
Spreading and compaction
Consider the situation where the road is built on land that is level, or nearly level, between
drains with very little cross slope.
The earthworks excavated from the side drains, this material is used to form the camber. (See
fig. below)
(Camber
(Side drain
Before carrying out any excavation of earth fill works, volumes must be determined in order to
estimate the material needed for the works.
In order to get accurate measurements, the formation, and road bed or drain levels during
construction must be set relative to existing ground by use of slot (slotting) technique. (See
fig2a)
The excavation to level technique, slots are used as a visual guide to the workers on the shape of
the road bed that they are to construct.
Slots are also used to expose the ground conditions where the construction activities are to take
place. Slots must be compacted by ramming at optimum moisture content.
The top of the slot should be 0.5m and the length depends on the road cross section.
The cross section areas of the existing ground in between slots can be accurately measured and
calculated using the following formula. And by multiplying the average area with the length of
work in successive slots give volume of earthworks.
Excavation to level is carried out to provide a level terrace (horizontal ground), in accordance
with the designed vertical alignment, on which the drainage and camber can be constructed in an
accurate and controlled manner.
The level of the terrace should be the same as the subsequent level of the shoulder break point of
the road.
The width of the level terrace is the distance from one outer end of the ditch invert to the outer
end of the ditch invert on the other side of the centerline. (See fig3a)
Work Method:
The slots are used, as a guideline for the excavation and filling of each 10-metre section
of road to achieve a transversely level terrace.
Define quantity of work for the day and allocate labourers accordingly. (Calculate
volume of earthworks between two consecutive slots for individual tasks).
Spread the fill material in thin layers (about 0.15m) and compact to a density as specified.
The operation continues until a smooth terrace is achieved to the same levels as the slots.
Check the level of the terrace with boning rods or a profile board and correct where
necessary.
Compact terrace to density specified, Using vibrating roller.
NB: Ensure optimum moisture content of the soil when compacting!
Tools
Pick axes, Mattocks , Hand rammers, Hoes , Shovels, Rakes or Spreaders ,Wheelbarrows,
Straight edge 2mlonger,Spirit level ,Boning Rod Set,
Equipment:
Vibrating roller, Water bowser
Material:
• Strings, Pegs
In this case, some material is cut to fill within the formation width, extra (borrow) material (from
outside the formation width) is required to bring the roadbed to the required level.
The productivity for this activity depends on the haul distance of the borrow material, the type of
equipment used like wheelbarrows, tippers etc and the type of material hauled.
This activity involves:
Excavation of borrow material from the quarry
Load and haul borrow material
Offload and spread borrow material
In this case the cut (excavated) material is thrown out of the roadway. This is applied when the
side long slope is too steep that it cannot safely support the fill material and cannot safely allow
workers to work on it.
Work method
Slotting is carried out first and the slot interval along the road must be 10m. The slot is
constructed as described in the earlier part of this section by cutting material from the high spots.
Once the slots are ready, excavation to level will follow to join up the slots.
Guidance to the workers are provided by strings and pegs that will clearly demarcate the limits
of excavation and extents of fill as shown in Fig6a
To ensure proper compaction of the fill, the roller must be working in the same area as the
people are working.
The fill layers must be compacted by roller and the loose fill layers must not exceed 150mm
loose.
The fill layers must be watered where necessary, such that the moisture content at compaction is
between 80% and 105%.
A minimum of six passes of compaction shall be applied or until no roller imprint on the surface
can be recognized.
Quality control
Visual observations must be supported by measurements from level reference marks to
ensure that excavation and filling are completed to design levels at each station.
With the use of boning rods, the level terrace must be checked so that it is to the correct
grade between the stations.
The width of the level terrace must be checked by tape every 100m. The longitudinal
levels must be checked every 20m using boning rods or profile boards.
The compaction should be checked by counting the number of passes made by roller and
checking that no visible roller imprints are present on the finished product.
This method is employed where it is necessary to raise the road level usually across low-lying
land with poor drainage, adjacent to bridges and culverts and on low sections of the road as
dictated by the vertical alignment. (See fig. 7a)
Tools
Picks, Shovels, Wheelbarrows, Heavy duty rakes, Watering cans, String and line level, Straight
edge 3m, Tape measure 30m, ranging rods with profile boards.
Equipment
Pedestrian roller
Tractor and tipper
Water Bowser
Work method
The quarry and haulage operations are organized in a similar manner to those for
gravelling.
After completion of the clearing activities, the vertical alignment is fixed using ranging
rods with adjustable profiles. However, instead of fixing the centreline profiles at 1m
above the required level, they should be fixed at final level of the centreline.
It is necessary to set out the toe of the embankment and, as the fill rises, the toe of the
shoulder. Pegs should be established for these points using the details in Fig7a
When the toe position T is determined, a peg should be installed. A batter profile of 1: 1
should also be erected to guide the earthworks fill. Profile boards should also be erected
to show the position and finished levels of the centreline.
Example: An embankment of 1.35m average height would have a cross-section area of:
(5.5 + 2 x 1.35) x 1.35 = 11.07m2or 11.07 m3 per metre length.
Quality Control
The dimensions (width and height) of the embankment must be checked for accuracy
every 20m. The levels should be strictly controlled by continuous boning for each fill
layer in order to ensure the correct height.
The smoothness of the longitudinal profile must be checked every 20m. This can be done
by using a 3m straight edge.
The compaction can be checked by counting the number of passes made by roller and
checking that no visible roller imprints are present on the finished product.
A proper test should be done to comply with the standard specifications.
Where any side-borrow has been made outside the formation width, it must be
rehabilitated to discourage ponding of water and/or possible erosion.
At any excavation face the use of heavy tools combined with the threat of falling material
constitutes a risk situation and labourers must be well-spaced to avoid injury.
In extremely dry areas, dust reduction measures (e.g. dampening the soil with water)
must be considered if unhealthy levels of dust are suspected.
A first aid kit must be readily available on site for any emergency.
Note: The quarry and haulage Compaction operations are organized in a similar manner to those
for gravelling.
