You are on page 1of 76

Highway Engineering I

CHAPTER 1
INTRODUCTION
1.1 Transport Planning Process
The transportation system now in place is the product of many individual decisions to build
or improve its various parts, such as bridges, highways, tunnels, harbors, railway stations,
and airport runways. Most of these transportation facilities were selected for construction or
improvement because those involved concluded that the project would result in overall
improvement.

Among the factors believed to justify a transportation project are improvements in traffic
flow and safety, savings in energy consumption and travel time, economic growth, and
increased accessibility. Some transportation projects, however, may be selected for other
reasons-for example, to stimulate employment in a particular region, to compete with other
cities or states for prestige, to attract industry, to respond to pressures from a political
constituency, or to gain personal benefit from a particular route location or construction
project. In some instances, transportation projects are /lot selected for construction because
of opposition from those who would be adversely affected. For example, a new highway
may require the taking of residential property, or the construction of an airport may
introduce undesirable noise due to low-flying planes. Whatever the reason for selecting or
rejecting a transportation project, a specific process led to the conclusion to build or not to
build.

The process for planning transportation systems is a rational one that intends to furnish
unbiased information about the effects that the proposed transportation project will have on
the community and on its expected users. For example, if noise or air pollution is a concern,
the process will examine and estimate how much additional noise or air pollution will occur
if the transportation facility is built. Usually cost is a major factor, and so the process will
include estimates of the construction, maintenance, and operating costs.
The process must be flexible enough to be applicable to any transportation project or system,
because the kinds of problems that transportation engineers work on will vary over time.
And the activities of transportation engineers have varied considerably with time, depending
on society's needs and concerns. Examples of societal concerns include energy conservation,
traffic congestion, environmental impacts, safety, security, efficiency, productivity, and

Lecture Note Page 1


Highway Engineering I

community preservation.
The transportation planning process is not intended to furnish a decision or to give a single
result that must be followed, although it can do so in relatively simple situations. Rather, the
process is intended to give the appropriate information to those who will be responsible for
deciding whether the transportation project should go forward.

1.2 The Environment of Highway Engineering

The highway-engineering problem, like any other problem, exists in a complex environment
that must be taken into account in decision-making. The engineer must analyze a particular
problem and, on the basis of this analysis, make recommendations which are not only
scientifically sound but are also adaptable to the physical environment, technologically
achievable, economically viable, and in the final analysis, socially acceptable.

1.2.1 The Physical Environment

This has traditionally been the environment of most concern to engineers, and includes the
following factors:
• Topography
• Geology
• Soils
• Natural drainage
• Vegetation
• Land use
• Rainfall
• Climate
• Materials
Highway engineers quickly come to know the effect of topography on alignment and
gradient or of geology on location and depth of cuts, or of materials on pavement design, or
of vegetation on clearing and grubbing.

Lecture Note Page 2


Highway Engineering I

1.2.2 The Technological Environment

The technological environment in which a solution may be prescribed seriously affects the
success of its implementation, whether success is measured in terms of quality, completion
or time.
Technological factors that affect highway-engineering decisions include:
• Skilled manpower
• Management manpower
• Tools and equipment
• Construction technology
• Technological literacy and awareness

1.2.3 The Economic Environment

Some of the factors that define the economic environment in so far as it affects highway-
engineering decision are as follows:
• Gross national product (GNP) or gross domestic product (GDP).
• Cash versus food crop cultivation.
• Agricultural versus industrial production.
• Distribution of economic activity.
• Export-import ratio.
With very few exceptions, the development of roads is the responsibility of governments,
and the extent to which this responsibility can be met is a function of the ability to set aside
funds from government revenue. The overall performance of the economy, therefore,
whether measured in GNP, GDP or per capita income, compelled with competing demands
from other development sectors establishes the limits of expenditure on road engineering,
whether it is construction or maintenance.

1.2.4 The Social Environment

Social acceptance is a vital factor in highway planning and engineering. A road program
which makes maximum utilization of the surplus manpower that is likely to exist in the rural

Lecture Note Page 3


Highway Engineering I

community through which it passes or into which it extends, and the construction of which is
timed to coincide with off-harvest peaks, is more likely to have the support of the
community than a program which is based on equipment technology requiring the
importation of skilled manpower that is not likely to be found waiting around.

1.3 The Highway Engineering Problem


• The route location problem
• The design problem
• The construction problem
• The maintenance problem

The Route Location Problem:

Between any two points that are to be connected by a road, there exist an infinite number of
combinations of horizontal and vertical alignment. The route location problem is to
establish, initially, a general location, or a narrow band, within which a more precise
alignment would be finally designed.

The Design problem:


➢ Geometric Design
➢ Drainage design
➢ Pavement design

1.4 Economic Evaluation of Highways

Economic evaluation is a rational approach at quantifying the future benefits and costs of
proposed highway improvements with a view to determine to what extent the schemes will
contribute to the goal of raising the living standard of the people and their general welfare.

The economic evaluation of highway schemes is generally done by computing the total
transport cost which consists of the following components:
• Cost of construction of the facility
• Cost of maintenance of the facility

Lecture Note Page 4


Highway Engineering I

• Road user cost


• Cost to the society
Road user cost is composed of:
➢ Vehicle operation cost
➢ Travel time costs
➢ Accident cost
Cost of society includes:
➢ Impact on the environment (noise pollution, air pollution, vibration)
➢ Changes in land values
➢ Land severance
➢ Loss of aesthetics

1.5 Effect of Highways on the Environment

Highway and traffic have earned the dubious distinction of being the worst defilers of the
environment. They have a direct impact on social and community values, the environment
and the ecology. In view of the growing awareness of the community and the government to
preserve and enhance the environmental values, highway engineers have to plan, construct
and maintain highways with this special requirement in mind. Before the highway engineer
prepares any scheme, he should prepare an environmental impact statement. The
environmental impact statement containing an assessment of the anticipated significantly
effects that the proposed action may have on the quality of the environment. The purpose of
the environmental impact statement is to ensure that careful attention is given to
environmental matters and that such matters are appropriately considered in the highway
agency’s decision.

Contents of an environmental impact statement:


• Description of the proposed action and alternatives considered
➢ Location, type, and length of facility, termini, number of lanes, right-of-
way width.
➢ Other design features such as general horizontal and vertical alignment,
structures, etc.

Lecture Note Page 5


Highway Engineering I

➢ Deficiencies of existing facilities, anticipated benefits

• Land use planning: description of planning processes for the area


• Probable impact of proposed action on the environment
➢ Natural, ecological, scenic resource impacts
➢ Relocation of individuals and families
➢ Social impacts
➢ Air quality impacts
➢ Noise impacts
➢ Water quality impacts
➢ Construction impacts
• Alternatives to the proposed action
• Probable adverse environmental effects that cannot be avoided.
• The relationship between local short-term uses of man’s environment and the
maintenance and enhancement of long-term productivity.
• Irreversible and irretrievable commitments of resources.
• The impact on properties and sites of historic and cultural significance
The effect of highways and traffic on the environment will be of the following type:
• Noise pollution
• Air pollution
• Visual intrusion and degrading the aesthetics
• Community impact: relocation of individuals and families.

Lecture Note Page 6


Highway Engineering I

CHAPTER 2
HIGHWAY ALIGNMENT AND ROUTE LOCATION

In general, the aim of alignment selection process is to find a location for the new road that
will result in the lowest total construction, land, traffic and environmental costs. Before an
attempt can be made at selecting a physical location for a highway improvement, data must
be available regarding traffic desires and needs the planning intentions within the area to be
traversed, and estimates or the future physical characteristics of the highway itself: Location
surveys involving geologic and photogrammetric skills provide the basic information for
structural design, as well as the economic analysis that have a considerable influence on the
final location of the highway.

Steps in route location:


• Know the termini points of the scheme.
• From the study of a map of the area, identify and locate:
➢ National parks
➢ Any ancient relics, castles and the likes
➢ Existence of monasteries
➢ Mining sites
➢ Existing transport facilities
➢ Other public facilities (electricity, water)
➢ Location of construction materials
• Conduct preliminary and reconnaissance surveys and collect information on pertinent
details of topography, climate, soil, vegetation, and any other factors.
• Based on the information collected in the previous two steps select a corridor.
• Identify a number of possible centerlines within the corridor.
• Make a preliminary design for the possible alternative alignments and plot on a base
map.
• Examine each of the alternative alignment with respect to grades, volume of earthwork,
drainage, crossing structures, etc to select the best alternative route.

Lecture Note Page 7


Highway Engineering I

• Make final design and location of the selected best alternative route.
Guidelines for Alignment and Route Location

There are certain guidelines that must be borne in mind in selecting the alignment and
locating the route. They are:
• The route of the highway should be so selected that it can handle the traffic most
efficiently and serve the inhabited localities.
• A direct alignment usually results in overall economy.
• The gradients and curvature should be kept to the minimum necessary for the terrain.
Excess of both may result in economy of initial cost, but will involve high operation
costs, time costs and accident costs.
• The location should minimize the use of agricultural land. If a road already exists, it may
be advisable to make use of the land already available to the maximum extent.
• The location should involve the least impact on the environment.
• Obstructions such as cemeteries, places of worship, archaeological and historical
monuments should be steered through.
• Proximity to schools, playgrounds and hospitals should be avoided.
• Interference with utility services like electric overhead transmission lines, water supply
mains, sewers, pipelines, etc should be avoided as far as possible.
• Frequent crossing and recrossing of railway lines should be avoided.
• Locate the highway close to sources of embankment materials and pavement materials.
• Avoid marshy and low-lying land areas having poor drainage.
• Avoid areas liable to flooding.
• Steep terrain should be avoided as much as possible.
• Deep cutting and costly tunnels should be avoided as far as possible.
• When the alignment has to cross major rivers, the crossing point should be fixed
carefully.
To aid in the decision making process, a classical conceptual approach has tended to be
developed with regard to gathering information about the areas being evaluated. Generally,
these can be divided into:
➢ Reconnaissance survey

Lecture Note Page 8


Highway Engineering I

➢ Preliminary location survey and Final location survey

Reconnaissance Survey

The purpose of the reconnaissance survey is to evaluate the feasibility of one or more
corridor routes for a highway between specific points that may be many kilometers away.
Mostly a desk study, good reconnaissance survey can be the greatest single money-saving
phase in the construction of a new road. Hence the engineer should make ample provision in
both time and finance for this stage of highway location study. The following is a useful
checklist of the general information required in the first phase of the reconnaissance study
for a major highway, irrespective of whether it is in a rural or in a urban area.

1. General Land Survey


a) Location of site on published maps and charts
b) Aerial survey, where appropriate
c) Site boundaries, outlines of structures, and building lines
d) Ground contours and natural drainage features
e) Above ground obstructions to view and flying, e.g. transmission lines
f) Meteorological information
2. Permitted use and restrictions
a) Planning and statutory restrictions applying to the particular areas
b) Tunnels, mine-works (abandoned, active and proposed)
c) Ancient monuments, burial grounds, etc
3. Approaches and access (including temporary access for construction purpose)
a) Road
b) Railway
c) By water
d) By air
4. Ground conditions
a) Geological maps
b) Flooding, erosion, landslide and subsidence history
c) Construction and investigation records of adjacent sites

Lecture Note Page 9


Highway Engineering I

d) Seismicity
5. Sources of material for the construction
a) Naturals
b) Tips and waste materials
c) Imported materials
6. Drainage and sewerage
a) Names of the sewerage and land drainage
b) Location and levels of the existing systems
c) Existing flow quantities
d) Flood risk to the proposed works
7. Water supply
8. Electric and gas supply
9. Telephone and others

The first step in the reconnaissance survey is the location and acquisition of all maps and
data relating to the area, as well as the most suitable air photographs. These are then
thoroughly studied. A visit to the area may also be considered desirable at this stage. Where
appropriate, additional information may be obtained from the relevant offices. Next, armed
with questions generated by the desk study, the engineer will evaluate the engineering
economic aspect of the area and delimits areas that are obviously unsuitable for highway
construction.

