Professional Documents
Culture Documents
www.alfanar.com
2
TABLE OF CONTENTS
1. Pre-Installation.................................................................................................................................................... 3
1.1 Introduction.............................................................................................................................................. 3
1.2 Pre-installation.......................................................................................................................................... 3
1.2.1 Cable Inspection.................................................................................................................................... 3
1.2.2 Cable Storage........................................................................................................................................ 3
1.2.3 Drum Handling...................................................................................................................................... 4
1.2.4 Prevention of Moisture Ingress............................................................................................................. 5
1.2.5 Pre-Installation Check List.................................................................................................................... 5
1.2.5.1 Code review........................................................................................................................................ 5
1.2.5.2 Cable inspection................................................................................................................................. 5
1.2.5.3 Cable storage...................................................................................................................................... 5
1.2.5.4 Cable handling.................................................................................................................................... 5
1.2.6 Route Survey......................................................................................................................................... 5
2 Installation........................................................................................................................................................... 6
2.1 Installation Temperature........................................................................................................................... 6
2.2 Equipment................................................................................................................................................ 7
2.2.1 Equipment check list............................................................................................................................. 7
2.2.2 Cable feed-in setups.............................................................................................................................. 8
2.3 Physical Limitations of Cables................................................................................................................. 9
2.3.1 Minimum installation radius................................................................................................................. 10
2.3.2 Maximum pulling tension..................................................................................................................... 10
2.3.2.1 Pulling eye attached to the conductor................................................................................................. 10
2.3.2.2 Cable grip over lead sheath................................................................................................................ 11
2.3.2.3 Cable grip over non-leaded cable....................................................................................................... 11
2.3.2.4 Check list prior to pulling cable......................................................................................................... 11
2.3.3 Sidewall pressure................................................................................................................................... 11
2.4 Laying Methods........................................................................................................................................ 12
2.4.1 Direct in the ground............................................................................................................................... 12
2.4.2 Underground tunnels or ducts............................................................................................................... 12
2.4.3 Cable tray.............................................................................................................................................. 13
2.4.3.1 Tray design......................................................................................................................................... 13
2.4.3.2 Tray system design............................................................................................................................. 13
2.4.3.3 Tray application.................................................................................................................................. 13
2.4.3.4 Tray load capacity.............................................................................................................................. 14
2.4.3.5 Cable tray installation......................................................................................................................... 14
2.4.4 Special laying........................................................................................................................................ 15
3 Splicing................................................................................................................................................................ 15
3.1 Solid Dielectric Insulated Cable............................................................................................................... 15
3.1.1 Removal of cable jacket and shield....................................................................................................... 15
3.1.2 Placing connectors................................................................................................................................. 16
3.1.3 Preparation of joint for insulation......................................................................................................... 16
3.1.4 Insulating the joint................................................................................................................................. 16
3.1.5 Shielding of the insulated joint.............................................................................................................. 17
3.1.6 Protective covering................................................................................................................................ 17
3.2 Lead Sheathed Cable................................................................................................................................ 17
3.2.1 Removal of the sheath........................................................................................................................... 17
3.2.2 Making the lead joint............................................................................................................................. 17
4 Terminating.......................................................................................................................................................... 18
4.1 Cable Preparation..................................................................................................................................... 18
4.2 Installation of Terminations...................................................................................................................... 18
Pre-Installation
4
1
1 - PRE-INSTALLATION
1.1 Introduction
This manual provides installation methods commonly encountered in industrial, commercial and electric power utility
applications and should be used in conjunction with the engineer’s installation specifications and all applicable codes.
These methods are recommended for all types of power and control cables. This manual is intended for use by the design
engineer and the installer in the field. The information provided is concise and should be adequate for the majority of
installations.
1.2 Pre-installation
To ensure safety during cable installation and reliability once the cable is installed, you should confirm the following
prior to installation.
Review all applicable local, state, provincial, and national codes to verify that the cable selected is appropriate for the
installation job.