4.0 GRAVELLING
Gravelling is the placing of gravel layer (selected granular, mainly laterite) material directly on
the sub grade to provide a strong surface layer which is passable in both dry and wet weather,
and which does not deform under the expected traffic loads.
A good gravel surface and the road camber, prevents water from entering into the road body and
thereby avoiding surface water from deteriorating the bearing strength of the road.
The gravel layer is placed immediately after the completion of earthworks. In some cases, newly
constructed roads are left un-gravelled for a period of time, allowing the base to settle and traffic
to provide compaction.
The following methods are used to gravel a road:
Use of a mix of labour and equipment,
Use labour for all activities except hauling over distances longer than 150 metres
.The preparation operations are carried out in advance of the gravelling and consist of:
reshaping the road
preparing quarry access roads
preparing quarries
Initial excavation of gravel.
The sequence of the actual gravelling works is as follows:
Main excavation of gravel in the quarry.
loading
hauling
offloading and spreading
compaction
Excavation depends on the hardness of the rock, and it carried out with, blasting or hand tools
such as pickaxes and crowbars.
The crushing can be done either with rock crusher or by hand.
Spreading is done by a grader or with hand tools. With very short hauling distances (less than
150m), it is even possible to carry out all activities with labour. The hauling can then be
economically done with wheelbarrows.
In some cases, newly constructed roads are left un-graveled for a period of time. This allows the
base to settle and traffic to provide compaction. In other cases, the gravelling layer is placed
immediately after the completion of earthworks.
After a certain period of time, i.e. six to ten years, depending on the traffic volumes, it is
necessary to re-gravel the road.
Standards
The thickness of gravel layers depends on the strength of the sub grade material, quality of
available materials and the expected traffic loads.
For rural, low traffic volume roads, a carriage width is 5m wide which is fully graveled with a
layer of 15-20cm (before compaction) is recommended.
The road camber should be maintained at 8% (10% before compaction).
When selecting appropriate gravel quarries, a number of aspects need to be considered. These
include:
the quality of the gravel material,
The terrain / level where the quarry is located.
the depth of soil (or overburden) over the gravel,
the quantity of good quality gravel available,
how to excavate the gravel,
how long access road needs to be constructed to access the quarry,
hauling distance from the quarry to the road site, and
Land ownership at the quarry site.
Preferably the gravel pit should be located close to your road to limit hauling distances, because
gravelling can be quite expensive and can sometimes cost as much as the construction of the road
itself.
Preparation of quarry site involves the removal of all vegetation, stumps, boulders, fences,
structures, top soil and any other material considered unsuitable from gravel excavation site.
Where necessary, provide an improved access for haulage equipment.
Tools used
Hoes, Mattocks, Shovels, Bush knives, Pick-axes, Rakes, Wheelbarrows
Labour
The gang size depends on the size of quarry area, access length, nature and difficulty of the
preparation works and productivity targets.
Materials
Wooden pegs
Strings/ropes of sisal twine
Work method
The area to be cleared is set by using tape measures, pegs and strings so that the quarry can be
exploited as planned.
Cut all vegetation including grass, bush, trees and remove stumps, boulders, fences and
structures that is in the quarry area using bush knives, mattocks and pickaxes.
Haul and deposit all cut or removed materials to approved locations.
Excavate using hoes or mattocks the overburden, load onto wheelbarrows, haul and stock within
10m from the planned quarry area so that it can be reused to reinstate quarry or as directed by the
engineer. See fig. 9a.
Location
Where possible, gravel quarries should be located in the road reserve and adjacent to the road,
which helps to avoid the need for access roads and additional turning areas.
Where quarry sites are located away from the road, access will be needed for haulage equipment
to use.
Quarry Layout
The quarry site and its layout must be well planned before any work starts. The quarry site must
be planned so that:
The quarry can be fully exploited with extraction of optimum amount of gravel
The overburden is stockpiled in such a manner as to allow for future extension and ease
in reuse to reinstate the quarry site.
The best quality gravel is taken in case of variable quality in the site
Environment damage by erosion or poor drainage is minimized (see Figure10a )
Reshaping
The road to be graveled should be brought to its correct cross section or shape before gravelling.
The reshaping activity is necessary if the road has been used for vehicular traffic for more than 1
- 2 weeks.
The activity will include reestablishment of the camber cross fall, shoulders and slopes to enable
the water to drain off easily.
Hoe , mattock, Rake, Camber board, Broom, Ditch and slope templates, Pick axe, Shovel, Wheel
barrow, Hand rammer, Spirit levels for templates, Temporary road signs
Equipment
Grader (for mechanised methods)
Tractor and towed grader
Vibrating rollers
Water browser.
Table 1
This involves the loosening of the insitu gravel, removing from cut position the loose gravel and
stockpiling in heaps alongside for easy loading. It also includes removal of boulders encountered
during excavations.
Tools
Mattocks, Hoes, Pick-Shovels, Wheel barrows, Sledgehammers, Tape measurers
Work methods.
Set out points for gravel excavation such that it is done in bays Fig12a and gravel excavation is
suitable for gang tasks.
Excavate gravel and stockpile ready for loading. One day before it is required to be hauled to the
gravelling site
The gravel is stockpiled alongside bays to allow for easy loading and avoid multiple handling.
Quality Control
Visual inspections are carried out to ensure that oversize particles or unsuitable material are
removed from the excavated material.
Environmental, Health and Safety
Workmen must have enough room to work safely and comfortably.
There must be enough room for trucks to maneuver.
In the case of hillsides high cuts must be avoided.
This involves placing of excavated loose gravel from the stockpile onto the hauling equipment,
i.e. truck, tractor-trailer etc.
Tools used.
Shovel
Hoes
Labour
The loading gang should be divided into groups of 4 to 6 labourers. These groups load the empty
trailers in the order in which they arrive at the site.
NB. Sufficient gang size for loading the truck must be selected to reduce idle time.
Work method
Trucks should be parked at the same height below the stockpiles for ease of loading. The gravel
is then loaded using shovels, into the trailers and trucks.