Upon completion of the reconnaissance survey, the engineer should be at least in a position
to design the more detailed geotechnical investigations which are likely to follow, and
should also have sufficient information available which, when taken in combination with the
social, ecology, traffic, economic, and political inputs, will enable the selection of one or
more apparently feasible corridor routes. If the reconnaissance survey has been very
thorough, and the necessary data are readily available, it may be possible immediately to
carry out the necessary economic and environmental comparisons to aid in the determination
of the best route.

Lecture Note Page 10


Highway Engineering I

The results of these studies are presented in a reconnaissance report. In its barest essentials,
this report should state the service and geometric criteria to be satisfied by the project,
describe the preferred route(s), and present tentative estimates of the cost.

Preliminary Location Survey

The preliminary survey is a large-scale study of one or more feasible corridor routes. It
results in a paper location and alignment that defines the line for the subsequent final
location survey. This paper location and alignment should show enough ties to existing
topography to permit a location party to peg the centerline. In many cases field details for
final design may also be obtained economically during the preliminary survey phase.

The preliminary survey is made for the purpose of collecting the additional physical
information that may affect the location of the highway within a given corridor area, the
shape of the ground, any potential ground subsidence problems, the limits of the catchment
areas, the positions and invert levels of streams and ditches, and the positions of trees, banks
and hedges, bridges, culverts, existing roads, power lines and pipe lines, houses and
monuments are determined and noted. These are then translated into maps, profiles and
(frequently) cross sections that can assist the engineer in the determination of preliminary
grades and alignments and the preparation of cost estimates for alternative centerlines.

Two approaches are available for preliminary survey mapping: aerial surveys and ground
surveys, either separately or in various combinations.

The ground method is best used in the situation where then corridor is closely defined,
narrow right-of-way are contemplated, and the problems of man-made culture are clear.
Ground surveys, beginning with a traverse baseline, will probably furnish necessary data
quite economically. Additional operations that can be quite easily included are the profile
levels and cross-sections, and the ties to land lines and cultural objects.

The aerial survey is likely to be more suitable and economical in the following instances:
➢ Where the reconnaissance was unable to approximate closely the final alignment
➢ Where a wide right-of-way is necessitated

Lecture Note Page 11


Highway Engineering I

➢ Where it is desired to prevent the premature or erroneous disclosure of the details of


probable location (preventing any land speculation or the premature awakening of
local public concerns).
The choice of method should be an educated one, based on an advanced cost analysis that
takes into account the overall project schedule and the time and need requirements of
various techniques. The following discussion is primarily with the carrying out of the
traditional type of ground survey.
o The first step is the carrying out of a baseline traverse – a series of connecting
straight lines and tangents stationed continuously from the beginning to the end of
the survey.
o The degree of accuracy commensurate with the importance of the project and the
nature of the topography being traversed.
o Angles between connecting lines should be measured in accordance with accepted
highway surveying procedures and every single point should be carefully referenced
to at least two points established well outside the area that might be occupied by the
highway construction.
o To furnish date for a profile of the baseline, levels should be taken at all marked
stations, as well as at all important breaks in the ground. Elevations should also be
noted at all cross roads, streams, and other critical points on the line.
o After the baseline has been pegged and levels run over it, the topography elevations
may be taken by one of the several methods, i.e. cross sectional leveling. These are
done at the same time as the profile levels. Observations are made at right angles
from each station as far as is considered necessary to cover the expected construction
area for a given centerline.
o At the same time locations of all trees, fences, building and important elements are
noted so that they can be shown on the preliminary amp.

Final Location Survey

This survey, much of which is very often carried out as part of the preliminary survey,
serves the dual purpose of fixing the centerline of the road, while at the same time
collecting physical data which are necessary for the preparation of plans for construction
purposes.

Lecture Note Page 12


Highway Engineering I

It involves:

✓ fixing the final, permanent, centerline of the road

✓ Additional physical data can be obtained to prepare construction plans.

✓ Leveling data- are fundamental to the vertical alignment, earthworks, and


drainage designs.

– Levels are taken at regular intervals along the center line.

✓ Sub-surface investigation to identify

- Borrow pits and quarry information

Lecture Note Page 13


Highway Engineering I

CHAPTER 3
GEOMETRIC DESIGN OF HIGHWAYS

Geometric design is the process whereby the layout of the road in the terrain is designed to
meet the needs of the road users.

3.1 Appropriate Geometric Standards

The needs of road users in developing countries are often very different from those in the
industrialized countries. In developing countries, pedestrians, animal-drawn carts, etc., are
often important components of the traffic mix, even on major roads. Lorries and buses often
represent the largest proportion of the motorized traffic, while traffic composition in the
industrialized countries is dominated by the passenger car. As a result, there may be less
need for high-speed roads in developing countries and it will often be more appropriate to
provide wide and strong shoulders. Traffic volumes on most rural roads in developing
countries are also relatively low. Thus, providing a road with high geometric standards may
not be economic, since transport cost savings may not offset construction costs. The
requirements for wide carriageways, flat gradients and full overtaking sight distance may
therefore be inappropriate. Also, in countries with weak economies, design levels of comfort
used in industrialized countries may well be a luxury that cannot be afforded.

When developing appropriate geometric design standards for a particular road in a


developing country, the first step should normally be to identify the objective of the road
project. It is convenient to define the objective in terms of three distinct stages of
development as follows:
Stage 1 – Provision of access
Stage 2 - Provision of additional capacity
Stage 3 – Increase of operational efficiency
Developing countries, by their very nature, will usually not be at stage 3 of this sequence;
indeed most will be at the first stage. However, design standards currently in use are

Lecture Note Page 14


Highway Engineering I

generally developed for countries at stage 3 and they have been developed for roads carrying
relatively large volumes of traffic. For convenience, these same standards have traditionally
been applied to low-volume roads that lead to uneconomic and technically inappropriate
designs.

A study to develop appropriate geometric design standards for use in developing countries
has been undertaken by the Overseas Unit of Transport Research Laboratory (TRL formerly
TRRL). The study revealed that most standards currently in use are considerably higher than
can be justified from an economic or safety point of view. Geometric design
recommendations have been published in Overseas Road Note 6.

In the above-mentioned Overseas Road Note 6 rural access roads are classified into three
groups.

Access roads are the lowest level in the network hierarchy. Vehicular flows will be very
light and will be aggregated in the collector road network. Geometric standards may be low
and need only be sufficient to provide appropriate access to the rural agricultural,
commercial, and population centers served. Substantial proportions of the total movements
are likely to be by non-motorized traffic.
Collector roads have the function of linking traffic to and from rural areas, either direct to
adjacent urban centers, or to the arterial road network. Traffic flows and trip lengths will be
of an intermediate level and the need for high geometric standards is therefore less
important.
Arterial roads are the main routes connecting national and international centers. Trip
lengths are likely to be relatively long and levels of traffic flow and speed relatively high.
Geometric standards need to be adequate to enable efficient traffic operation under these
conditions, in which vehicle-to-vehicle interactions may be high.

3.2 Design Controls and Criteria

The elements of design are influenced by a wide variety of design controls, engineering
criteria, and project specific objectives. Such factors include the following:
➢ Functional classification of the roadway

Lecture Note Page 15


Highway Engineering I

➢ Projected traffic volume and composition


➢ Required design speed
➢ Topography of the surrounding land
➢ Capital costs for construction
➢ Human sensory capacities of roadway users
➢ Vehicle size and performance characteristics
➢ Traffic safety considerations
➢ Environmental considerations
➢ Right-of-way impacts and costs

These considerations are not, of course, completely independent of one another. The
functional class of a proposed facility is largely determined by the volume and composition
of the traffic to be served. It is also related to the type of service that a highway will
accommodate and the speed that a vehicle will travel while being driven along a highway.

Of all the factors that are considered in the design of a highway, the principal design criteria
are traffic volume, design speed, sight distances, vehicle size, and vehicle mix.

3.2.1 Design Speed and Design Class

The assumed design speed for a highway may be considered as “the maximum safe speed
that can be maintained over a specified section of a highway when conditions are so
favorable that the design features govern”. The choice of design speed will depend primarily
on the surrounding terrain and the functional class of the highway. Other factors determining
the selection of design speed include traffic volume, costs of right-of-way and construction,
and aesthetic consideration.

It is therefore recommended that the basic parameters of road function, terrain type and
traffic flow are defined initially. On the basis of these parameters, a design class is selected,
while design speed is used only as an index which links design class to the design
parameters of sight distance and curvature to ensure that a driver is presented with a
reasonably consistent speed environment.

Lecture Note Page 16


Highway Engineering I

Table 3.1 shows the design classes and design speeds recommended in Overseas Road Note
6 in relation to road function, volume of traffic and terrain. The table also contains
recommended standards for carriageway and shoulder width and maximum gradient.

The terrain classification as ‘level’, ‘rolling’ or ‘mountainous’ may be defined as average


ground slope measured as the number of five-meter contour lines crossed per kilometer on a
straight line linking the two ends of the road section as follows:
• Level terrain: 0 – 10 ground contours per kilometer;
• Rolling terrain: 11 – 25 ground contours per kilometer;
• Mountainous terrain: > 25 ground contours per kilometer.
Table 3.1 Road design standards (TRRL Overseas Road Note 6)

3.2.2 Sight Distance

The driver’s ability to see ahead contributes to safe and efficient operation of the road.
Ideally, geometric design should ensure that at all times any object on the pavement surface
is visible to the driver within normal eye-sight distance. However, this is not usually feasible
because of topographical and other constraints, so it is necessary to design roads on the basis
of lower, but safe, sight distances.

There are three different sight distances that are of interest in geometric design:
➢ Stopping sight distance;
➢ Meeting sight distance;
➢ Passing sight distance.

Lecture Note Page 17


Highway Engineering I

Stopping Sight Distance:

The Stopping sight distance comprises two elements: d1 = the distance moved from the
instant the object is sighted to the moment the brakes are applied (the perception and brake
reaction time, referred to as the total reaction time) and d2 = the distance traversed while
braking (the braking distance).

The total reaction time depends on the physical and mental characteristics of the driver,
atmospheric visibility, types and condition of the road and distance to, size color and shape
of the hazard. When drivers are keenly as in urban conditions with high traffic intensity, the
reaction time may be in the range of 0.5 – 1.0 seconds while driver reaction time is generally
around 2 – 4 seconds for normal driving in rural conditions. Overseas Road Note 6 assumes
a total reaction time of 2 sec..