Any existing cable damage must be identified and any further damage prevented from occurring. This is done through
proper cable inspection, handling and storage.
YES NO
Cradle both reel flanges between forks Do not lift by top flange. Cable
or reel will be damaged
Reels can be hoisted with a shaft Use a spreader bar to prevent bending
extended through both flanges the reel flanges and mashing the cable
Place spacers under the bottom flange and Upended heavy reels will often
between reels to create a space to insert the forks arrive damaged. Refuse or receive subject
to inspection for hidden damage
Lower reels from truck using hydraulic gate, Never allow forks to touch cable
hoist or fork lift. LOWER CAREFULLY. surface or reel wrap
6
1.2.4 Prevention of Moisture Ingress
Care should be exercised during installation to avoid any damage to cable coverings. This is important in wet or other
harsh environments. The protective end cap should not be removed from the ends of the cable until immediately prior
to termination or jointing, especially for cables that do not have extruded bedding. When the caps have been removed,
the unprotected ends of the cable should not be exposed to moisture.
One of the objectives of the pre-survey is to determine where each reel of fiber optic cable is to be placed. Slack locations
and cable storage requirements must also be considered along with splice locations. The pre-survey will verify construction
methods, special tools required, or possibly require a revision of preliminary splice locations.
The characteristic of the ground along the route needs to be investigated. If a subsurface investigation seems to be required,
it should be conducted. This will clear up any concerns about underground conditions that may be encountered during
installation.
All road crossings, creek crossings, etc. need to be addressed so that preparatory work can begin before cable laying.
This will identify what type of preparatory work will be required to negotiate these crossing points. A good pre-survey
and proper planning will preclude reel ends falling too close to roads, creeks, or any other undesirable locations.
Installation
8
2
2 - INSTALLATION
A high percentage of cable failures are due to mechanical damage, which typically occurs during transportation, handling
and installation.
In fact, most cables are subjected to more mechanical stress during installation than they ever experience in actual
operation. Needless to say, handling and installing the cable according to the manufacturer’s recommendations is extremely
important.
When cables are installed in a raceway, underground electrical duct or cable tray, the following factors must be considered:
• Conductor configuration
• Raceway or cable tray fill
• Physical limitations of cables
• Installation equipment
• Ambient temperature and conditions
Similarly, when cable is installed as exposed wiring or as messenger-supported wiring, all of the above factors except
raceway or cable tray fill must be considered as well as the requirements for securing and supporting the cables.
2.2. Equipment
The proper use of appropriate equipment is crucial to a successful cable installation. The equipment recommended for
a variety of installations is listed in the following checklist and the appropriate equipment should be selected for the
particular installation requirements.
Guide-in Tube
PROPER IMPROPER
10
Single Sheave Sheave Assembly
Single sheaves should only be used for GUIDING cables. Arrange multiple blocks to maintain bending radii whenever cable
changes direction or elevation. For pulling around bends, use conveyor sheave assemblies of the appropriate radius series.
The pulleys must be positioned to ensure that the effective curvature is smooth and changes direction or elevation
evenly at each pulley. Never allow a polygon curvature to occur as shown in the below figure.
The fit of the pulley around the cable is also important when pulling heavy weights (e.g. pulleys at the top of a vertical drop).
NEVER ALLOW
Radius
Remember to use the radius of the surface over which the cable is bent, not the outside flange diameter of the pulley.
A “10 inch” cable sheave typically has a 10 in. outside flange diameter with a 6 in. inside diameter that provides an
inside (bending) radius of 3 in.
• Calculate and do not exceed the maximum pulling tension, maximum sidewall bearing pressure or the minimum
bending radius.
• Verify that the raceway or cable tray system is completely installed prior to cable installation and that the wiring
space is adequate.
• Train the cable to avoid dragging it on the edge of the raceway or cable tray.
• When using a basket grip, it must be securely fastened to the cable. Once the cable is installed, cut the cable behind
the location of the basket grip.
• The elongation characteristics of the pull rope should provide a constant and smooth pulling tension.
• Pull no faster than 40 ft (12 m) per minute.