Situations that result into the Truck being far high above the stockpile should be avoided as
loading may be difficult.
Quality Control
All trailers and trucks must be loaded to the correct load line.
Health and Safety
Workmen must have enough room to work safely and comfortably.
Hauling involves the movement of excavated material from the source to the point of use of the
material.
Or the average hauling distance is the distance from the quarry to the middle of the closest and
furthest road section that you need to gravel.
Transport of gravel can be organised in many ways, depending on the distance from the gravel
quarry to the site and the type of equipment available to the project.
The table2 below is a guide for selecting the type of transport appropriate for different haulage
distances
Tractor towing tipping trailers can be a very economical mode of transport when the hauling
distance does not exceed 8km.
The trailers are more suitable than lorries in cases where manual loading is to be used
DISTANCE TRANSPORT
10 – 150m Wheelbarrows
150 – 1000m Animal Carts
1000 – 5000m Tractors & Trailers
Over 5000m Truck
Table 2
When hauls exceed 1km, gravelling should continue in only one direction at a time. It is also
advisable to gravel the road section where the access road meets to reduce the wear and tear of
the road around the access junction.
The advantages of these are that:
The gravelling equipment compact the material as they haul over the laid gravel
Damage to existing road camber is minimised
Gravelling traffic does not interfere with reshaping activities
Gravelling can restart sooner after rainfall
This involves removal of gravel material from the equipment and spreading it to the required
thickness and width.
Tractor trailers have to be offloaded by labour. While Trucks remove their load by tipping and
do not require labour to offload.
Off-loading
Drivers should be instructed to dump the entire load within an area which you have clearly
marked with pegs and string lines.
To make spreading easier, instruct the drivers to move slowly forward while dumping, so that the
gravel is evenly distributed along the length of the rectangular area.
Spreading
Once the material is unloaded, you can start the spreading.
Spread immediately before compaction to make use of the natural moisture content of the
material.
The workers should use special spreading rakes, or hoes to spread the material evenly onto the
road base.
The Work should start from the centre line towards the shoulder, and spread one side of the
centre line at a time.
Oversize pieces of rock should be removed or crushed using sledge hammers
Work Method:
This is a combined activity, carried out by one gang of labourers. It is important that the trucks or
trailers are off-loaded in the shortest possible time.
Set out off-loading and spreading boxes using pegs and strings in accordance with the volume of
the haulage equipment.
Box width is equal to standard width of road, length of box = trailer or truck capacity divided by
road width multiplied by layer thickness (loose)
Pegs are set at the centre line and edge of box to ensure a satisfactory cross fall (8%) and
longitudinal gradient.
Calculate the total volume of gravel to be spread for the day. Allocate labourers accordingly.
Offload gravel and spread immediately using hoes and heavy-duty rakes or spreaders. Any
gravel lumps or stones larger than 63mm should be broken down using sledge hammers
The quality of the gravel needs to be determined in advance of the project commencing
gravelling works. This enables the project to prepare and negotiate gravel rates adequately in
advance and to time the gravelling works to the optimal period of the year (dry season).
Although the process is called "gravelling", various materials can be used such as laterite,
limestone and gravel. Most suitable materials consist of a mixture of stones, sand and clay.
The stone particles will lock together and form a strong skeleton which spreads the traffic load
to the natural soil. The sand and clay acts as a binder keeping the stone particles in place.
Good gravelling material should contain between 35 - 65% stones, 20 - 40% sand, and 10 - 25%
clay. However, in wet weather a high proportion of clay in the mixture would make the layer too
soft and slippery.
Information about soil characteristics is useful both to help in selecting sites, routes and to
facilitate design and specification of the project.
Engineers and technicians are often limited to make some of the field tests but When an
Engineer is used with laboratory tests taken on similar samples for other projects and with a
sound knowledge built up by observing how similar materials have performed, these field tests
can provide sufficient information for making sensible engineering decisions.
1) Take a sample, moisten it and mould it into a ball. You can feel the sand and stones
by the gritty feel of the sample when you squeeze it. When, after drying, the ball
retains its shape, you can assume that there is enough clayey binder in the material.
2) You can also make a flat thick piece from the moist sample and try to penetrate it
with a pencil. If the pencil penetrates easily, the material is not suitable because it
contains too much binder or clayey material. If it is difficult to penetrate, there is a
sufficient proportion of fine and course materials which interlocks well.
3) Settling test: used to find out the proportions of the various soil fractions in the
sample.
The sample is put in a glass jar like this Fig15a. .
Only half the jar should be filled with the sample.
Then add water till the jar is three-quarters full.
Add some salt, as this will improve the settling of the finer materials.
Shake the jar, and let the soil in the jar settle.
You will see, the gravel and the course sand fractions settling immediately.
The finer sand and the course silt fractions settle more slowly.
The clay and the fine silt will remain in suspension for some time before they settle.
You can see the proportion of each fraction as layers in the jar.
The results of these tests provide indications on how these soils could react when subjected to
compaction, traffic and weather conditions.
If you are still in doubt about the suitability of the gravel, consult your engineer to carry out
laboratory tests to confirm your observations.
4.10 Water
Good water sources are also important. When the gravel operation commences, the projects
needs water haulage equipment available on site, i.e. a water pump, water bowser and an
appropriate spreader. Make sure that this equipment is available and in good working condition
before gravelling works starts.
5.0 COMPACTION
Soil compaction is the process whereby soil particles are constrained to pack more closely
together through a reduction of the air voids, generally by mechanical means.
Soil and gravel in its natural state consists of solid particles, water and air.
Air does not contribute to the strength and stability of the soil, it reduces the stability of a soil.
If the soil contains too much moisture and is too wet, the soil particles are kept apart by the
water. When the soil is too moist and you try to compact it, it will simply not compress, but flow
out sideways. (See fig 16a)
The level of compaction to be achieved in the field during construction is normally specified as a
percentage of the maximum dry density obtained in a compaction test in the laboratory.