The distance traveled before the brakes are applied is:


d1 = 10/36 * V * t
where:
d1 = total reaction distance in m;
V = initial vehicle speed in Km/h
t = reaction time in sec.
The braking distance, d2, is dependent on vehicle condition and characteristics, the
coefficient of friction between tyre and road surface, the gradient of the road and the initial
vehicle speed.
d2 = V2 / (254(f + g/100))
where:
d2 = breaking distance in meters;
V = initial vehicle speed in km/h;
f = coefficient of longitudinal friction;
g = gradient( in %; positive if uphill and negative if downhill)
The determination of design values of longitudinal friction, f, is complicated because of the
many factors involved. The design values for longitudinal friction used in Overseas Road
Note 6 are shown in table 3.2.

Lecture Note Page 18


Highway Engineering I

Table 3.2 Coefficient of Longitudinal friction


Design speed
(Km/h) 30 40 50 60 70 85 100 120
f
0.60 0.55 0.50 0.47 0.43 0.40 0.37 0.35

Meeting Sight Distance:

Meeting sight distance is the distance required to enable the drivers of two vehicles traveling
in opposite directions to bring their vehicles to a safe stop after becoming visible to each
other. Meeting sight distance is normally calculated as twice the minimum stopping sight
distance.

Passing Sight Distance:

Factors affecting passing (overtaking) sight distance are the judgment of overtaking drivers,
the speed and size of overtaken vehicles, the acceleration capabilities of overtaking vehicles,
and the speed of oncoming vehicles.

Passing sight distances are determined empirically and are usually based on passenger car
requirements. There are differences in various standards for passing sight distance due to
different assumptions about the component distances in which a passing maneuver can be
divided, different assumed speed for the maneuver and, to some extent driver behavior.

The passing sight distances recommended for use by Overseas Road Note 6 are shown in
table 3.3.

Table 3.3 Passing sight distances


Design speed 50 60 70 85 100 120
(Km/h)

Passing sight 140 180 240 320 430 590


distance(m)

Lecture Note Page 19


Highway Engineering I

3.2.3 Traffic Volume

Information on traffic volumes, traffic composition and traffic loading are important factors
in the determination of the appropriate standard of a road. The traffic has a major impact on
the selection of road class, and consequently on all geometric design elements. The traffic
information is furthermore necessary for the pavement design.

For low volume roads the design control is the Average Annual Daily Traffic (AADT) in the
‘design year’. For routes with large seasonal variations the design control is the Average
Daily Traffic (ADT) during the peak months of the ‘design year’. The design year is usually
selected as year 10 after the year of opening to traffic.

3.2.4 Design Vehicle

The dimensions of the motor vehicles that will utilize the proposed facility also influence the
design of a roadway project. The width of the vehicle naturally affects the width of the
traffic lane; the vehicle length has a bearing on roadway capacity and affects the turning
radius; the vehicle height affects the clearance of the various structures. Vehicle weight
affects the structural design of the roadway.

The design engineer will select for design the largest vehicle that is expected to use the
roadway facility in significant numbers on a daily basis.

3.3 Geometric Design Elements

The basic elements of geometric design are: the horizontal alignment, the vertical alignment
and the cross-section. The following elements must be considered when carrying out the
geometric design of a road:
1. Horizontal Alignment:
➢ Minimum curve radius (maximum degree of curvature);
➢ Minimum length of tangent between compound or reverse curves;
➢ Transition curve parameters;
➢ Minimum passing sight distance and stopping sight distance on horizontal
curves.

Lecture Note Page 20


Highway Engineering I

2. Vertical Alignment:
➢ Maximum gradient;
➢ Length of maximum gradient;
➢ Minimum passing sight distance or stopping sight distance on summit (crest)
curves;
➢ Length of sag curves.
3. Cross-section:
➢ Width of carriageway;
➢ Crossfall of carriageway;
➢ Rate of super elevation;
➢ Widening of bends;
➢ Width of shoulder;
➢ Crossfall of shoulder;
➢ Width of structures;
➢ Width of right-of-way;
➢ Sight distance;
➢ Cut and fill slopes and ditch cross-section.
Horizontal and vertical alignment should not be designed independently. They complement
each other and proper combination of horizontal and vertical alignment, which increases
road utility and safety, encourages uniform speed, and improves appearance, can almost
always be obtained without additional costs.

3.3.1 Horizontal Alignment

The horizontal alignment should always be designed to the highest standard consistent with
the topography and be chosen carefully to provide good drainage and minimize earthworks.
The alignment design should also be aimed at achieving a uniform operating speed.
Therefore the standard of alignment selected for a particular section of road should extend
throughout the section with no sudden changes from easy to sharp curvature. Where a sharp
curvature is unavoidable, a sequence of curves of decreasing radius is recommended.

Lecture Note Page 21


Highway Engineering I

The horizontal alignment consists of a series of intersecting tangents and circular curves,
with or without transition curves.

3.3.1.1 Straights (Tangents)

Long straights should be avoided, as they are monotonous for drivers and cause headlight
dazzle on straight grades. A more pleasing appearance and higher road safety can be
obtained by a winding alignment with tangents deflecting some 5 – 10 degrees alternately to
the left and right. Short straights between curves in the same direction should not be used
because of the broken back effect. In such cases where a reasonable tangent length is not
attainable, the use of long, transitions or compound curvature should be considered.

The following guidelines may be applied concerning the length of straights:


➢ Straights should not have lengths greater than (20 * V) meters, where V is the design
speed in km/h.
➢ Straights between circular curves turning in the same direction should have lengths
greater than (6*V) meters, where V is the design speed in km/h.
➢ Straights between the end and the beginning of untransitioned reverse circular curves
should have lengths greater than two-thirds of the total superelevation run-off.

3.3.1.2 Circular Curves

Horizontal curvature design is one of the most important features influencing the efficiency
and safety of a highway. Improper design will result in lower speeds and lowering of
highway capacity.

Lecture Note Page 22


Highway Engineering I

Figure 3.1: Parts of a Circular Curve


Note:
• PC – point of curvature
• PI – point of intersection
• PT – point of tangency
• Δ – central angle
• R – radius of curve
• D – degree of curve that defines,
a. Central angle which subtends 20m arc (arc definition),
b. Central angle which subtends 20m chord (Chord definition)
From arc definition,
R = 1145.916 / D
From chord definition,
R = 10 / Sin (D/2)

Lecture Note Page 23


Highway Engineering I

• Tangent (T): distance from PC to PI(backward tangent) or from PT to PI(forward


tangent)
T = R*tan (Δ/2)
• External distance (E): distance from PI to middle of curve.

E = R*(Sec (Δ/2) – 1 or E = T*tan (Δ/4)

• Middle ordinate (M): length from the middle of chord to the middle of curve.

M = R*(1- Cos (Δ/2))


• Long chord(C): straight-line distance from A to B.

C = 2R*Sin (Δ/2)
• Length of Curve (Lc): distance from PC to PT along the curve.

Lc = 20* Δ/D or Lc = R*π* Δ/180


• Sub-arc angles di: are angles subtended by an arc less than the degree of curve (D).
di = Ai*D/20
where:
di = angle subtended by sub-arc of length Ai
Ai = arc less than 20m.

• Sub chord angle (dj): are angles subtended by a chord less than the degree of curve
(D).

cj = 2R*Sin(dj/2)
Also
cj = 20Sin(dj/2)/Sin(D/2)
Where:
dj = angle subtended by sub-chord of length cj
cj = chord less than 20m.

Lecture Note Page 24


Highway Engineering I

• Deflection angles: The angle that a chord deflects from a tangent to a circular curve
is measured by half of the intercepted arc.
o Deflection angle for Lc m = Δ/2
o Deflection angle for 20m = D/2
o Deflection angle for Ai m = di/2
• Stations of PC, PI, and PT:
PC = PI – T
P T = PC + Lc or PT = PI + T

Several variations of the circular curve deserve consideration when developing the
horizontal alignment for a highway design. When two curves in the same direction are
connected with a short tangent, this condition is referred to as a “broken back” arrangement
of curves. This type of alignment should be avoided except where very unusual
topographical or right-of-way conditions dictate otherwise. Highway engineers generally
consider the broken back alignment to be unpleasant and awkward and prefer spiral
transitions or a compound curve alignment with continuous superelvation for such
conditions.

Figure 3.2 identifies elements of a typical compound highway curve with variable
definitions and basic equations developed for a larger and smaller radius curve, based on the
assumption that the radius dimensions RL and RS and central angles ΔL and ΔS are given or
have been previously determined.

Lecture Note Page 25


Highway Engineering I

Figure 3.2 Properties of a Compound Curve

Another important variation of the circular highway curve is the use of reverse curves, which
are adjacent curves that curve in opposite directions. The alignment illustrated in figure 3.3,
which shows a point of reverse curvature, PRC, and no tangent separating the curves, would
be suitable only for low-speed roads such as those in mountainous terrain. A sufficient
length of tangent between the curves should usually be provided to allow removal of the
superelevation from the first curve and attainment of adverse superelevation for the second
curve.

Lecture Note Page 26


Highway Engineering I

Figure 3.3 Properties of a Reverse Curve

Lecture Note Page 27


Highway Engineering I

Sight Distance on Horizontal Curves:

(a) (b)

Figure 3.4 Sight Distance Around Horizontal Curve: (a) S < Lc and (b) S > Lc

Situations frequently exist where an object on the inside of a curve, such as vegetation,
building or cut face, obstructs the line of sight. Where it is either not feasible or
economically justified to move the object a larger radius of curve will e required to ensure
that stopping sight distance is available. The required radius of curve is dependent on the
distance of the obstruction from the centerline and the sight distance.

Case 1. S < Lc
S = 40 * Cos-1 ((R-M)/R) / D
Case 2. S > Lc
M = Lc* (2S - Lc) / 8R

Night driving around sharp curves introduces an added problem related to horizontal sight
distance. Motor-vehicle headlights are pointed directly toward the front and do not provide
as much illumination in oblique directions. Even if adequate horizontal sight distance is
provided, it has little useful purpose at night because the headlights are directed along a
tangent to the curve, and the roadway itself is not properly illuminated.

Lecture Note Page 28


Highway Engineering I

3.3.1.3 Superelevation

Any body moving rapidly along a curved


path is subject to an outward reactive force
called the centrifugal force. If the surface is
flat, the vehicle is held in the curved path
by side friction between tires and
pavement. The total of these friction forces
balances the centrifugal force. Expressed in
terms of the coefficient of friction f and the
normal forces between the pavement and
the tires, the relationship is

m *v2/R = (NL + NR)*f = m*g*f


Figure 3.5 Forces acting on a vehicle moving or
f = v2 / ( g * R)
along a curved path.

When velocity v(m/s) is stated in V(Km/h), and the radius of curve(R) in meters, the
equation reduces to
f = V2 / (127*R)
On highway curves, this centrifugal force acts through the center of mass of the vehicle and
creates an overturning moment about the points of contact between the outer wheels and the
pavement. But a stabilizing (resisting) moment is created by the weight acting through the
center of mass. Thus for equilibrium conditions,

(m * v2 / R) * h = m * g * d/2
and
h = d / (2v2 / gR) = d / 2f
where
h = height of the center of mass above pavement
d = lateral width between the wheels

Lecture Note Page 29


Highway Engineering I

For the moment equation, if f = 0.5, then the height to the center of mass must be greater
than the lateral distance between the wheels before overturning will take place. Modern
passenger vehicles have low center of mass so that relatively high values of f have to be
developed before overturning would take place. In practice, the frictional value is usually
sufficiently low for sliding to take place before overturning. It is only with certain
commercial vehicles having high center of mass that the problem of overturning may arise.