• Pull with a capstan, whenever possible.
• Do not stop a pull unless absolutely necessary.
• Never pull the middle of the cable.
• Seal the cable ends of cable with an end seal with mastic coating inside.
2.3.1 Minimum installation radius
Single-Core Cables
15 Ø 20 Ø
- Unarmoured
15 Ø 15 Ø
- Armoured
Multi-Core Cables
12 Ø 20 Ø
- Unarmoured
12 Ø 15 Ø
- Armoured
Wherever possible, larger installation radius should be used, except that the minimum bending radius where the cables
are placed in position adjacent to joints and terminations may be reduced to that given in the below table, provided that
the bending is carefully controlled, e.g. by the use of a former.
Single-Core Cables
8Ø 15 Ø
- Unarmoured
8Ø 12 Ø
- Armoured
Multi-Core Cables
6Ø 12 Ø
- Unarmoured
6Ø 10 Ø
- Armoured
Tm = 0.036 x n x Cm (Copper)
The maximum limitation for this calculation is 22240 N (2268 kgf) for single conductor (1/C) cables, and 44480 N
(4536 kgf) for multi core cables. This limitation is due to unequal distribution of tension forces when pulling multiple
conductors.
When the calculated pulling tension is close to (or within 10 % of) the maximum pulling tension, the use of a tension
gauge during the pulling is recommended.
12
2.3.2.2 Cable grip over lead sheath
The maximum pulling tension on the lead sheath should not exceed 10.33 N/mm2 (1500 lbf/in2).
Where
The normal maximum sidewall pressure per meter (foot) of radius is as given below. However, in order to minimize
cable damage because of excessive sidewall pressure, the installer should check the proper recommendations for each
type of cables to be installed.
operator
pulling wire
pulling eye
roller or caterpillar
telephone cable drum
telephone tension meter cable drum
caterpillar
tension meter
power cable for caterpillar
caterpillar
operator
operator
pulling wire
pulling wire
pulling eye
trough, if necessary
pulling eye roller or caterpillar
roller or caterpillar
1. The casetelephone
of main underground transmission
trough, if necessary
cable drum line where the number of cables is many or expected to be increased in
the near future.
control panel caterpillar
2. The case of hard pavement or where hard pavement will be constructed in future.
3. Where digging is difficult due to heavy traffic.
operator
telephone
control panel caterpillar
cable drum Fig. 2 Cable Layig at Duct Manhole
Tunnel roller or caterpillar
Manhole control panel caterpillar cable
pulling eye
operator
operator
pulling wire
pulling wire
pulling wire
power cable for caterpillar
operator
pulling wire
operator pulling eye
operator
Manhole Duct
cable Manhole
Manhole Duct
cable Manhole tension meter
tension meter
pulling wire
pulling eye
pulling wire
pulling eye
14
2.4.3 Cable tray
2.4.3.1 Tray design
a. Cable tray design should be based upon the required loading and the maximum spacing between supports. Loading
calculations should include the static weight of cables and a concentrated load of 890 N (200 lb) at midspan. The
tray load factor (safety factor) should be at least 1.5 based on collapse of the tray when supported as a simple beam.
b. When the ladder-type tray is specified, rung spacing should be a nominal 22.9 cm (9 in). For horizontal elbows, rung
spacing should be maintained at the center line.
c. Design should minimize the possibility of the accumulation of fluids and debris on covers or in trays.
• Dropouts
a. Drop-out fittings should be provided when it is required to maintain the minimum cable bending radius.
b. Where conduit is attached to the tray to carry exiting cable, the conduit should be rigidly clamped to the side rail.
When conduit is rigidly clamped, consideration should be given to the forces at the connection during dynamic (seismic)
loading of the tray and conduit system. Conduit connections through the tray bottom or side rail should be avoided.
• Covers
a. Horizontal trays exposed to falling objects or to the accumulation of debris should have covers.
b. Covers should be provided on exposed vertical tray risers at floor levels and other locations where possible physical
damage to the cables could occur.
c. Where covers are used on trays containing power cables, consideration should be given to ventilation requirements and
cable Ampacity derating.