The layers of fill material shall be compacted throughout to a dry density of at least 95%MDD,
except for the upper 300mm, which shall be compacted to a dry density of at least 100% MDD
Another way of determining compaction is to specify the minimum number of passes to be
carried out with a certain type of roller and with a specified moisture content of the soil. This
method is called Method Specification
Amout of compaction.
The degree of compaction that is achieved in a certain volume of material is a function of
the compactive effort applied. The higher the compactive effort , the higher the density
that will be achieved and therefore more stable the soil will be.
The amount of compaction aplied to a soil vary in two ways.
i) By varying the type of compaction plant.(a 3 tonne roller will achieve a smaller
compactive effort than a 8tonne roller).
ii) By varying the number of passes.
NB. Each plant has an upper limit of compactive effort, beyond which additional passes
have no further effect. And this upper limit is reached after about 6 passes.
Thickness of layer.
The thicker the layer of loose material that is being compacted, the less the average
density will be and therefore the stability resulting from a certain compactive effort.
The loose layer to be compacted should range from 100mm to 400mm depending on the
roller to be used.
Smooth wheeled rollers: Suitable for light clayey and well graded soils.
Grid rollers: Suitable for light clayey and well graded soils
Tamping roller: suitable for clayey soils.
Towed vibrating rollers: Suitable for light clayey and well graded soils.
Self-propelled double vibrating rollers: Suitable for light clayey and well graded soils
Pedestrian tandem vibrating rollers: Suitable for light clayey and well graded soils
Pedestrian vibrating rollers: Suitable for clayey soils.
Vibro tampers: Suitable for light clayey and well graded soils
Dropping weight compactors: Suitable for all soils.
A hand rammer
This is called `indirect compaction' method or natural consolidation. It is only used on very low
fills, and is most effective if the fill material is very moist and must dry out.
Given sufficient time, it has been found that roads compacted by natural consolidation can
achieve similar densities as roads compacted by equipment.
The main disadvantage is that while the soil is not consolidated, it is prone to erode more easily.
It is good to leave the fill for a period of six months to achieve an effective degree of
compaction.
To check whether the required compaction has been achieved, then the field density tests have to
be taken during the construction period.
5.4.1 Methods used to determine field density:
5.4.1.1 Drive Cylinder:
This is the simplest method where a fixed volume of soil is removed by driving a thin-walled
cylinder down into the soil. The sample is taken to the laboratory where the dry weight is
determined.
The dry density is calculated by dividing the oven-dried mass of the soil specimen by its volume.
This method is not applicable to soils containing too much clay content.
5.4.1.2 Rubber Balloon:
In this method,
A sample is removed by hand excavating a hole in the soil.
The volume of the test hole is determined by measuring the volume of water necessary to
fill the hole after a thin, elastic, water tight membrane (balloon) has been inserted into the
hole. .
A slight pressure is applied to the water to ensure complete filling of the test hole.
Newly formed slopes on fills and embankments can be easily damaged by runoff surface water,
cattle, etc.
It is necessary to protect the slopes as soon as they have been constructed. The erosion protection
can be of different types, the most common being planting grass.
A more expensive but fast and effective method is to use stones for protection.
Grass can provide very effective protection against erosion if the right method of planting and
the right type of grass is used.
The planting can be done:
by planting grass runners,
By covering the slopes with turfs (grass).
Side Drain: is the Long flat-bottomed excavation running along the road side, designed to
collect and drain surface runoff water from the carriageway and adjoining land, away from the
roadway to a suitable point of disposal.
Ditch (Drain): A long narrow excavation intended to collect and drain off surface water.
Mitre Drain: is the drain which leads the water out of the side drains and safely disperses it
onto adjoining land.
Catch Water Drain: is a ditch constructed on the uphill side designed to intercept or collect and
drain away surface runoff water flowing towards the road from the uphill side, and lead it to a
suitable point of disposal.
Scour Check: is a small structure placed across the drain on steep gradients and is designed to
slow down the flow of water to prevent erosion of drain invert and slopes.
Apron: is the flat paved area at the culvert inlet or outlet to prevent erosion.
Headwall: is a Retaining wall at the entry or exit of the culvert to retain and protect the
embankment or retained soil.
Wing wall: is a Retaining wall at the side of the culvert or large structures to retain and protect
the embankment or retained soil.
Soffit: The highest point in the internal cross-section of a culvert, or the underside of a bridge
deck.
Basin: A structure at a culvert inlet or outlet to contain turbulence and prevent erosion.
Cut off Wall: is the vertical wall under the headwall to prevent Water from seeping (Leaking)
under the structure.
Invert: is the lowest point on the cross section through the culvert opening.
Weep hole: is an Opening provided in retaining walls to permit drainage of water in the filter
layer or soil layer behind the structure. They prevent water pressure building up behind the
structure.
A trapezoid.
The V-shape is the standard shape for ditches constructed by a motor grader. It can be easily
maintained by heavy equipment, however it carries a low capacity.
The rectangular shape requires little space but needs to be lined with rock or concrete to maintain
its shape.
A trapezoid shape carries a high flow water capacity by carefully selecting the gradients of its
side slopes and resist erosion. It is easy to construct using labour based methods.
V-shaped Rectangular
Trapezoid
It involves the excavation of the ditch, leaving the walls vertical and throwing suitable
excavated material onto the road centre line.
The material thrown into the road centerline area is then spread, watered and compacted.
This forms the first part of camber construction.
Tools Used:
Pick, mattock, hoe, Spades, Heavy duty rake for spreading, Shovels, Watering cans
Equipment
Vibrating roller
Water bowser
Work Method
Set out the width of the ditches on both sides using pegs and strings.
Establish the material pegs and show edge of fill in the middle with strings. (See fig3)
Excavate the ditches for the correct size. Use the ditch template to control width and
depth. (seefig4).
Throw the excavated material to the middle in between the material pegs.
Spread and level the material in the middle
Compact middle layer with vibrating roller
Two situations exist for ditching:
Ditching after excavation to level
Ditching where excavation to level has not taken place
Fig3 :Ditching
Quality Control.