In order to resist the outward acting centrifugal force, and to enable vehicles to round curves
at design speed without discomfort to their occupants, the pavements are “tilted” or
“superelevated” so that the outer edges are higher than the inner edges. This tilting, plus
frictional resistance between the tires and the pavement provides a horizontal resistance to
the centrifugal forces generated by the circular movement of the vehicle around a curve.

Analysis of the forces acting on a vehicle as it moves around a curve of constant radius
indicates that the theoretical superelevation can be expressed as:

e + f = V2 / (127*R) ……………………………………………(*)
where:
e = rate of superelevation(m per m)
f = side friction factor (or coefficient of lateral friction)
V = speed (Km/hr)
R = radius of curvature (m)

Equation (*) above is the basic equation relating the speed of vehicles, the radius of curve,
the superelevation and the coefficient of lateral friction. This equation forms the basis of
design of horizontal curves.

If the entire centrifugal force is counteracted by the superelevation, frictional force will not
be called into play. Proper design does not normally take full advantage of the obtainable
lateral coefficients of friction, since the design should not be based on a condition of

Lecture Note Page 30


Highway Engineering I

incipient sliding. In design, engineers use only a portion of the friction factor, accounting for
the comfort and safety of the vast majority of drivers.

From equation (*), the minimum radius or maximum degree of curvature for a given design
speed can be determined from the rate of superelevation and side friction factor.

R = V2 / (127*(e + f))
D = 1145.916 / R

Attainment of Superelevation:

The transition from a tangent, normal crown section to a curved superelevated section must
be accompanied without any appreciable reduction in speed and in such a manner as to
ensure safety and comfort to the occupants of the traveling vehicle.

The normal cambered surface on a straight reach of road is changed into a superelevated
surface into two stages. In the first stage, the outer half of the camber is gradually raised
until it is level. In the second stage, three methods may be adopted to attain the full super-
elevation.
i. The surface of the road is rotated about the centerline of the carriageway, gradually
lowering the inner edge and raising the upper edge, keeping the level of the
centerline constant.
ii. The surface of the road is rotated about the inner edge, raising the center and the
outer edge.
iii. The surface of the road is rotated about the outer edge depressing the center and the
outer edge.

Method (i) is the most generally used.

The distance required for accomplishing the transition from a normal to a superelevated
section, commonly referred to as the transition runoff, is a function of the design speed and
the rate of superelevation.

Lecture Note Page 31


Highway Engineering I

Superelevation is usually started on the tangent at some distance before the curve starts, and
the full superelevation is generally reached beyond the point of curvature (PC) of the curve.
In curves with transitions, the superelevation can be attained within the limits of the spiral.

Value of Coefficient of Lateral Friction:

The value of coefficient of lateral friction depends upon a number of factors, chief among
them being the vehicle speed, type and condition of roadway surfaces, and type and
condition of the tyres.

Table 3.4 Coefficient of Lateral Friction as Recommended by AASHTO


Design 50 65 80 100 120 130
Speed
(Km/hr)
Maximum 0.16 0.15 0.14 0.13 0.12 0.11
f

Table 3.5 Coeff. Of Lateral Friction as Recommended by TRRL Overseas Road Note 6
Design 30 40 50 60 70 85 100 120
Speed(Km/hr)
f 0.33 0.30 0.25 0.23 0.20 0.18 0.15 0.15

Maximum Superelevation Value:


If eqn (*) is to be used for design, it is desirable to know the maximum superelevation that
can be permitted. Practice in this regard varies from country to country.

According to Transport Construction Design Enterprise (TCDE):


• emax = 10%
• fmax = 0.16

3.3.1.4 Transition Curves

Transition curves provide a gradual change from the tangent section to the circular curve and
vice versa. For most curves, drivers can follow a transition path within the limits of a
normal lane width, and a spiral transition in the alignment is not necessary. However, along

Lecture Note Page 32


Highway Engineering I

high-speed roadways with sharp curvature, transition curves may be needed to prevent
drivers from encroaching into adjoining lanes.

A curve known as the Euler spiral or clothoid is commonly used in highway design. The
radius of the spiral varies from infinity at the tangent end to the radius of the circular arc at
the end of the spiral. The radius of the spiral at any point is inversely proportional to the
distance from its beginning point.

Figure 3.6 Main Elements of A Circular Curve Provided with Transitions

Some of the important properties of the spirals are given below:


▪ L = 2Rθ
▪ θ = (L / Ls)2 * θs
▪ θs = Ls / 2Rc (in radians) = 28.65Ls / Rc (in degrees)
▪ Ts = Ls /2 + (Rc + S)*tan(Δ/2)
▪ S = Ls2 / 24Rc
▪ Es = (Rc + S)*sec(Δ/2) - Rc

Lecture Note Page 33


Highway Engineering I

Note:
θs = spiral angle
Δ = total central angle
Δc = central angle of the circular arc extending from BC to EC = Δ - 2
θs
Rc = radius of circular curve
L = length of spiral from starting point to any point
R = radius of curvature of the spiral at a point L distant from starting
point.
Ts = tangent distance
Es = external distance
S = shift
HIP = horizontal intersection point
BS = beginning of spiral
BC = beginning of circular curve
EC = end of circular curve
ES = end of spiral curve

Length of Transition:

The length of transition should be determined from the following two conditions:
➢ The rate of change of centrifugal acceleration adopted in the design should not cause
discomfort to the drivers. If C is the rate of change of acceleration,
Ls = 0.0215V3 / (C*Rc)
Where:
V = speed (Km/hr)
Rc = radius of the circular curve (m)
➢ The rate of change of superelevation (superelevation application ratio) should be
such as not to cause higher gradients and unsightly appearances. Since
superelevation can be given by rotating about the centerline, inner edge or outer
edge, the length of the transition will be governed accordingly.

Lecture Note Page 34


Highway Engineering I

3.3.1.5 Widening of Curves

Extra width of pavement may be necessary on curves. As a vehicle turns, the rear wheels
follow the front wheels on a shorter radius, and this has the effect of increasing the width of
the vehicle in relation to the lane width of the roadway. Studies of drivers traversing curves
have shown that there is a tendency to drive a curved path longer than the actual curve,
shifting the vehicle laterally to the right on right-turning curves and to the left on left-turning
curves. Thus, on right-turning curves the vehicle shifts toward the inside edge of the
pavement, creating a need for additional pavement width. The amount of widening needed
varies with the width of the pavement on tangent, the design speed, and the curve radius or
degree of curvature.

The widening required can be calculated from


We = n *B2/ 2R + V / 10 R
Where:
We = total widening
B = wheel base
R = radius of curve
V = design speed (Km/hr)
n = number of lanes

3.3.2 Vertical Alignment

The vertical alignment of the roadway and its effect on the safe, economical operation of the
motor vehicle constitute one of the most important features of a highway design. The
vertical alignment, which consists a series of straight profile lines connected by vertical
parabolic curves, is known as the profile grade line. When the profile grade line is increasing
from a level or flat alignment, this condition is referred to as a “plus grade”, and when the
grade is decreasing from a level alignment, the grade is termed a “minus grade”. In
analyzing grade and grade controls, the designer usually studies the effect of change on the
centerline profile of the roadway.

Lecture Note Page 35


Highway Engineering I

In the establishment of a grade, an ideal situation is one in which the cut is balanced against
the fill without a great deal of borrow or an excess of cut material to be wasted. All
earthwork hauls should be moved in a downhill direction if possible and within a relatively
short distance from the origin, due to the expense of moving large quantities of soil. Ideal
grades have long distances between points of intersection, with long curves between grade
tangents to provide smooth riding qualities and good visibility. The grade should follow the
general terrain and rise or fall in the direction of the existing drainage. In rock cuts and in
flat, low-lying or swampy areas, it is necessary to maintain higher grades with respect to the
existing ground line. Future possible construction and the presence of grade separations or
bridge structures can also act as control criteria for the design of a vertical alignment.

3.3.2.1 Grades and Grade Control

Changes of grade from plus to minus should be placed in cuts, and changes from a minus
grade to a plus grade should be placed in fills. This will generally give a good design, and
many times it will avoid the appearance of building hills and producing depressions contrary
to the general existing contours of the land. Other considerations for determining the grade
line may be of more importance than the balancing of cuts and fills.

In the analysis of grades and grade control, one of the most important considerations is the
effect of grades on the operating costs of the motor vehicle. An increase in gasoline
consumption, a reduction in speed, and an increase in emissions and noise are apparent when
grades are increased. An economical approach would be to balance the added cost of grade
reduction against the annual costs and impacts of vehicle operation without grade reduction.
An accurate solution to the problem depends on the knowledge of traffic volume and type,
which can be obtained by means of a traffic survey.

Minimum grades are governed by drainage conditions. Level grades may be used in fill
sections in rural areas when crowned pavements and sloping shoulders can take care of the
pavement surface drainage. However, it is preferred that the profile grade be designed to
have a minimum grade of at least 0.3 percent under most conditions in order to secure
adequate drainage.

Lecture Note Page 36


Highway Engineering I

3.3.2.2 Vertical Curves

The parabolic curve is used almost exclusively in connecting profile grade tangents. The
primary reason for the use of this type of curve in vertical highway alignments is the
convenient manner in which the vertical offsets can be computed and the smooth transitions
created from tangent to curve and then back to tangent. When a vertical curve connects a
positive grade with a negative grade, it is referred to as a “crest curve”. Likewise, when a
vertical curve connects a negative grade with a positive grade, it is termed a “sag curve”.
Various configurations of crest and sag curves are illustrated in figure 3.7. Various
definitions and basic equations for a typical vertical curve are presented in figure 3.8. The
sign conventions for g1 and g2 allow the use of the same formulas in the calculation of
offsets and elevations for a sag curve also.

All distances along vertical curves are measured horizontally, and all offsets from the
tangents to the curve are measured vertically. Accordingly, the length of a vertical curve is
its horizontal projection. The error resulting from this assumption is negligible in practice
since the curve is quite flat. Unless otherwise defined, vertical curves are symmetrical in the
sense that the tangents are equal in length.

Figure 3.7 Types of crest and sag vertical curves

Lecture Note Page 37


Highway Engineering I

Figure 3.8 Properties of a typical vertical curve

Lecture Note Page 38


Highway Engineering I

3.3.2.3 Length Of Vertical Curves

A. Crest Curves:

For crest curves, the most important consideration in determining the length of the
curve is the sight distance requirement.

Case1: S < L

GS 2
L=
( 2h1 + 2h2 ) 2

Case 2: S > L

2( h1 + h2 ) 2
L = 2*S −
G

AASHTO recommendations:
• For stopping sight distance over crest: h1 = 1.07m and h2 = 0.15m
• For passing sight distance over crest: h1 = 1.07m and h2 = 1.30m

B. Sag Curves:

For sag curves, the criteria for determining the length are vehicle headlight distance,
rider comfort, drainage control and general appearance.