• Grounding
Cable tray systems should be electrically continuous and solidly grounded. When cable trays are used as raceways for
solidly grounded or low-impedance grounded power systems, consideration should be given to the tray system Ampa-
city as a conductor. Inadequate Ampacity or discontinuities in the tray system may require that a ground conductor be
attached to and run parallel with the tray, or that a ground strap be added across the discontinuities or expansion fittings.
The ground conductor may be either bare, coated, or insulated, depending upon metallic compatibility.
• Identification
Cable tray sections should be permanently identified with the tray section number as required by the drawings or construction
specifications.
• Supports
The type and spacing of cable tray supports will depend on the loads. Tray sections should be supported near section
ends and at fittings such as tees, crosses, and elbows.
• Location
Trays should not be installed in proximity to heating pipes and other heat sources.
16
Splicing
3
3 - SPLICING
These general guidelines are offered for splicing cables 6 kV and higher. However, because of the variety of cables
and methods of splicing, they are not intended as a detailed set of instructions. Most contracting companies have in-
structions for specific cable constructions and the type of splice being used, and these instructions are to be followed.
There are many different splices available, such as: pre-molded rubber, heat shrink, cold shrink, resin, and tape. This
section will cover the basic requirements for splicing insulated copper or aluminum conductors up to 69 kV (using
any of the above methods): shielded and non-shielded; single and three conductor; thermoset, thermoplastic, or paper
insulated; lead, thermoset, or thermoplastic covered and/or jacketed.
The objective is to make a joint in a power cable that is electrically equivalent to the cable. To achieve this objective,
the following conditions are necessary to properly prepare the cable and install the joint:
a. Tools should be in first class condition—clean, dry and sharp.
b. Strict adherence to instructions, dimensions, cleanliness, and freedom from contamination are to be followed.
c. The materials used in the fabrication of the joint must be compatible with the cable materials and be new and clean.
d. The materials used for re-jacketing the splice should be suitable for the environment.
18
c. If a tape method is used to insulate the joint, the manufacturer’s instructions should be followed. The conductor
shield will be installed over the connector and slightly onto the pencil, using semiconducting tape. Apply the
semiconducting tape as smoothly as possible so there are no abrupt dimensional changes. Over this use high-voltage
insulating rubber tape. Stretch the tape to a minimum of 80% of its original width while wrapping with smooth half-lapped
layers. Continue installing the tape to the dimensions as specified by the manufacturer.
20
4
4 - TERMINATING
Cable terminations are required when connecting insulated shielded power cables to other conductors such as a bus
bar or un-insulated overhead lines. When a shielded power cable is ended or terminated, and the outer cable shield is
stopped on the cable insulation, there is a very high concentration of stress at this point. These terminations must contain
a method of controlling this high stress (stress cone or stress grading material), an outer non-tracking surface, and
a means of providing an environmental seal to prevent moisture ingress. There are many different types of terminations
available, such as pre-molded rubber, heat shrink, cold shrink, and tape.
For non-shielded cable, environmental sealing of the connector to the jacket is advantageous to keep out water, and an
outer insulating non-tracking covering will minimize the possibility of a failure due to surface discharge.
These general guidelines are offered for terminating cables. However, because of the variety of cables and methods of
terminating, they are not intended as a detailed set of instructions. Most manufacturers have instructions for specific
cable constructions and the type of termination being used, and these instructions are to be followed.
The objective is to make a termination in a power cable that is electrically equivalent to the cable. To achieve this
objective, the following conditions are necessary to properly install the cable and the termination:
a. Tools are to be in first class condition clean, dry and sharp.
b. Strict adherence to instructions, dimensions, cleanliness, and freedom from contamination are to be followed.
c. The materials used in the fabrication of the termination must be compatible with the cable materials and be new and clean.
22
For catalogue soft copy scan QR code MKT_120342_Cables Instl_Oct19_01
www.alfanar.com