Ensure that the ditch dimensions i.e width and depth are as per the design.
The ditch invert gradient must be checked for compliance at all points. It is very
important that the ditch invert slopes are accurately constructed as errors may lead to
water flowing in the wrong direction.
The compaction can be checked by counting the number of passes made by roller and
checking that no visible roller imprints are present on the finished product.
Environment, Health and safety
A first aid kit must be readily available on site.
In extremely dry areas, dust reduction measures (e.g. dampening the soil with water)
must be considered if unhealthy levels of dust are suspected.
6.3.1 Sloping
The sloping operation involves two activities, namely,
fore sloping
Back sloping.
The sloping involves excavation of both fore slope and back slope and throwing the excavated
material into the road centerline. The suitable material is used to form camber.
6.3.2 Sloping (fore Sloping)
Procedure
Set out the shoulder break-point line using pegs and strings. Establish the material pegs
again and show edge of fill in the middle with string.
Allocate labourers quantity of work for the day accordingly.
Cut the slopes to the correct shape. Use the ditch-slope template to control the slope.
Throw the excavated material to the middle in between the material pegs.(seefig5)
After throwing the excavated material for both fore slope and back slope to the road
centerline, It is spread evenly from the centre line out towards the shoulder break points.
The camber cross fall should be about 10% before compaction and 8% after compaction.
Use a chamber board and a spirit level to check the final camber.
Use a 3m straight edge to check the longitudinal smoothness of the compacted
camber
Camber formation is the spreading of the material excavated from the side drain and compacting
it to the required cross fall.
Procedure:
Set out the shoulder break-point line, using pegs and strings and establish centre line pegs
(Seefig8).
Spread the material that has been heaped in the middle towards the edge (shoulder break Point).
Form the camber by ensuring that the cross fall from the middle to the edge is about 8% to
10%. Check with the camber board and spirit level. The spread material are Compacted with a
pedestrian vibrating roller or tractor towed death weigh roller.
Mitre drains are outfalls of the side drain, which are dug at regular intervals.
Their function is to release the quantity of water collected in the side drain and lead it away from
the road.
The location of mitre drains should be determined during the initial stages when setting out the
road alignment, thereby ensuring that the road receives a good off road drainage.
NB: Sufficient number of mitre drains should be located before side drain excavation starts.
Provide a mitre drain for every 100m or less. This ensures that the quantity of water
being discharged at each mitre drain is small, and does not cause erosion damage to the
drainage system or on the adjoining land
Provide mitre drains at every 50m along the side drain. when the road gradient is very
small,
Where the road is situated on a hillside a significant amount of rainwater may flow down the hill
towards the road.
This may cause damage to the cut face of the road and even cause land slips.
Where this danger exists a catch water drain should be installed to intercept this surface water
and carry it to a safe point of discharge.
The catch water drain should be discharged at least every 200 - 300 metres through a cross
drain to avoid the accumulated water volume.
On side cuts and in full cuts, catch water drains are required to intercept run-off water from big
catchment areas above the roadway, which may overload and silt the side drains.
Work Method:
Set out the catchwater drain using string and pegs. Make sure the gradient of min 2 %
but not steeper than 4% are used
. The drain should not be too close to the cut face, it will cause the land slip (see fig12).
The drain should be minimum 60cm wide and at the valley side 40cm deep.
Excavate the drain with slopes of min. 3:1. Heap the excavated material below the drain
and Compact slightly with hand rammer.
Plant grass or fast growing bush consolidate and retain the material of the block.
Where the gradient of the drain is more than 4% construct scour checks for erosion
control.
French drains are drainage systems in which a pipes are laid at the base of a ditch and protected
by a thick layer of gravel. (A French drain is a term for a gravel-filled trench.)
These trenches are built to block or divert the flow of water through the soil and direct it to a
desired location.
It commonly contains a perforated pipe covered with gravel or rock. It may appear on the surface
to be a gravel pathway, or it may be covered with a grid through which water can pass
French drain to function appropriately, the correct type of stones or gravel are necessary. (See
fig. 13)
Fig. 13. A section through French drain without and with a pipe
The drain with no perforated pipe, they are filled with gravel or stones and they contain voids.
These voids hold water and allow it to flow down the French drain and away from the road
section towards a water outlet.
Shovel, striping spray paint, top soil, sand, drain pipe, gravel, turf, landscaping stones
Fig. 15: Cross-section view showing French drain with one or two underground pipes
The drop inlet is constructed in a square shape with its inside dimensions equivalent to the
outside diameter of the culvert pipe. (See fig. 16)
The thickness of the walls of the drop inlet should follow the thickness of the headwalls and
wing walls. The height should be minimum 40cm higher than the outside diameter of the pipes
and its bed level should flush with the culvert pipe.
The level of the inlet of the collectors should be at the same level as the side drains, and its size
and shape should follow the size and shape of the side drains.
After construction of the drop inlet Gratings should be provided to control debris entering in the
culvert pipe which may cause the blockage (see fig. 16)
Install a bridge.
6.8.2 Culvert outlet
The gradient of 3% is preferred when placing culvert pipes because:
Lower gradient will cause the risk of sediments being deposited in the culvert pipe.
The 3% or higher gradients the flow of water will keep the culvert free of deposits and
APRON
The level of the outlet = the level of the inlet plus the level difference caused by the gradient.
Depth of trench (inlet Level) = Backfill (Camber formation) of 3/4 of the inside diameter of the
pipe (3/4 x 600 = 450mm) Plus The trench depth which is based on the outer diameter
of the culvert pipe.
With a pipe thickness of 60mm, the outer diameter would then be: (600mm + 2 x 60mm) =
720mm Plus Finally, with a 100mm trench bed of imported materials
Depth of trench (inlet level) = 450mm + 720mm + 100mm = 1270mm
Therefore outlet level =450mm + 720mm + 100mm + difference in levels at the inlet and the
outlet
Outlet level =450mm + 720mm + 100mm + 150mm =1420mm
When laying pipes, are placed on a well-compacted foundation, thereby avoiding any future
settlements.