Lecture Note Page 39


Highway Engineering I

B.1 Headlight Sight Distance:

Case 1: S < L

S 2G
L=
1.22 + 0.035* S

Case 2: S > L

 1.22 + 0.035* S 
L = 2S −  
 G 

B.2 Comfort

There is still a considerable difference of opinion as to what value of radial acceleration


should be used on vertical curves for comfort purposes. The most commonly quoted values
are between 0.30 and 0.46m/s2, but lesser values are preferred. If the vertical radial
acceleration is assumed to be equal to ar (in m/s2), then

V 2G
L= V - speed in Km/hr
13ar

Lecture Note Page 40


Highway Engineering I

3.3.2.4 Sight Distances at Underpass Structures:

Case 1: S < L
S 2G
L=
8m
Where:
m = C – (h1+h2)/2
C = Vertical clearance distance

Case 2: S > L

8m
L = 2S −
G

• AASHTO recommendations: h1 = 1.829m, h2 = 0.457m and C = 5.182m

3.3.3 Cross-Section

The cross-sectional elements in a highway design pertain to those features that deal with its
width. They embrace aspects such as right-of-way, roadway width, central reservations
(medians), shoulders, camber, side-slope etc.

Right- Of –Way

The right-of-way width is the width of land secured and preserved to the public for road
purposes. The right-of-way should be adequate to accommodate all the elements that make
up the cross-section of the highway and may reasonably provide for future development.

Lecture Note Page 41


Highway Engineering I

Road Width

Road width should be minimized so as to reduce the costs of construction and maintenance,
whilst being sufficient to carry the traffic loading efficiently and safely.

The following factors need to be taken into account when selecting the width of a road:
1. Classification of the road. A road is normally classified according to its function in
the road network. The higher the class of road, the higher the level of service
expected and the wider the road will need to be.
2. Traffic. Heavy traffic volumes on a road mean that passing of oncoming vehicles
and overtaking of slower vehicles are more frequent and therefore that paths of
vehicles will be further from the center-line of the road and the traffic lanes should
be wider.
3. Vehicle dimensions. Normal steering deviations and tracking errors, particularly of
heavy vehicles, reduce clearances between passing vehicles. Higher truck
percentages require wider traffic lanes.
4. Vehicle speed. As speeds increase, drivers have less control of the lateral position of
vehicles, reducing clearances, and so wider traffic lanes are needed.
Figure 3.9 shows the typical cross-sections recommended by Overseas Road Note 6, for the
various road design classes A – F.

The cross-section of the road is usually maintained across culverts, but special cross-sections
may need to be designed for bridges, taking into account traffic such as pedestrians, cyclists,
etc., as well as motor traffic. Reduction in the carriageway width may be accepted, for
instance, when an existing narrow bridge has to be retained because it is not economically
feasible to replace or widen it. It may also sometimes be economic to construct a
superstructure of reduced width initially with provision for it to be widened later when
traffic warrants it. In such cases a proper application of traffic signs, rumble strips or speed
bumps is required to warn motorists of the discontinuity in the road.

Lecture Note Page 42


Highway Engineering I

Figure 3.9 Typical cross-sections (TRRL Overseas Road Note 6)

Lecture Note Page 43


Highway Engineering I

For single-lane roads without shoulders passing places must be provided to allow passing
and overtaking. The total road width at passing places should be a minimum of 5.0m but
preferably 5.5m, which allows two trucks to pass safely at low speed. The length of
individual passing places will vary with local conditions and the sizes of vehicles in
common use but, generally, a length of 20m including tapers will cater for trucks with a
wheelbase of 6.5m and an overall length of 11.0m.

Normally, passing places should be located every 300-500m depending on the terrain and
geometric conditions. They should be located within sight distance of each other and be
constructed at the most economic locations as determined by terrain and ground conditions,
such as at transitions from cut to fill, rather than at precise intervals.

Shoulders

Shoulders provide for the accommodation of stopped vehicles. Properly designed shoulders
also provide an emergency outlet for motorists finding themselves on a collision course and
they also serve to provide lateral support to the carriageway. Further, shoulders improve
sight distances and induce a sense of ‘openness’ that improves capacity and encourages
uniformity of speed.

In developing countries shoulders are used extensively by non-motorized traffic


(pedestrians, bicycles and animals) and a significant proportion of the goods may be
transported by such non-motorized means.

Cross-Fall

Two-lane roads should be provided with a camber consisting of a straight-line cross-fall


from the center-line to the carriageway edges, while straight cross-fall from edge to edge of
the carriageway is used for single-lane roads and for each carriageway of divided roads.

The cross-fall should be sufficient to provide adequate surface drainage whilst not being so
great as to be hazardous by making steering difficult. The ability of a surface to shed water
varies with its smoothness and integrity. On unpaved roads, the minimum acceptable value
of cross-fall should be related to the need to carry surface water away from the pavement

Lecture Note Page 44


Highway Engineering I

structure effectively, with a maximum value above which erosion of a material starts to
become a problem.

According to Overseas Road Note 6 the normal cross-fall should be 3% on paved roads and
4 – 6% on unpaved roads.

Due to the action of traffic and weather the cross-fall of unpaved roads will gradually be
reduced and rutting may develop. To avoid the rutting developing into potholes a cross-fall
of 5 – 6% should be reestablished during the routine and periodic maintenance works.

Shoulders having the same surface as the carriageway should have the same cross-slope.
Unpaved shoulders on a paved road should be about 2% steeper than the cross-fall of the
carriageway.

Side Slopes

The slopes of fills (embankments) and cuts must be adapted to the soil properties,
topography and importance of the road. Earth fills of common soil types and usual height
may stand safely on slopes of 1 on 1.5 and slopes of cuts through undisturbed earth with
cementing properties remain in place with slopes of about 1 on 1. Rock cuts are usually
stable at slopes of 4 on 1 or even steeper depending on the homogeneity of the rock
formation and direction of possible dips and strikes.

Using these relatively steep slopes will result in minimization of earthworks, but steep
slopes are, on the other hand, more liable to erosion than flatter slopes as plant and grass
growth is hampered and surface water velocity will be higher. Thus the savings in original
excavation and embankment costs may be more than offset by increased maintenance
through the years.

Lecture Note Page 45


Highway Engineering I

CHAPTER 4: EARTHWORK

The term earthwork includes all clearing, grubbing, roadway and drainage excavation,
excavation for structures, embankments, borrow, overhaul, machine grading, subgrade
scarifying, rock fill, and all the operations of preparing the subgrade foundation for highway
or runway pavement.

The quantity and cost of earthwork are calculated in terms of cubic meters of excavation in
its original position on the basis of cross-section notes from field measurements.

Modern grading operations are carried on by power equipment including power shovels,
scrapers, bulldozers, blade graders, rollers, dragline excavators, motor trucks, tractors, etc.

Classification of Excavated Material

Excavated material is usually classified as (1) common excavation, (2) loose rock, or (3)
solid rock. Common excavation is largely earth, or earth with detached boulders less than ½
cu yd. Loose rock usually refers to rock which can be removed with pick and bar, although
the use of power shovels or blasting may be advantageous. Solid rock comprises hard rock
in place and boulders that can be removed only by the use of drilling and blasting
equipment.

Shrinkage and Swell Factors

When earth is excavated and hauled to form an embankment, the freshly excavated material
generally increases in volume. However, during the process of building the embankment it is
compacted, so that the final volume is less than when in its original condition. This
difference in volume is usually defined as “shrinkage”. In estimating earthwork quantities, it
is necessary to make allowance for this factor. The amount of shrinkage varies with the soil
type and the depth of the fill. An allowance of 10 to 15 percent is frequently made for high
fills and 20 to 25 percent for shallow fills. The shrinkage may be as high as 40 or 50 percent
for some soils. This generally also allows for shrinkage due to loss of material in the hauling
process.

Lecture Note Page 46


Highway Engineering I

When rock is excavated and placed in the embankment, the material will occupy a larger
volume. This increase is called “ swell” and may amount to 30 percent or more.

Percent shrinkage = ( 1 – ( wt. bank measure / wt. compacted ) ) *100

% sh. = ( 1 – (γB / γC) ) * 100 …………………………………………..(1)

Percent swell = ((wt. bank measure / wt. loose measure) – 1) * 100

% sw. = ((γB / γL) - 1) * 100 …………………………………………..(2)

Cross-Sections and Templates

In order to determine earth excavation and embankment requirements by manual means, a


section outline of the proposed highway, commonly referred to as a template section, is
placed on the original ground cross-section; the areas in cut and the areas in fill are
determined; and the volumes between the sections are computed. Figure 4.1 shows various
conditions that may be encountered when plotting these template sections. “Cut” and “fill”
are the terms that are usually used for the areas of the sections, and the terms “excavation”
and “embankment” generally refer to volumes.

Each cross-section should show the


location or station of the original
ground section and template section,
the elevation of the proposed grade at
the station, and the areas of cut and
fill for each section. The computed
volume of excavation and
embankment may also be placed on
the cross-section sheet between two
successive cross-sections.

Figure 4.1 Original ground line and


template sections

Lecture Note Page 47


Highway Engineering I

Slope Stakes

The final grade line having been established, slope stakes are set at points where the side
slopes of the graded road will intersect the ground surface; they mark the limits of the
excavation and embankment. The slope stakes are driven at points of zero cut or fill, but the
numbers written on them give the vertical distance with reference to the finished grade of the
subgrade. On the inner side of the stakes is marked in meters the “cut” or “fill” as the case
may be. Thus, “C1.2” indicates that the centerline elevation of the roadbed is to be cut 1.2m
below the ground at the slope stake; and “F2.3” indicates that the fill is to be 2.3m above the
slope stake.

The stakes are driven with the tops slanting outward and with the sides upon which the cuts
or fills are marked facing the roadway. The station number is marked on the outside of the
stake. The usual equipment for setting slopes consists of a level, rod, tape, notebook, stakes,
and keel.

If a profile map has been established from previous surveys and the final grade line drawn
thereon, the centerline cut or fill may be found from the map by subtracting the elevation of
grade from the elevation of ground.
Also, if a cross-section of the ground and finished shape of roadway have been plotted to
scale, the position of the slope stakes could be scaled from the map.

Aside from the elevation of grade, the most satisfactory procedure is to determine all
distances and elevations in the field. The method must necessarily be a “measure and try”
process, but the work can be done rather easily.

General Method of Procedure: Let ABEPD in Figs. 4.2 and 4.3 represent the cross-
sectional area of highway in fill or cut, for which we have the following general notation
applying to both excavation and embankment:
b = AB = AC + CB = width of roadbed
s = “slope ratio” for the banks AD and BE = ratio of horizontal to vertical (plus for
cut, minus for fill)
d = PC = depth of fill or cut at the center

Lecture Note Page 48


Highway Engineering I

x1 = horizontal distance from P to slope stake at D


x2 = horizontal distance from P to slope stake at E
y = vertical distance from P to slope stake
h1 = d + y1 = FD = vertical distance from C to D
h2 = d + y2 = GE = vertical distance from C to E

Figure 4.2 Cross section on fill (slope


stakes at E and D)

Figure 4.3 Cross section in cut (slope


stakes at E and D)

The slope stake at point D on the right is correctly established if

x1 = ½ b + sh1 = ½ b + sd + sy1 ……………………………………..(3)

Likewise, point E on the left is correctly established if

x2= ½ b + sh2 = ½ b + sd + sy2 ……………………………………...(4)

In the foregoing equations, b, d, and s are known, while x and h (or y) are measured and
remeasured in the field until the equations are satisfied (trial-and-error method).

If the ground is level, y1 = y2 = 0; then x1 = x2 = ½ b + sd.

