Professional Documents
Culture Documents
Sani
THE FEDERAL POLYTECHNIC NASARARAWA
DEPARTMENT OF CIVIL ENGINEERING
LECTURE NOTE (1 of 5) ON HIGHWAY ENGINEERING (CEC 413)
CLASS: HND 2
INTRODUCTION
The transportation by road is the only mode which could give maximum service to one and all. The road or
highways not only include the modern highway system but also the city streets, feeder roads and village roads,
catering for a wide-range of road vehicles and the pedestrians. This mode has also maximum flexibility for travel
with reference to route, direction, time and speed of travel etc. through any mode of road vehicle. It is possible to
provide door to door service by road transport. The other three modes (railways; water ways; airways) has to
depend on the roadway for the service. Ultimately, road network is therefore needed not only to serve as feeder
system for other modes of transportation and to supplement them, but also to provide independent facility for road
travel by a well-planned network of roads throughout. The illustrations below give some insight into highway
classification.
HIGHWAY LOCATION
• Road locations are most easily determined in relatively undeveloped, low-cost areas where basic
engineering and construction cost considerations dominate the cost of the road provided that
environmental issues are not of major concern.
Page 1 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
• However, the road location become more complex and non-engineering’ issues become more
conspicuous if the route is required to pass through well-developed rural areas. This is because the new
road has to interact with existing roads and built-up areas.
• Moreover, the problems are at their most complex when the road traverse major urban areas where
community desires, interactions with existing roads and streets, and economic, environmental and
planning issues become critical.
• Ideally a new major road needs to be located where the following objectives are achieved at minimum
construction, environmental, land, traffic operations and maintenance costs.
However, due to its profound complexity, the location process in and about an urban area can, in practice,
be reduced to finding an alignment that meets traffic desire lines, is acceptable to the public, and enables
road construction to occur at an economical cost.
The location of a new major road can require consideration of many complex and interrelated factors,
which normally utilize the skills of economists, geologists, planners and surveyors as well as those of road
engineers (see Table below).
Page 2 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
Reconnaissance Survey
• Walking the sites
• Several feasible routes are identified, each within a band of a limited width of a few hundred metres
• For rural roads, maps or photographs give little information, and therefore aerial photography is
commonly used to obtain the required information.
• Feasible routes are identified through careful examination of the aerial photographs, with due
consideration of the following factors:
Terrain and soil conditions
Serviceability of route to industrial and population areas
Crossing of other transportation facilities, such as rivers, railroads, and highways
Directness of route
Page 3 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
• Control points between the two endpoints are determined for each feasible route. For example, a bridge
site with no alternative may be taken as a primary control point. The feasible routes carefully chosen are
then plotted on photographic base maps.
A particular location is usually selected based on the following factors in relation to the design control
Topography
Soil characteristics
Environmental factors such as noise and air pollution
Economic factors
Human habitation
• Route location process consists of selecting the best compromise between 'demand‘ factors and 'terrain'
factors. Demand factors determine the areas to be served and the road standard, and terrain factors
influence the engineering cost.
• The principal terrain factors are:
Ground conditions as they influence the strength of the soil beneath the road (the sub grade) or present
instability problems or natural hazards
Materials used in construction, including quarried rock
Earthworks (the volume and stability of cuttings and embankments)
Surface and sub-surface drainage, including erosion
• The emphasis placed on these different factors will vary with the stage of the survey. The choice of route
is normally associated with the identification and feasibility stages.
• One of the major objectives of these stages is to identify critical factors which could have a major impact
on engineering costs and therefore deserve extra study at the early stages of the project.
• Changes to the design that must be made during the course of a construction contract often involve
considerable disruption, delay and expense, and are normally the result of insufficient preliminary survey
work.
• The main principle for highway location is that the roadway elements involved are blended together to
produce a system that meets the design criteria and safety standards while allowing for smooth flow of
traffic at the design capacity. The Primary principles of route location consist of the following
Connect two points with shortest distance
Traverse through favorable topography
Avoid areas where land cost is high
Determine the two end terminus
Principles of route location
Page 4 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
• Also, highway location process should ensure minimum disruption to historic, religious and
archaeological sites and to other land-use activities. The minimum disruption can be achieved through
careful Environmental Impact Assessment (EIA).