Materials for the culvert bed used consist of gravel or Blinding or concrete (1:3:6) if the soil in
the trench is too soft. Stone can also be used to create adequately strong foundation.
Toe wall
.NB: If the headwalls and wing walls are omitted, the side slopes of the backfill should not be
steeper than 1:2. However with well-graded and cohesive (consistent) natural soils, the gradient
of the side slopes can be increased. The culvert should be long enough to reach the end of the
side slopes on each side of the road.
Fig 24: Culvert pipe end with no headwall and wing wall
Assignment 1:
Write short notes on the following equipment for the drainage work:
1). Boning rods.
2). Camber string line
3). Camber Boards
4). Ditching boards
5). Sloping Board
6). Spirit Level
7). Width and depth stick
Assignment 2:
List and explain wholly the advantages the nation can get from labour based road construction.
(Final work will be power point presentation and typed bound report)
7.1 Culvert
It is a structure constructed under the road and is designed to allow water from the drains and
natural water course to safely cross under the roadway.
The basic guidelines for use of culverts on roads are given below:
Culverts are generally less expensive than drifts. However, transportation costs to remote
areas may make concrete pipes more expensive than drifts.
Culverts require regular routine maintenance.
Culverts concentrate the collection and dispersal of water, which implies that serious
attention must be paid to inlet and outlet works in order to avoid erosion.
Culverts provide a more comfortable ride for motorists than drifts.
Culverts are preferred where cross drainage is at low point where the level of the road is
to be raised to improve its longitudinal gradient.
Once the trench has been excavated, check the level of the bottom with a traveller to
ensure that it is level and with the desired slope. If necessary, use a 100mm layer of compacted
gravel to achieve a solid foundation for the culvert. During excavation, ensure that any water
which may enter the trench can run off.
Example:
Establish the excavation level for the culvert by measuring vertically down 1.39m from peg B
and 1.17m from peg A by using boning rods and a stick or rod of length 1.39m.
The culvert pipes are gently lowered into the trench see fig.26. Avoid the pipes falling onto
each other. This may damage the pipes. Using crowbars, ease the pipes up tight against
each other and ensure that all are in a straight line.
Finally, give serious concern to the outfall and undertake any additional works required
such as properly forming an adequate outlet drain to discharge the water, providing grassing or
stone gabion steps, or other interventions to ensure good erosion protection.
Fig 28: levelled, well compacted base & alignment, inlet, outlet construction of a culvert
NB: During installation of culvert lines, it is very important that the supervising officer is
involved frequently and checks all stages of construction, because many things can go wrong.
Like to discover that concrete foundation, correct slope are absent during final inspection, this
situation may cause erosion and washout of the culvert during the rainy season
A mistake often made in the installation of culverts is, that the side drains on the downstream
side are excavated until they reach the outlet structure, after which the water is expected to make
a 90º-turn into the culvert
The water flowing through the culvert pipe, and the water accumulated in the downstream side
drains, will come together at the outlet of the culvert, causing flow turbulence and as a result,
unnecessary erosion and scouring.
A better and safer option is to excavate mitre drains just 10 to 15 meters before the outlet
structure and divert the water from the side drain into the culvert discharge drain. (See fig below)
Fig 29:Green colour lines show Constructed mitre drain diverted before culvert
outlet.
Fig 30: Section through bedding and haunch of the culvert pipes:
Drift is a low level structure constructed to allow water from the drains and natural water course
to safely cross over the road at bed level.
Drifts are very common structures especially in areas where rivers are seasonal.
Where a constant flow of water has to be accommodated, vented drifts (Irish bridges) are built.
Drifts are built where there is only little or no water flowing in a river during most of the times
(seasonal).
During rainy season when floods are high, the water overtops the drift. Drifts are built using
locally available materials like stones, (masonry, gabions) or concrete where no stones are
available.
Drifts provide an efficient and economic method of allowing water to cross from one side of a
road to the other.
This is done by constructing a stone packed or concrete surface where the water will pass. The
level of the drift is lower than the road on each side, to make sure that water does not spill over
onto the unprotected road surface.
During rains, most drifts carry shallow flows of water through which vehicles can pass, deep
drifts are flooded for short periods and the road will be closed for traffic.
With seasonal flows of water, a concrete slab would be sufficient, however, with all-year-round
flow of water, it is more appropriate to design a vented ford, or a combination of a vented ford
and a drift slab.
Once the site has been established, the finished level of the drift is set out at the same level as the
present level of the riverbed.
The level of the drift should not be set below or above the level of the riverbed, any disturbance
of the natural flow of water may cause scouring at or next to the drift.
But where the river is suffering from silting up, it is better to lift the drift 200 – 250mm above
the natural rived bed. This will speed up the water passing over the drift and reduce the danger of
the drift becoming silted up.
The actual river crossing should be at least the same width as before the drift was constructed.
No attempt should be made to constrain the width of the river by reducing the length of the
actual drift. This may seem feasible during the dry season, however, during high flood periods
this may lead to scouring and eventually wash-outs of parts of the river crossing structure.
When planning the construction of a drift, the approaches are set out first to assess how much
excavation is required.
The traveller is used to measure the depth of the excavation along the proposed approach, and
this is used to estimate the volume of excavation required.
There are a number of solutions ranging from gabions with gravel, stone paving or constructing a
concrete slab.
The choice depends on the following issues:
the expected force of the water flow,
the availability of materials, such as gravel, stone, aggregate and sand,
the quality and strength of the existing river bed foundation, and
Costs of labour and materials.
For slower flowing water, graveled drifts with gabions or dry pitched stone paving is adequate.
The construction drift using gabion and gravel is a simple and economical. A one-metre wide
trench is excavated along the downstream edge of the road.
The gabions are then placed in position, filled with rock and bound together with binding wire.
Gravel is then placed upstream from the gabion to form the road surface. An apron on the
downstream side of the gabion should be constructed to resist scouring.
Gabions have the advantages that;
they are easier and faster to build,
stone of lesser quality and size can be utilized, which are easier to find locally,
gabions are more resistant to erosion and
they do not require skilled masons.