In fig. 4.3, it is assumed that rod readings to all points within the cross profile under
consideration can be taken from a single position of the level (which of course is not always

Lecture Note Page 49


Highway Engineering I

possible). By means of previous differential leveling from the nearest benchmark, the HI
(height of instrument or elevation of line HJK) is established.

If we imagine the bottom of the road to be at grade at point C, the rod reading would be CJ,
which is called “grade rod”. That is

Grade rod = HI – grade elevation

Negative values of grade rod would occur when the HI is below “grade”.

Since the actual reading at the centerline stake (fig. 4.3) is PJ (not CJ), the depth of cut is CP
= CJ – PJ; that is,
d = grade rod – ground rod

Negative values of d indicate fill.

Similarly at the slope stake D,


FD = FK – DK
That is, h1 (or h2) = grade rod – ground rod

Negative values of h indicate fill.

The values of x1 and h1 (or x2 and h2) corresponding to the intersection of two slopes are
found easily after two or three field measurements.

Area of Cross-Section

From the data supplied by slope stake or cross-section notes, the area of cross-section may
be calculated. If the ground is level or regular, simple geometry may be applied; for irregular
ground, two general methods are used; (1) the graphical method and (2) the coordinate
method.

Lecture Note Page 50


Highway Engineering I

➢ Area for Level Ground. For level ground, the area of cross-section in cut (or fill) is
merely that of a trapezoid. In figure 4.4:
b = width of base AB
d = center cut (or fill)
s = slope of banks = MD / AM = NE / BN
Hence,
Area = d(b + sd) …………………………………..(5)

Figure 4.4

➢ Area for Three-Level Section. With three readings taken directly from slope stake
notes, one at the center and one at each slope stake, the area of cross section may be
obtained. For regular ground, this is an accurate and very satisfactory method. Such a
section is known as a three-level section, and the area may be calculated readily from
field notes without plotting.

Imagine the area ABED (fig. 4.5) to be divided into four triangles, two having the
common base d and altitudes x1 and x2, and two having bases = ½ b and altitudes h1
and h2. Hence the area of section is

A = ½ [d(x1 + x2) + ½ b(h1 + h2)] ………………………….(6)

Figure 4.5

If the slope stake notes are not available and the center fill is known, the end area
A may be found conveniently from the four field measurements indicated in fig. 4.6.
Assuming uniform slope of the original ground underneath the fill,

A = ½ (h1x’’ + h2x’) ………………………………….(7)

Lecture Note Page 51


Highway Engineering I

Figure 4.6

➢ Area by Coordinate Method. With the coordinates of all the corners of a cross-
section known, the end area may be computed by means of the coordinate method.

Let the corners A, B, C, and D of the area ABCD (fig. 4.7) be located by the
coordinates (x1,y1), (x2,y2), (x3,y3), and (x4,y4). Then the area is given by the
algebraic sum of four trapezoids. Thus,

Area = ABba + BCcb – ADda - DCcd


=1/2 [y1(x4 – x2) + y2(x1 - x3) + y3(x2 – x4) + y4(x3 – x1)] …………….(8)

From eqn.(8) we may state the following rule for


area:

Multiply each ordinate by the algebraic difference


between the adjacent abscissas, find the algebraic
sum of the products, and then take half of this
result.

Figure 4.7 Area by coordinate method

A simpler rule for area follows if we arrange in counterclockwise order the


coordinates (fig. 4.7) in the form of fractions, the initial fraction (beginning at any
corner) being repeated to give a closed boundary. Thus, we have

Lecture Note Page 52


Highway Engineering I

y1 y2 y3 y4 y1
x1 x2 x3 x4 x1

Multiply along the marked diagonals and add the products (all positive); multiply
along the unmarked diagonals and add the products (all negative). The difference
gives the double area.

Volume of Earthwork

The volume of earthwork may be found by means of either the average end area or the
prismoidal formula. Although the former is less exact than the latter, it is generally accepted
as the standard earthwork formula, on account of its simplicity.

➢ Average End Area Formula. The volume of a right prism equals the average area
multiplied by the length. Assuming the average area to be the same as the average
end area,

Volume = V = ½ (A1 + A2)L

In which: A1 and A2 = area of end sections (m2)


L = length of solid (m)

This formula is applied to areas of any shape, but the results are slightly too large.
The error is small if the sections do not change rapidly.

➢ Prismoidal Formula. A prismoid is a solid whose ends are parallel and whose sides
are plane or wrapped surfaces. Fig. 4.8 represents a typical prismoid.

Lecture Note Page 53


Highway Engineering I

Figure 4.8

The volume of a prismoid is:

V = L/6 (A1 + 4Am + A2)

In which L is the distance between the two parallel bases A1 and A2 and Am is a
section midway between the two end bases and parallel to them. Am is not an average
of A1 and A2, but each of its linear dimensions is an average of the corresponding
dimensions of A1 and A2.

Haul and Overhaul

In grading contracts for roads it is usually stipulated that the contractor shall be paid a
certain price per cubic meter for excavating, hauling, and dumping the material, regardless
of distance hauled, provided it does not exceed a specified limit called free haul. The free
haul distance may be as low as 150m and as high as 900m or more.

If there is an overhaul on some of the material, that is, if the distance from excavation to
embankment is beyond the free haul limit, then an extra charge may be allowed.

A mass diagram is helpful in determining the amount of overhaul and the most economical
distribution of the excavated material.

Limit of Economic Haul

When there are long hauls, it may be more economical to waste and borrow materials rather
than pay for the cost of overhauling. Equating the cost of excavation plus overhaul to the

Lecture Note Page 54


Highway Engineering I

cost of excavation from both the roadway and borrow pit, one can estimate the limit of
economic haul for making the embankment. Thus, let
c = cost of roadway excavation per cubic meter
b = cost of borrow per cubic meter
h = cost of overhaul, on the bases of 1m3 per station
x = economical length of overhaul

Cost to excavate and move 1m3 material from cut to fill

= c + hx …………………………………………….(a)

Cost to excavate from cut, waste, borrow, and place 1m3 material in fill

=b+c ……….….………………………………..(b)

Equating equations (a) and (b) and solving for x, we have

x = b/h (s + a) …………………………………..(c)

adding the free haul distance to equation (c), we get the limit of economical haul.

Mass Diagram

A mass diagram is a graphical representation of the amount of earthwork and embankment


involved in a project and the manner in which the earth is to be moved. Its horizontal or x-
axis represents distance and is usually expressed in meters or stations. It is drawn to the
same horizontal scale as the profile. The vertical or y-axis represents the cumulative quantity
of earthwork in cubic meters. The quantity of excavation on the mass diagram is considered
positive, and embankment as negative. Preliminary to drawing the mass curve it is
convenient to tabulate the cumulative volumes of cuts and fills at each station.

Lecture Note Page 55


Highway Engineering I

The mass diagram allows a highway engineer to determine direction of haul and the quantity
of earth taken from or hauled to any location. It shows “balance points”, the stations between
which the volume of excavation (after adjustment for “shrinkage” or “swell”) and
embankment are equal.

Figure 4.9: Profile and mass diagram. AC = free-haul distance; HJ – AC = overhaul


distance; BB = free-haul volume; A’A = C’C = overhaul volume; OD = length of balance.

A study of the mass diagram (or curve) shown in figure 4.9 will verify the following
statements:
• The ordinate at any point on the mass curve represents the cumulative volume to that
point on the profile.
• Within the limits of a single cut, the curve rises from left to right; within the limits of a
single fill, it falls from left to right.
• Sections where the volume changes from cut to fill correspond to a maximum; sections
where the volume changes from fill to cut correspond to a minimum. Evidently the
maximum and minimum points on the diagram occur at, or near, grade points on the
profile.

Lecture Note Page 56


Highway Engineering I

• Any horizontal line, as AC, cutting off a loop of the mass curve, intersects the curve at
two points between which the cut is equal to the fill (adjusted for shrinkage). Such a line
is called a balance line.
• The loops convex upward indicate that the haul from cut to fill is to be in one direction
(to the right in this case); loops concave upward indicate a reverse direction of haul.
• The final point on a mass diagram for a given project gives the overall net amount of
earthwork for the entire project. This amount, if positive, would indicate a surplus of
excavation material and a need to waste that quantity of material. If the final point on the
mass diagram is a negative amount, it indicates a net shortage of earthwork for the
project and a need to borrow that quantity of earthwork material.

Determination Of Overhaul From The Mass Diagram: One of the important uses of the
mass diagram, aside from balancing cuts and fills and indicating the most advantageous
distribution of the same, is to establish definitely the overhaul distance and the portion of the
total volume which is to be regarded as hauled beyond the specified free-haul limit.

Referring to figure 4.9, proceed as follows:

i. Assuming the free-haul distance to be 150m, find by trial a horizontal line


intersecting the curve at points A and C, such that AC = 150m. Then the material
above line AC will be hauled at no extra cost. The amount of this material is given
by the ordinate from line AC to point B and is a measure of the volume in cut from a
to b, which makes the fill from b to c.

ii. Consider now the volume above the balance line OD. A study of the mass curve and
the corresponding profile shows that the cut from o to b will make the fill from b to
d. But since part of this solidity, the part above the balance line AC, is included in
the free-haul limit, the other part between lines OD and AC – which is measured by
the ordinate A’A – is subject to overhaul unless wastage and borrow take place. That
is, some or all of the volume from o to a may be “overhauled” to make the fill from c
to d.

Lecture Note Page 57


Highway Engineering I

The average length of haul of the solidity from o to a to make the fill from c to d is the
distance between the centers of gravity of cut o to a and fill c to d. The gravity lines are
found as follows: Bisect AA’ at M and draw a horizontal line intersecting the mass curve
at H and J. These points H and J are assumed to be vertically below the desired centers
of gravity. Therefore the average haul is given by the length of line HJ, and the overhaul
is this distance HJ less the free haul distance AC. The overhaul distance (in stations)
multiplied by the net volume gives the station-volumes of overhaul.

It should be note that the foregoing graphical method of determining the center of
gravity of the masses in cut and fill is inaccurate when there is abruptness in the mass
curve. In such cases, a more accurate method is to divide the volume in parts and take
moments about a vertical line of reference just as is done in finding the center of gravity
of a system of forces.

The mass diagram may be used to indicate the most economical procedure for disposing
of excavated material, what part of it should be moved forward or backward, and
whether borrowing and wasting are advisable. Thus if the balance line OD is continued
horizontally to point X, it will be seen that the cuts and fills from o to f are balanced, but
the solidity represented by the ordinate at G is excess cut (from f to g) which may be
carried forward, backward, or wasted. If the project ends at point g or if there are no fills
immediately ahead, then this excavated material should be carried backward to help
make the fill from b to c (it being downhill and within the free-haul limit), while an
equivalent amount of volume from the cut o to a would be wasted, thus reducing the
station-volume of overhaul.

