Professional Documents
Culture Documents
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
1. Define pavement roughness, how to quantify? What are the two classes
of equipment’s used to measure roughness?
Answers:
Pavement roughness is an expression of irregularities in the pavement surface that
adversely affect not only ride quality but also vehicle operation cost, fuel
consumption and maintenance costs. RI is a standard quantitative roughness
measure developed at the international road roughness experiment healed in Brazil
in 1982 under the sponsorship of the World Bank.
- pot-hole patching
- crack sealing
- filling depressions
Routine maintenance: it’s a group of activities that aims at keeping the road safe
through daily examination by the road control officials on both sides. From economical
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
viewpoint, routine maintenance must be interested to prolong the roads life and avoid
the necessity for recurrent maintenance or reconstruction. The activities may include
some immediate and proactive measures.
The activities to be done in routine maintenance are:
- Removal of all obstacles
- The cleaning of the road surface, the mediate, the shoulders, ans
sides road.
- Filling a pot-hole
- Edge patching
- Shoulder repair
An example that can influence equipment selection soil encountered. The compaction of
clayey soil is done best with a sheep’s foot roller, whereas more sandy soil is best
compacted with a vibratory roller. Physical constraints on site refer to site area and
layout, surface condition, topography, and adjacent neighborhood.
The nature of the work: Some factors relating to the nature of the work include
payload, the total quantity of work, and the construction schedule. Payload has a
direct relation to the capacity of the equipment selected. For example, the
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
particular crane selected must be able to lift the maximum load the work may
require. A higher quantity of work can influence and justify the selection of
higher capacity equipment. Although higher capacity equipment has higher
mobilization and rental costs, the per-unit production costs are lower
i. Quantity of work
Using construction equipment is productive for large project relative to small project.
Using labour for small project is more economical and productive than using
construction equipment.
Earthwork rates for machines are invariably higher than corresponding rates through
manual labor
Tasks which are too heavy or too delicate for human muscles to do can be done
manually or to do them more economically and much faster.
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
iii. Cost
Using construction equipment reduce the overall construction costs especially for large
contracts
o Using labour will increase economic condition of workers and Increase the
circulation of the money and the per capital income of the worker
o By using equipment increasing rate of output through work progress with the
best effective and efficient methods
v. Labor availability
In developing country like Ethiopia especially in rural area there is large human
resource. So using labour for small project is more economical and productive than
using construction equipment.
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
Ruts caused by studded tire wear present the same problem as the ruts described here,
but they are actually a result of mechanical dislodging due to wear and not pavement
deformation.
The proactive measures to prevent the occurrence of such defects:
Wooden sheets, battens, plywood, fiber hard board, steel plates, angles, rope etc are
generally use for form work.
Before using formwork, it should free from all type material like as dust, cement.
To placing the concrete in appropriate depth used 2.5-5cm thick and 3m long
wooden sheeting
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
If the base of the road is dry or construction is taken place during summer seasons, then
watering is done using the sprinkling process, after this concrete should be placed.
3) Construction of joints
There are three basic joint types used in concrete pavement: contraction,
construction and isolation.
Except for some isolation joints, all joints provide a means to mechanically
connect slabs. The connection helps to spread a load applied on one slab onto
slabs along its perimeter.
Mixer is equipment that mixes the concrete using distinct amount of cement, concrete,
sand and water. There are two type of mixer generally used during construction,
If distance is more from site, mix concrete transported at site within setting time.
4) Placing of concrete
Two methods generally used in placing of concrete-
1- Alternate bay method-
Placed the concrete on both side of road alternatively like as 1, 3, 5…part at one side
and 2,4,6… part other side, This method have slow process due to road traffic problems,
2- Continuous bay method-
Construct one side of road regularly, after construction of some part of first side than
construct other side, this method have fast process without no obstruction of traffic
5) Compaction of concrete
Purpose of compaction is that to pull out air from void and make concrete harden.
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
After this, Floating, Belting, Screeding or Strike off, Bull floating and Brooming is
done as per requirement for the finishing purpose of concrete pavement to
smoothen the top surface.
6) Curing
After completion of the finishing operations, the surface of pavement shall be entirely
covered with wet hessian cloth, burlap or jute mats
Curing is the process of increasing the hydration of cement, after setting the concrete
curing process done till 14-28 days.
7) Opening of the traffic
Generally after a month, road should be open to traffic, but if we used rapid hardening
cement it take 7 days to open traffic.
Construction materials used are as follows:
Cement
o Ordinary Portland cement (OPC)
Ordinary Portland cement and high strength ordinary Portland cement are most widely
used for concrete pavements.
o Rapid hardening Portland cement
In general, this cement would be used only where time is a critical factor and the road is
required to be opened to traffic at an earlier date than would be possible if ordinary
Portland cement or high strength ordinary Portland cement is used.
Aggregates
There are two types of aggregates are used during construction of road i.e. Fine
and Coarse aggregate depending on requirements.
Maximum size of aggregate should not exceed 1/4th of the pavement slab
thickness.
Water
Water used in mixing or curing of concrete shall be clean and free from injurious
amounts of oil, salt, acid, vegetable matter or other substances harmful to the
finished concrete.
ASTU
Pavement Evaluation and Rehabilitation Assignment Two
Equipment’s used
A list of tools, equipment and appliances required for the different phases of concrete
road construction is given below:
Mild steel sections and blocks for making joint grooves for finishing purpose
ASTU