• The highway location process involves the following phases:
Reconnaissance survey (study of existing information)
Preliminary location survey
Final location survey
Preliminary Location Survey
• The positions of the feasible routes are set as closely as possible by establishing all the control points and
determining preliminary vertical and horizontal alignments for each.
• In the course of the preliminary survey the
• detailed relief of the ground,
• the locations of ‘soft’ ground and
• potential ground subsidence areas,
• the limits of the water catchment areas,
• the positions and invert levels of streams and ditches,
• the positions of trees, banks and hedges, bridges, culverts, existing tracks and roads, power lines and
pipelines, houses and monuments, and other natural and man-made cultural places need to be clearly
determined and noted for each route within the established corridor.
• These details are then translated into base topographic maps so that likely road alignments can be plotted.
• Preliminary alignments are used to evaluate the economic and environmental feasibility of the
alternative routes.
Economic Evaluation
• Economic evaluation of each alternative route is carried out to determine the future effect of investing the
resources necessary to construct the highway. Factors usually taken into consideration in Economic
evaluation include
Road user costs
Construction costs
Maintenance costs
Road user benefits and
Road user dis-benefits (adverse impacts due to dislocation of families, businesses etc.)
The results obtained from the economic evaluation of the feasible routes will provide information
on the economic resources that will be gained or lost if a particular location is selected. This
Page 5 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
information is also used to aid the policy maker in determining the type of highway to be built
and whether it is economically viable.
Environmental Evaluation
• Highway is an integral part of the local environment, therefore, highway constructions at any location
will have a significant impact on its surroundings.
• The environment in which the highway is built comprises interrelated variables: plant, animal, and
human communities and encompasses social, physical, natural, and man-made variables.
• These variables are in a manner that maintains equilibrium and sustains the lifestyle of the different
communities.
• The construction of a highway may offset the equilibrium and result in significant adverse effects on the
environment. This may lead to a reduction of the quality of life of the animals and/or human
communities. Hence the need for environmental impact of any alignment selected be fully evaluated.
• Federal government legislation has been enacted that sets forth the requirements of the environmental
evaluation required for different types of projects.
The environmental evaluation should include:
A detailed description of each route alternatives
The probable environmental impact, including the assessment of positive and negative effects on the
environment
An analysis of short-term impact as differentiated from long-term impact
Any secondary effects, which may be in the form of changes in the patterns of social and economic
activities
Probable adverse environmental effects that cannot be avoided if the project is constructed
Any irreversible and irretrievable resources that have been committed
• In cases where an environmental impact study is required, it is conducted at this stage to determine the
environmental impact of each alternative route. Such a study will determine the negative and/or positive
effects the highway facility will have on the environment.
• For example, the construction of a freeway at grade through an urban area may result in an unacceptable
noise level for the residents of the area (negative impact), or the highway facility may be located so that it
provides better access to jobs and recreation centres (positive impact).
• Public hearings are also held at this stage to provide an opportunity for constituents to give their views on
the positive and negative impacts of the proposed alternatives.
The best alternative, based on all the factors considered, is then selected as the preliminary
alignment of the highway.
Final Location Survey
Page 6 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
process.
• Once the need for a major road has been justified by the transport planning process, the approach to
selecting an appropriate route location can be described as a ‘hierarchically structured decision process’.
See Fig. 1.
• The first step in the location process requires fixing the end termini (i.e. two points to be connected)
• Defining a region, A, which will include all feasible routes between these two points; in a non-urban
setting this region will often be, say, one-third as wide as it is long.
• The region is then searched using reconnaissance techniques to obtain a limited number of broad bands,
B and C, within which further (refining) searches can be concentrated; for a rural motorway, for example,
such bands might be as much as 8–16km wide.
• Within these bands, further reconnaissance-type searching may result in the selection of corridors D, E
and F, each perhaps 3–8km wide.
Page 7 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
• A comparison of these corridors may then suggest that E will provide the best route, and Route G is then
generated within it; typically, this route could be 1–1.5km wide in a rural locale.
• The next, preliminary location, step is to search this route and locate within it (not shown in Fig. 1) one
or more feasible alignments, each perhaps 30m wide and containing relatively minor design differences.