Lecture Note Page 58


Highway Engineering I

Example: Given the following end areas for cut & fill, complete the earthwork
calculation using a shrinkage of 10%. Then draw the M.H.D. and the longitudinal profile
of the earthworks & find the following:
a) Limit of Economic Haul (L.E.H.).
b) Freehaul volume (F.H.V.).
c) Overhaul volume (O.H.V.).
d) Waste volume.
e) Borrow volume.
f) Total cost of the earthworks.
Given that:
- Cost of overhaul = 30 ID/m3.station.
- Cost of borrow = 120 ID/m3.
- Cost of freehaul = 70 ID/m3.
- Freehaul Distance (F.H.D.) = 200m = 2 stations.
Solution:
2 3 3
Station Areas (m ) Volumes (m ) Excess of (m ) Cumulative
3
Volume(m )
Cut Fill Cut+ Fill- Corrected Cut+ Fill-
Fill -
0 10 - 1100 -- -- 1100 -- 0
1 12 - 1300 -- -- 1300 -- +1100
2 14 - 1500 -- -- 1500 -- +2400
3 16 - 1500 -- -- 1500 -- +3900
4 14 - 350 250 275 75 -- +5400
5 - 10 -- 1300 1430 -- 1430 +5475
6 - 16 -- 1500 1650 -- 1650 +4045
7 - 14 -- 1300 1430 -- 1430 +2395
8 - 12 -- 1000 1100 -- 1100 +965
9 - 8 300 200 220 80 -- -135
10 12 - 1400 -- -- 1400 -- -55
11 16 - +1345

Lecture Note Page 59


Highway Engineering I

Notes for the table:


✓ 1100 = [(10+12)/2]*100 (by using average area method).
✓ 350 = [(14+0)/2]*[100/2]
✓ 275 = 250 * (1.10) (Correction by shrinkage factor).
✓ 75 = 350 - 275
✓ 80 = 300 - 220
• Economic overhaul limit (L) = (cost of borrow/cost of overhaul) = (120/30)
= 4 stations.
Therefore, Limit of Economic Haul (L.E.H.) = Free haul distance + Economic overhaul limit
= 2 + 4 = 6 stations.

Lecture Note Page 60


Highway Engineering I

• Freehaul volumes = (FHV1+FHV2) =


• Overhaul volumes = (OHV1+OHV2) =
• Waste volume =
• Borrow volume =
• Total cost of the earthworks =
= [cost of freehaul*(FHV1+FHV2)] + [cost of waste*waste vol.] + [cost
of borrow*borrow vol.] + [cost of freehaul*(OHV1+OHV2)] +
[(cost of overhaul*OHV1*(average hauling distance1-FHD)) + (cost
of overhaul*OHV2*(average hauling distance2-FHD)]
= ---------------

Lecture Note Page 61


5. INTERSECTIONS, INTERCHANGES, AND TERMINALS

5.1. Intersections

Intersections are areas shared by two or more roads serving conflicting traffic when
competing for the same space at the same time when going ahead or changing directions.
Intersections vary in complexity from a simple intersection, which has only two roads
crossing at a right angle to each other, to a more complex intersection, at which three or more
roads cross within the same area. The process of decision making for road users at
intersections is complex and this is part of the reason why intersections tend to have a high
potential for accidents and delays. The overall traffic flow on any highway depends to a great
extent on the performance of the intersections, since intersections usually operate at a lower
capacity than through sections of the road.

Intersections are generally classified into three general categories:

• At-grade intersections,
• Grade-separated without ramps, and
• Grade-separated with ramps (commonly known as interchanges).

Grade-separated intersections usually consist of structures that provide for traffic to cross at
different levels (vertical distances) without interruption. The potential for accidents at grade-
separated intersections is reduced because many potential conflicts between intersecting
streams of traffic are eliminated. At-grade intersections do not provide for the flow of traffic
at different levels, and therefore there exist conflicts between intersecting streams of traffic.

5.1.1. At Grade Intersections


Most highways intersect at grade, and the intersection area should be designed to provide
adequately for turning and crossing movements, with due consideration to sight distance,
signs, and alignments. The basic types of at-grade intersections are T, Y or three-leg
intersections, which consist of three approaches; four-leg or cross intersections, which consist
of four approaches; and multileg intersections, which consist of five or more approaches. A
few examples of these types of intersections are given Figure 6 - 1.

5.1.2. Grade Separations and Interchanges

Intersections at grade can be eliminated by the use of grade-separation structures that permit
the cross flow of traffic at different levels without interruption. The advantage of such
separation is the freedom from cross interference with resultant saving of time and increase in
safety for traffic movements. Grade separations and interchanges may be warranted

(1) As part of an express highway system designed to carry high volumes of traffic,
(2) To eliminate bottlenecks,
(3) To prevent accidents,
(4) Where the topography is such that other types of design are not feasible,

57
(5) Where the volumes to be catered for would require the design of an intersection
at grade of unreasonable size, and
(6) Where the road user benefit of reducing delays at an at-grade intersection
exceeds the cost of the improvement.

Figure 5 - 2 Types of at grade intersection

An interchange is a grade separation in which vehicles moving in one direction of flow may
transfer by the use of connecting roadways. These connecting roadways at interchanges are
called ramps. Many types and forms of interchanges and ramp layouts are used. Some of these
are shown Figure 5 - 3. The choice between these intersection types depends on various
factors such as traffic, economy, safety, aesthetics, delay, space requirements, etc.

58
Figure 5 - 3. Highway interchanges

5.2. Design Principles of At-Grade Intersections

The fundamental objectives in the design of at-grade intersections are to minimize delay and
the number and severity of potential conflicts among different streams of traffic and between
pedestrian and turning vehicles. At the same time, it is necessary to provide for the smooth
flow of traffic across the intersection. The design should therefore incorporate the operating
characteristics of both the vehicles and pedestrians using the intersection. For example, the
corner radius of an intersection pavement or surfacing should not be less than either the
turning radius of the design vehicle or the radius required for design velocity of the turning
roadway under consideration. The design also should ensure adequate pavement widths of
turning roadways and approach sight distances. This suggests that at-grade intersections
should not be located at or just beyond sharp crest vertical curves or at sharp horizontal
curves.

59
The basic requirements of intersection design are maximize safety and minimize traffic delay.
The design of an at-grade intersection involves:

(1) The design of the alignment including profiles, minimum radius and widths of
turning roadways,
(2) The design of a suitable channelling system for the traffic pattern,
(3) The assurance that the sight distances are adequate for the type of control at the
intersection.

Alignment of At-Grade Intersections

The best alignment for an at-grade intersection is when the intersecting roads meet at right or
nearly right angles. This alignment is superior to acute-angle alignments because much less
road area is required for turning at the intersection, there is a lower exposure, time for
vehicles crossing the main traffic flow, and visibility limitations, particularly for trucks, are
not as serious as those at acute-angle intersections. Figure 5 - 4 shows alternative methods for
realigning roads intersecting at acute angles to obtain a nearly right-angle intersection.

Figure 5 - 4. Alternative methods of realigning skewed intersections

In designing the profile (vertical alignment) at the intersection, large changes in grade should
be avoided; preferably, grades should not be greater than 3 percent. The stopping and
accelerating distances for passenger cars on grades of 3 percent or less are not much different
from those of cars on flat grades; however, significant differences start to occur at grades
higher than 3 percent. When it is unavoidable to use grades of 3 percent or more, design
factors such as stopping distances and accelerating distances should be adjusted so that

60
conditions equivalent to those on level ground exist. In any case, it is not advisable to use
grades higher than 6 percent at intersections.

It should always be remembered that the combination of horizontal and vertical alignments at
an intersection should produce traffic lanes that are clearly seen by motorists at all times,
without the sudden appearance of potential hazards. Also, motorists should be able to easily
understand the path they should take for any desired direction. The angle of turn, the turning
speed, the design vehicle, and traffic volume are the main factors governing the design of
curves at at-grade intersections. When the turning speed at an intersection is assumed to be 25
km/h or less, the curves for the pavement edges are designed to conform to at least the
minimum turning path of the design vehicle. When the turning speed is expected to be greater
than 25 km/h, the design speed is also considered. It is also necessary to increase the
pavement width of turning roadways when the speed is greater than 25 km/h.

Channelisation of At-Grade Intersections

AASHTO defines channelisation as the separation of conflicting traffic movements into


definite paths of travel by traffic islands or pavement markings to facilitate the safe and
orderly movements of both vehicles and pedestrians. A traffic island is a defined area between
traffic lanes where vehicular traffic is excluded and provided to regulate the movement of
vehicles or to serve as a pedestrian refuge. A properly channelised intersection will result in
increased capacity, enhanced safety, and increased driver confidence. Properly designed
channelisation systems increase intersection capacity and decrease conflicts and accidents.

Islands in an intersection serve one or more of the following purposes:

1. Separation of conflicts
2. Control of angle of conflict
3. Reduction of excessive pavement areas
4. Regulation of traffic flow in the intersection area
5. Arrangements to favour a predominant turning movement
6. Protection of pedestrians
7. Protection and storage of turning and crossing vehicles
8. Location of traffic control devices.

Islands are generally grouped into three major classes: directional or channelised, divisional,
and refuge. Islands can be formed by using raised curbs, pavement markings, or the pavement
edges. General types and shapes of islands are shown in Figure 5 - 5. Directional islands are
designed primarily to guide the motorist through the intersection by indicating the intended
route. Where spacious area exists at an intersection and leaves much to the discretion of the
driver, islands may be used to channel the motorist into the desired lane by placing a
channelling island in the little-used portion of the intersection.

Divisional islands are most frequently used on undivided highways approaching intersections.
They serve to alert the driver to the intersection and regulate the flow of traffic into and out of
the intersection. Their use is particularly advantageous for controlling left-turning traffic at
skewed intersections. A refuge island is located at or near crosswalks to aid and protect
pedestrians crossing the roadway. Refuge islands are most generally used on wide streets in
urban areas for loading and unloading of transit riders.

61
Figure 5 - 5. Types and shapes of islands

Sight Distance at Intersections

The high accident potential at an intersection can he reduced by providing sight distances that
allow drivers to have an unobstructed view of the entire intersection at a distance great
enough to permit control of the vehicle. At-grade intersections either have no control or are
controlled by one of the following methods: yield control, stop control, or signal control. At
signalised intersections, the unobstructed view may be limited to the area where the signals
are located, but for un-signalised intersections, it is necessary to provide an adequate view of
the crossroads or intersecting highways to reduce the potential of collision with crossing
vehicles.

Figure 5- 6. Minimum sight triangle at an intersection

62
Figure 5- 6 shows a schematic of the sight triangle required for the location of an obstruction
that will allow for the provision of the minimum distance da and db. the safe stopping sight
distance for the give design speed should be used for da and db. It can be seen from that
triangle ABC and ADE are similar, which gives:

CB ED
=
AB AD

db a
=
da da − b

From this equation, if any of the variables da, db, a, and b are known the fourth can be
determined.

Sight Distance Requirements for No-Control Intersections: - In this situation the


intersection is not controlled by a yield sign, a stop sign, or a traffic signal, but sufficient sight
distance is provided for the operator of a vehicle approaching the intersection to see a crossing
vehicle and if necessary to adjust the vehicle's speed so as to avoid a collision. This distance
must include the distance travelled by the vehicle both during the driver's perception reaction
time and during brake actuation or the acceleration to regulate speed. At intersections, 2.0 sec
is usually acceptable for perception reaction time, and an additional 1.0 see is added for the
driver to actuate braking or to accelerate to regulate speed. It is, generally, preferable to
design uncontrolled intersections such that the driver of each vehicle sees the intersection and
the traffic on the crossroad insufficient time for stopping the vehicle before reaching the
intersection.