A typical cross section of gabion, gravel and a concrete slab is shown below (see fig. 32).
If the foundation is made of gabions, the concrete is laid on an adjustment layer of gravel/sand
which is placed on the top of the gabion mattresses.
The gravel needs to be levelled to provide a uniform and well-compacted surface on which the
concrete deck is constructed.
Once the concrete has been placed, it should be kept damp and allowed to cure for 7 to 10 days.
An adequate supply of water must be available on site during the curing period, and a worker
should be assigned to keep the concrete surface moist during this period. The traffic needs to be
diverted away from the drift during the curing period.
If the length of the slab is less than 12m there is no need for an expansion joint. On the longer
river crossings, expansion joints are required for approximately every 10 to 15 metres.
(See fig. 32)
7.3 Splashes
Splashes are minor crossings that carry water from a side drain across the road to the lower side.
Splashes are located at low points along the road alignment when the side drain cannot be
emptied by mitre drains and the water has to be lead across the road.
A splash is a low-cost solution to cross road drainage and provides an inexpensive alternative to
culverts.
This drainage structure is normally only applied to rural roads with very limited traffic volumes.
The splash is basically a simplified version of the drift, however, while drifts are used to cross
natural streams and rivers, the splash is mainly used to lead road surface water across and away
from the road.
The main purpose of the splash is
To lead water from the hillside drain across the roadway to be discharged on the
downstream side of the road.
The main design element when building a splash is to secure a surface on which the water can
flow without creating any erosion or reducing the bearing capacity of the road.
In exceptional cases, where there is a limited flow of water, good natural soils and little traffic,
the splash can be built using gravel.
However, in most cases it is necessary to install a more durable surface made from materials
such as stone or concrete.
Similar to drifts, the splash is designed at a lower level than the road with descending approaches
on both sides. The splash needs to be deep enough to cater for the highest flow of water, without
reaching the unprotected road sections on each side of the water crossing.
As with all drainage structures, the frequency and capacity of the splashes need to be assessed in
relation to the overall drainage system of the road
Downstream from the splash, it is necessary to protect the area where the water is discharged.
Using gabions.
Fig. 33 A Plash
Vented ford is a medium level structure designed to allow the normal flow of water in a natural
water course to pass safely through openings below the roadway and to be overtopped during,
periods of heavy rainfall.
Vented fords are used for crossing rivers and streams which carry a minimal flow of water
throughout the dry season while drifts are appropriate for streams which dry out during periods
of the year,
. The advantage of the ford is that
It is a relatively inexpensive structure appropriate for both narrow and wide river
crossings.
Vented fords use a combination of culvert pipes to discharge water under the road during
low water flows, and a drift slab allowing water to overtop the structure during high
water flows.
Like to drifts and culverts, the installation of vented fords needs to be carefully designed, taking
into consideration the topography, the features of the river or stream and the water flow.
The key design parameters for a vented ford are to:
(i) Establish the appropriate drainage required through the culvert pipes during low
flows.
(ii) Provide a sufficiently solid structure with adequate capacity to cater for the highest
water flows.
Important factors for the design of a vented ford are low and high water levels, design and
protection of approach roads and protecting the structure and its surroundings against scouring.
Once the location for the river crossing has been selected, the ford can be set out using the same
methods as when building a drift.
This includes establishing the exact location of the end points of the ford bed and designing the
approach roads with a gentle and uniform slope.
With the highest flood levels established, it is possible to determine the appropriate length of the
sections of the approach roads that need to be protected with a reinforced surface.
Allow between 300mm and 500 mm in elevation between the top of the reinforced roadbed and
the highest level of the floodwater.
The ford need proper aprons on the downstream side of the structure because the stream will
cause some form of disruption in the natural flow of water which may cause scouring in the soils
surrounding the ford.
To avoid the water from scouring the soils close to the inlet and if the ford foundation is weak, it
is useful to install a cut-off wall upstream and strengthen the riverbed next to the inlets. Gabion
mattresses provide low-cost and effective protection for this purpose.
Also the sides of the approach road need to be protected from scouring during high flood levels.
Equipment and construction materials need to be assembled in advance, so work is ready to start
when the stream is at its lowest.
Before any construction work to take place, the existing stream needs to be temporarily diverted
away from the work site as well as the equipment and materials should be read in adverse.
The steps are to
Excavate the trenches for the cut-off walls.
Level the culvert bed and compact between the cut-off walls.
Provide the concrete bedding on which the pipes are to be placed.
The bedding should be indented to accommodate the shape of the culverts and its joints.
The bedding is set out at the correct level and ensure that the culvert pipes are flushing with the
riverbed.
After laying the culvert pipes, the headwalls are constructed up to the road level and built from
cement bound masonry.
The space between the pipes is backfilled with a well-graded stony material.
For the road surface, provide 100mm reinforced concrete layer with a 3% cross-fall.
The surface slab needs to be strong enough to protect the culvert pipes from the expected traffic
loads.
The connection between the approaches and the horizontal stretch should be rounded to provide
a smooth riding surface. The concrete slab must be kept moist for at least 10 days during curing.
Traffic should be kept off the slab for two weeks.
Aprons should be constructed from stone masonry, concrete or gabions.
NB: Marker stones should be placed along both sides of the road surface slab to provide traffic
with proper guidance when the ford is immersed in water (seefig 34).
7.5 Bridge
A structure providing a means of crossing safely above water, railway or other obstruction
whether natural or artificial.
a) Task allocation
The labour required for this activity will vary depending on the workload. However, the limits to
the numbers of labourers will be related to the capacity of the hauling and compaction
equipment.
The gang sizes will vary according to the intensity of the workload. The workload is directly
proportional to the amount of material that must be brought into the formation of the camber.
b) Gender and family issues
Gender issues and Women participation Introduction to Gender Concepts, Issues & Women
Participation
Objectives
Gender is a social construction that determines the relationship between men and women in the
society.
It is referred as a social construction because it is constructed through a socialization
process.
