Assembly Shed Qoutation
Assembly Shed Qoutation
Sir:
We are pleased to submit to you our proposal with complete supply of materials,
labor , equipment and supervision for the completion of the above project
based on the given plans and specification .
II SITEWORKS
Excavation 44.78 cum 1,000.00 P 44,780.00
Backfill & Compaction 36.86 cum 350.00 12,901.00
Hauling and Disposal 7.92 cum 500.00 3,960.00
Gravel Bed & Compaction 3.26 cum 1,000.00 3,260.00
Sub- Total P 64,901.00
III REBARS
10mmǿ 700.76 kgs 98.00 P 68,674.48
12mmǿ 402.79 kgs 98.00 39,473.42
16mmǿ 1,182.40 kgs 98.00 115,875.20
Tie Wires Ga.16 1.00 rolls 3,000.00 3,000.00
Sub- Total P 227,023.10
VI STEEL WORKS
Steel columns , 39 units 7,873.10 kgs 90.00 P 708,579.00
Steel Roof Framing 16,151.00 kgs 90.00 1,453,590.00
Sub- Total P 2,162,169.00
Sub- Total
**GRAND TOTAL COST ** P 2,678,723.10
TERMS OF PAYMENT:
30% Down payment
70% Progress Billing
Respectfully yours,
JOHN WICK