Sight Distance Requirements for Yield-Control Intersections: - In this situation the minor
road is controlled by a yield sign. Vehicles on the minor road are therefore required to yield to
vehicles on the major road, which often requires the vehicle on the minor road to slow down
or to stop prior to reaching the intersecting roadway. The sight distance provided on the minor
road must therefore be sufficient for the driver to see a vehicle approaching from either the
left or right of the major road, and to be able to stop the vehicle before reaching the
intersecting roadway, as shown in Figure 5- 6. The solution is similar to that for the no-
control condition except that in this case the minimum stopping sight distances given for the
appropriate speeds are always used for da, and db. It should be noted that the grades of the
approaches should be taken into consideration when determining the minimum stopping sight
distances.

Sight Distance Requirement for Stop-Control Intersections: - When vehicles are required
to stop at an intersection, the drivers of such vehicles should be provided sufficient sight
distance to be able to stop the vehicle before reaching the intersecting roadway and allow for
a safe departure from the stopped position for the three basic manoeuvres that occur at an
average intersection. These manoeuvres are:

(1) Crossing the intersection, thereby clearing traffic approaching from both sides of the
intersection,
(2) Turning left onto the crossroad, which requires clearing the traffic approaching from
the left and then joining the traffic stream on the crossroad with vehicles
approaching from the right, and

63
(3) Turning right onto the crossroad by joining the traffic on the crossroad with vehicles
approaching from the left.

Sight Distance at Intersections with Signal Control: - Although the unobstructed view at
signalised intersections may be limited to the area of control, it is recommended that the
minimum sight distances based on sight distance requirement for stop-control intersections be
made available at these intersections. These minimum sight distances are necessary to avoid
the hazardous situations resulting from unanticipated conflicts at signalised intersections,
including signal failure, vehicles running the red light, use of the flashing red/yellow mode,
and right turns on red. The basic principle of signalised intersections is to provide sight
distances that will enable the driver to see the signals early enough to take the necessary
action indicated by the signals.

5.3. Traffic Controls

The purpose of traffic control is to assign the right of way to drivers, and thus to facilitate
highway safety by ensuring the orderly and predictable movement of all traffic on highways.
Control may be achieved by using traffic signals, signs, or markings that regulate, guide,
warn, and/or channel traffic. Complex maneuvering areas of highways such as intersections
require properly designed traffic control systems.

Conflicts occur when traffic streams moving in different directions interfere with each other.
The three types of conflicts are merging, diverging, and crossing. Figure 5 - 7 shows the
different conflict points that exists at a four-approach unsignalized intersection. There are 32
conflict points in this case. The number of possible conflict points at any inter- section
depends on the number of approaches, the turning movements, and the type of traffic control
at the intersection.

Figure 5 - 7. Conflict points at four-approach unsignalised intersection

The primary objective in the design of a traffic control system at an intersection is to reduce
the number of significant conflict points. In designing such a system, it is first necessary to

64
undertake an analysis of the turning movements at the intersection, which will indicate the
significant types of conflicts. Factors that influence the significance of a conflict include the
type of conflict, the number of vehicles in each of the conflicting streams, and the speeds of
the vehicles in these streams. Crossing conflicts, however, tend to have the most severe effect
on traffic flow and should be reduced to a minimum whenever possible.

Types of intersection control: - Several methods of controlling conflicting streams of


vehicles at intersections are in use. The choice of one of these methods depends on the type of
intersection and the volume of traffic in each of the conflicting streams. The different types of
intersection control are described below.

YIELD Signs: - Yield signs are usually placed on minor-road approaches; where it is
necessary to yield the right of way to the major-road traffic. All drivers on approaches with
yield signs are required to slow down and yield the right of way to all conflicting vehicles at
the intersection. Stopping at yield signs is not mandatory, but drivers are required to stop
when necessary to avoid interfering with a traffic stream that has the right of way.

STOP Signs: - A stop sign is used where an approaching vehicle is required to stop before
entering the intersection. A stop sign may be used on a minor road when it intersects a major
road, at an unsignalised intersection, and where a combination of high speed, restricted view
and serious accidents indicates the necessity for such a control. Stop signs should not be used
at signalised intersections or on through roadways of expressways.

Roundabouts: - A roundabout is a means of traffic control where one-way traffic is


circulating around a central island. Priority within the roundabout is controlled by GIVE
WAY (YIELD) signs for entering traffic, although occasionally traffic signals may be used. It
considerably reduces the number and severity of conflicts, makes the traffic flow self-
regulatory and continuous, reduces congestion, and promotes safety.

Traffic Signals: - One of the most effective ways of controlling traffic at an intersection is
the use of traffic signals. Traffic signals can be used to eliminate many conflicts because
different traffic streams can be assigned the use of the intersection at different times. Since
this results in a delay to vehicles in all streams, it is important that traffic signals be used only
when necessary. The most important factor that determines the need for traffic signals at a
particular intersection is the intersection's approach traffic volume, although other factors
such as pedestrian volume and accident experience may also play a significant role.

The efficient operation of the signal requires proper timing of the different colour indication,
which is obtained by implementing the necessary signal timing design. The main objectives of
signal timing at an intersection are to reduce the average delay of all vehicles and the
probability of accidents. These objectives are achieved by minimizing the possible conflict
points when assigning the right of way to different traffic streams at different times. The cycle
length for an isolated intersection should be short, preferably between 35 and 60 sec, although
it may be necessary to use longer cycles when approach volumes are very high. However,
cycle lengths should be kept below 120 sec, since very long cycle lengths will result in
excessive delay. Several methods have been developed for determining the optimal cycle
length at an intersection and, in most cases, the yellow interval is considered as a component
of the green time.

Figure 5 - 8 shows a typical two-phase signal system to illustrate the terminologies commonly
used in the design of signal times.

65
Figure 5 - 8. Two-phase signal system

Yellow interval: - The main purpose of the yellow indication after the green is to alert
motorists to the fact that the green light is about to change to red and to allow vehicles already
in the intersection to cross it. A bad choice of yellow interval may lead to the creation of a
dilemma zone, an area close to an intersection in which a vehicle can neither stop safely
before the intersection nor clear the intersection without speeding before the red signal comes
on. The required yellow interval is the time period that guarantees that approaching vehicles
can either stop safely or proceed through the intersection without speeding.

The yellow interval, which eliminates the dilemma zone, is estimated from the following
equations:

W + L u0
τ min = δ + +
u0 2a

If the effect of grade is added,

W +L u0
τ min = δ + +
u0 2(a + Gg )

where, τ min = the minimum yellow interval, (sec)


δ = perception-reaction time, (sec)
W = width of intersection, (m)
L = length of vehicle, (m)
u 0 = speed (m/sec)
a = deceleration, (m/sec2)
G = grade of the approach road, and
g = acceleration due to gravity.
Yellow intervals of 3 to 5 sec are normally used. When longer yellow intervals than 5 sec are
computed from the above equations, an all-red phase can be inserted to follow the yellow

66
indication, but the change interval, yellow plus all-red, must be at least the value computed
from the equations.

Cycle Lengths: - The signals at isolated intersections can be pretimed (fixed), semiactuated,
or fully actuated. Pretimed signals assign the right of way to different traffic streams in
accordance with a preset timing program. Each signal has a preset cycle length that remains
fixed for a specific period of the day or for the entire day. Several design methods have been
developed to determine the optimum cycle length, two of which the Webster method is
presented here.

Webster Method. Webster has shown that for a wide range of practical conditions, minimum
intersection delay is obtained when the cycle length is obtained by the equation

1.5 L + 5
C0 = n
1 − ∑ Yi
i =1
where, C0, = optimum cycle length (sec)
L = total lost time per cycle (sec)
Yi = maximum value of the ratios of approach flows to saturation flows for all
traffic streams using phase i (i.e., Vij/ Sj)
n = number of phases
Vij = flow on lane j having the right of way during phase
Sj = saturation flow on la.nei

Total Lost Time. Figure 5 - 9 shows a graph of rate of discharge of vehicles at various times
during a green phase of a signal cycle at an intersection. Initially, some time is lost before the
vehicles start moving, and then the rate of discharge increases to a maximum. This maximum
rate of discharge is the saturation flow. If there are sufficient vehicles in the queue to use the
available green time, the maximum rate of discharge will be sustained until the yellow phase
occurs. The rate of discharge will then fall to zero when the yellow signal changes to red. The
number of vehicles that go through the intersection is represented by the area under the curve.
Dividing the number of vehicles that go through the intersection by the saturation flow will
give the effective green time, which is less than the sum of the green and yellow times. This
difference is considered lost time, since it is not used by any other phase for the discharge of
vehicles; it can be expressed as

li = Gai + τ i − Gei

where, li = lost time for phase i


Gai = actual green time for phase i (not including yellow time) ,
τ i = yellow time for phase i
Gei = effective green time for phase i

Total lost time is given as


n
L = ∑ li + R
i =1
where, R is the total all-red time during the cycle.

67
Figure 5 - 9. Discharge of vehicle at various times during a green phase

Allocation of Green Times. In general, the total effective green time available per cycle is
given by

⎛ n ⎞
Gte = C − L = C − ⎜ ∑ l i + R ⎟
⎝ i =1 ⎠

where, C = actual cycle length used (usually obtained by rounding off C0, to the nearest 5 sec)
Gte = total effective green time per cycle

To obtain minimum overall delay, the total effective green time should be distributed among
the different phases in proportion to their Y values to obtain the effective green time for each
phase.

Yi
Gei = Gte
Y1 + Y2 + ... + Yn

and the actual green time for each, phase is obtained as

Ga1 = Ge1 + l1 − τ 1
G 2 i = Ge 2 + l 2 − τ 2
Gai = Gei + l i − τ i
Gan = Gen + l n − τ n

68
Example Figure 5 - 10shows peak-hour volumes for a major intersection on an arterial
highway. Using the Webster method, determine suitable signal timing for the intersection
using a four-phase system and the additional data given in the figure. Use a yellow interval of
3 sec.

a) Data on traffic flow

b) Equivalent straight-through passenger cars


Figure 5 - 10. Peak-hour volumes for major intersection on a an arterial highway

69
Solution:

First convert the mixed volumes to equivalent straight-through passenger cars. The equivalent
volumes are shown in Figure 5 - 10b. The volumes were obtained by dividing by the PHF,
and then by applying the relevant factors for trucks and left-turning vehicles as necessary. No
factors for right-turning vehicles were used because those volumes were very low. Assume
the following phasing system, where the arrows indicate traffic streams that have the right of
way:

The critical lane volumes are (see Figure 5 - 10b):

Phase, n Critical Lane Volume


A 499
B 338
C 115
D 519
Σ1471

Compute the total lost time using. Since there is not an all-red phase-that is, R = 0 and there
are four phases,
L = Σli = 4 x 3.5 = 14 sec

Determine Yi and Σ Yi:

Phase A (EB) Phase B (WB) Phase C (SB), Phase D (NB)


Lanes: 1 2 3 1 2 3 1 2 3 1 2 3
Vij 335 490 499 189 338 338 115 79 37 519 105 217
Sj 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000
Vi/Si 0.17 0.25 0.25 0.09 0.17 0.17 0.06 0.04 0.019 0.26 0.05 0.11

Yi 0.25 0.17 0.06 0.26


Σ Yi = 0.74

Determine the optimum cycle length


1.5 L + 5
C0 = n
1 − ∑ Yi
i =1

70
1.5 × 14 + 5
C0 =
1 − 0.74
= 100 sec
Find the total effective green time:
Gte = C - L
= (100 - 14) = 86 sec

Effective time for phase i is obtained from:

71

You might also like