• These alignments are then compared during the final location phase of the analysis, and the most suitable
one is selected for structural design and construction purposes.
• Select the road type, the number of lanes needed to carry the traffic load, and the level of service to be
provided to road users
• Establish one or more preliminary routes that meet desire-line needs, and sketch preliminary designs,
including interchange and flyover locations
• Assign traffic to one or more of the selected routes to determine design traffic volumes
• Adjust routes and complete preliminary plans for major alternative road locations
• Compare alternative locations using cost, environmental, road user benefit, and social analyses and select
the preferred one(s) for public consultation.
• Note:
• The number of alternative road locations available for consideration in a built-up area are normally fairly
limited. The town is an established entity and it is only in run-down areas (such as alongside old railway
lines) and on the very outskirts that relatively low-cost land may be available.
• The existing streets are fixed in location and size by the natural topography and by the buildings that they
service.
• Thus, the location of a new major road or the substantial upgrading of an existing one must inevitably
result in changes to portions of the established city culture which, in turn, has many direct and indirect
impacts upon owners and users of the affected urban infrastructure.
Page 9 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
Page 10 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
• Once the final location of the highway system is determined, it is then necessary
to provide the plans and specifications for the facility.
• The plans and specifications of a highway are the instructions under which the highway is constructed.
• They are also used for the preparation of engineers’ estimates and contractors’ bids.
• When a contract is let out for the construction of a highway, the plans and specifications are part of the
contract documents and are therefore considered legal documents.
• The plans are drawings that contain all details necessary for proper construction, whereas the
specifications give written instructions on quality and type of materials and methods of construction.
Determination of levels
One of the major purposes of the longitudinal section and cross section diagrams is to show the proposed levels or heights at
which a road is to be constructed and also the existing levels of the ground. It is therefore of the utmost importance than the
road constructor ensures that the road is constructed at the correct height or level.
Setting out
The Surveyor must set out the levels for the road construction using the following
procedures:
1. Place two reference pegs at each chainage peg, one on each side of the road at the right angles to the centre line and at a
fixed distance of 1,5metres behind the edge of black top. All reference pegs at both horizontal and vertical curves as well as
at any change of grade to be concreted in.
2. Place a gum pole or fencing standard at about 200mm behind each reference peg.
Page 11 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
3. After all the reference pegs and poles have been placed, the level of each reference peg must be determined by the Surveyor
by levelling from a benchmark with Surveyor`s level. Forward and return levelling must be done to eliminate errors in
levelling.
4. Levels one metre higher than the final centre line, quarter point, and gutter levels at each particular chainage are marked
on each gum pole as follows:
Cambered road
Alternatively, the levels determined in (c) may be marked on the pole directly using the surveyor`s level.
(f) A nail should be knocked into the pole at each pencil mark to provide a more
permanent reference.
g) Calculate the levels of the imaginary points p and q (see figure 5.9 and model calculation)
Page 12 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
h) Calculate the level of P1 and Q1 by adding 1 metre to the level of p and q.
i) The levels of the reference pegs are already known from previous levelling (see point 3
above)
j) The difference in height between the levels of the tops of the pegs and the levels of P1 and Q1 are obtained by subtracting
(i) from (h).
k) The levels of P1 and Q1 are then marked in pencil and the poles using the method
described in (e) and nails are knocked into the poles at these points.
Therefore, ap = qb = 0,073 m
To calculate P1 and Q1
Page 13 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
4. If, say, the subgrade level at the centre line is required to be set out on a cambered road, the string is stretched between
points A1 on opposite poles and the gauge rod is held at the centre line with the subgrade mark against the string. The bottom
of the rod will then be at the proposed subgrade level. If the subgrade level at the gutter line is required, the string is stretched
between points C1 on the poles and the gauge rod is held at the gutter line position with the sub-grade mark against the string.
The bottom of the rod will again denote the subgrade level at that point.
The subgrade level at the quarter point can similarly be found by stretching the string between point B1 and holding the
gauge with the subgrade mark against the string
Similarly, if the sub-base, base course or surface level is required, the gauge rod is held
with the sub-base, base course or surface mark against the string.
Page 14 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
Page 15 of 16
Highway Engineering – CEC 413 | Engr. A. M. Sani
Page 16 of 16