The nature of relationship between men and women is unbalanced, with men treated as
superior human beings (and yet people are born the same).
■ The family institution plays a key role in the socialization process. During the upbringing of
a child in a family, the parent guides the children on how to grow up into a good woman or
man.
■ In most cases, the mothers are responsible for the upbringing of girls into "good" women and
fathers are responsible for the upbringing of boys into "good" men.
■ Apart from being guided by the parents, the children also learn through observation of their
parents with fathers and mothers being models to boys and girls respectively. In these cases,
boys will treat what their fathers do as good practices and girls treat what their mothers do as
good practices and they will copy accordingly.
■ Outside homes, socialization takes place in by peer groups through learning and peer
pressure through sanctioning what is good and bad.
■ Socialization outside the homes also takes place in other institutions such as schools. From
school textbooks, subjects and assignment of roles, pupils/students go through a process that
shapes how they relate with one another when they grow up.
Generally the relationship between men and women is unbalanced, as a result of socialization
process and culture in general that treat women as an inferior group.
■ The low women's participation in decision making at household, community and national
levels (and globally) can be attributed to factors such as marriage (payment of bride price),
poor education of girls, few women in middle and high positions in organisations and
government among others.
■ In most cases, women do not have control over productive resources such as land, a factor of
production, which has resulted into their inability to make decision on production. This has
often led to low levels of livelihood among them.
■ Compared to their female counterparts, men do less work and spend less time in undertaking
the "so called" productive work.
■ In summary, the relationship is that of male superiority and domination. Under this, women
tend to do more work around the homes, which is not recognised as productive, thereby
referred to as reproductive.
Exercise 1
a) List all the productive resources owned by a family. Against each of them, write A for
those accessed by women and "C" for those women have control over.
b) List all the decisions taken in a family on a regular basis. In which of them do women
have a say?
■ Since gender is socially constructed and has to do with attitudes and behaviour, it can be
deconstructed through a similar process outlined under social construction of gender above.
Are roles performed by women and men on a routine basis due to their being in a particular
responsibility positions?
■ Through the socialization process, women and men develop distinctive roles in the
households and communities with women involved in domestic-related responsibilities and
men being active outside the domestic sphere.
■ Some of the roles performed by women within the homes include housekeeping, child caring,
cooking, washing and cleaning among others. Traditionally, no values are given to these
activities and are therefore referred to as reproductive activities.
■ The so-called reproductive roles tend to overwork women, limiting their participation in
productive activities outside homes such as participation in road works
Exercise 2
Construct daily activity profiles for men and women. Giving your analysis of the Activity
Profiles, who does more work and how can the situation be improved?
■ Practical gender needs can be addressed by providing for the immediate needs of women. For
instance, construction of a borehole to solve women's problem of walking long distance to
collect water.
■ However, it should be pointed out that addressing practical needs does not challenge the
status quo (or change the status of women). “Strategic gender needs are those that are long-
term and cannot be solved at one time. Examples include low literacy rates among women,
few women in formal employment and few women in decision-making positions in the
formal and informal sector.
■ Addressing these needs would require a long-term approach such as sending and maintaining
girls in schools. Addressing the strategic gender needs would change women's status quo.
Affirmative action refers to measures designed to favour persons who are at a disadvantage or
treated unfairly because of their status.
■ In gender, affirmative action is female favoritism, which recognizes the disadvantaged
position of women.
■ While providing opportunities to both men and women, factors that put women at a
disadvantage are taken into consideration and attended to as appropriate.
■ Examples of affirmative action in Uganda include:
admission of girls to secondary schools with lower marks
the 1.5 additional points to female students seeking admission to Makerere University
the requirement that a third of Local Council members be women, and
Woman members of parliament from each district.
■ All these have been done in recognition that "the playing field is not levelled" therefore, there
is need to have women supported.
Exercise 3
Women's participation in. number of areas is low For instance, very few women can take
decision on their own and own property
Only highly educated and single women are able to make decision on their own and own
property. Even so their male friends or relatives sometime control this class of women.
Low women's participation in various areas is a result of their upbringing and culture
responsible for that (poor education, early marriages low presence in decision-making
position and payment of bride price among others).
This has resulted in women's issues being poorly addressed, generally leaving women to
lag behind.
Exercise 4
List the advantages and disadvantages of women's participation in road works
When road workers build, maintain, repair, or conduct other work on public roads/ highways,
they must be protected from traffic or haulage hazards. A variety of traffic control measures such
as signs, lights, and other devices, along with continuous patrol, detours, and barricades can be
used as traffic control measures, depending on the type of road and the work being done.
When you start work near a road, evaluate the work site for hazards. Look for blind corners, how
heavy the traffic is, and how fast it flows. Note the weather, temperature, and visibility and how
they will affect the work that you are doing and how motorists will respond. Plan and draw out a
diagram of your work site layout including the staging area, buffer area, transition area, and work
area.
Determine, based on the road type and the typical vehicle speeds, how many advanced warning
signs you will need and how long the buffer area and tapers need to be.
Use at least one warning sign before the road work area begins to inform motorists that they are
approaching an area where workers may be in the road. You may need more signs depending on
sight distance along the road. Use a tapered line of cones to establish and separate the work area
and redirect traffic away from workers. Use clean, unbroken, and highly visible safety cones to
outline traffic lanes. Inspect all signs, signals, and lights to make sure they are working properly
seefig1
After the e work starts, diversion has been completed and before starts, warning sign barriers and
cones must be placed around the work area. Signs must be placed in the following order:
¨Men Working¨ signs should be placed 200 metres in front of the work area.
¨Turn Left/Right¨ arrows should be placed 100 metres in front of the work area.
Cones should be placed diagonally across the road to lead into the diversion
¨Keep Left/Right¨ arrows should be placed at the ends of the lines of cones.
Barriers should be placed behind the lines of cones
¨Speed Limit¨ signs should be placed at the start of the work area,
Barriers should be placed at each end of the work area
End of Restriction¨ signs should be placed beyond the ends of the diversion
At night yellow lamps should also be used to mark the extent of the work at the
diversions.