You are on page 1of 6

Olise Henry George

Doha Qatar
Mob. +974- 77069673
Email: Henrygeorger201@engineer.com
Email: Henrygeorger5030@gmail.com

Senior Planning/Project Control & EOT-Claims Specialist

A competitive professional putting forth an experience of over GCC 10 years’ experience in the Construction
and Engineering industry. Outstanding personnel and project management abilities with a proven record of
accomplishment in handling high-profile projects. Excellent communication skills with splendid knowledge in
the areas of Primavera Version 3 to Primavera Release 16.1, Project Controls, Planning and Budget Costs,
Invoicing & Invoicing Plan towards Baseline program look-ahead planned Activities in Engineering
Procurement, Fabrication and Construction. Proven history in utilizing a fact-based, process-oriented
approach towards reaching goals in support of cost and profit. Service and organizational objectives identify
loopholes ahead in construction timeline, create Innovative and exceptional ideas for possibilities towards a
result-oriented direction. Driven by new challenges which improves awareness and professional capability

KEY SKILLS
 Project Scope of work decomposition and WBS  Kickoff Meeting/ Project Invoicing plan &
Preparation and baseline Execution programs Contractual Values/Cost Control & Budgeting
plan
 Time Impact Project Management Delay  Oracle P6 Usage & Excel/Power Point
Analysis Presentations,
For EOT-Claim’s preparation

 Execution Program Baselining /Revisions

 Detailed Site Weekly & Monthly reports

 Assets Capitalization (Oil & Gas)

 Project Dashboard Updating with Monthly Look


ahead programs

 EVM Monthly (Earned Value Management)

 Design Review meetings & MOM Documentation

 Lean Construction and Recycling procedures to


avoid waste during construction (Material, Cost
& time)

Page 1 of 6
QUALIFICATION

• Bachelors in Business Management –Delta State University (2008)


(Bachelor’s Degree -2nd Class Upper)

• Diploma in Business Management –Delta State University(2006)

• Secondary School College Certificate –Delta State (2001)

PROFESSIONAL QUALIFICATION
Madras Management Training Institute Doha Qatar &
Chicago Training Center Doha Qatar

• Planning Tools-Primavera P6.16 Version (Certified)- MMTI-Institute Qatar

• Project Advanced Scheduling Program- (PSP)- MMTI-Institute Qatar

• Cost Engineering Professional (CEP)-MMTI-Institute Qatar

• Resource Management & Cost Loading-Chicago Training Center

• Contract Management (CMP)-Chicago Training Center

• Project Management Professional (PMP)- Famous-Institute of Management Qatar

• IOSH (Managing Safely)-RCS Institute D-ring Qatar • 132 Occupational Safety and Health
Professional

WORK EXPERIENCE

 Company : QSP-Qatar Site & Power (Main Contractor)


 Client : Ooredoo Qatar
 Project : Ooredoo & Google-Design & Built Data Center Messamier Doha Qatar
 Consultant : QDC-Qatar Design Consortium
 Position Held : Senior Planning Engineer (QSP-Main Contractor)

Page 2 of 6
 Duration : From 2020-Till Date

 Company : AL AALI INTERNATION (Main Contractor)


 Client : MOI Qatar
 Project : Construction of New Headquarters of General Directorate for borders, Passport.
Expatriate Affairs & Nationalities Travel Document (Civil, MEP & landscaping Irrigation Works)
 Consultant : CEG International
 Position Held : Senior Planning Engineer (Main Contractor)
 Duration : From 2019-Till 2020

 Responsibilities

• Execution Program Baseline Preparation for the project & Sub-contractors


• Logical Methodology Sequence of activity for Baseline Program proper Scope of work decomposition,
Defining project WBS & milestones and possible Constraints,
• Weekly & Monthly progress report & Dashboard updates with look-ahead checklist program with site
Engineers
• Weekly Progress Meeting with Consultant & Client discussing project delays and possible
constraints
• Forecast Monthly Invoicing Plan / Cash flow as per Look-Ahead monthly monitoring program
• Time impact delay analysis for EOT Claims preparation, showing the link properly narrating
the impacted activities and their predecessors as planned with proper backup documents in
relation to the causes of delay
• Comparing Sub-Contractors Actual updates to their approved baseline for proper progress
work monitoring
• Recourse & Cost Loading when necessary, generating S-curve and Manpower Histogram for
approved Baseline Program
• Monthly Earned Value Management (EVM )

 Company : AYTB-Al Yur Townsend & Bottom Qatar


 Client : Qatar Petroleum
 Project : Construction of Catchment & Drain Pit, Pig Launcher, Civil, Mechanical, Electrical &
Instrumentation work Duhkan Field 8 stations
 Position Held : Senior Planning Engineer
 Duration : From 2016-2019

 Responsibilities

Page 3 of 6
• Execution Program for tender preparation & Budgeting with detailed awareness of
Contract invoicing & Claim’s procedures
• Logical Methodology Sequence of activity for Baseline Program proper Scope of work decomposition,
Defining project milestones & possible Constraints,
• Weekly & Monthly progress report & Dashboard updates with look-ahead checklist program
• Monthly Invoicing as per monthly performance percentages Progress Cumulative
• Forecast Monthly Invoicing Plan / Cash flow as per Look-Ahead monthly monitoring program
• Recourse & Cost Loading when necessary, generating S-curve and Manpower Histogram for
approved Baseline Program
• Monthly Earned Value Management (EVM)
• Assets Capitalization for close out contract and documentation (Oil & Gas sector)
• Under Consultant--Review Baseline program for contractors and make necessary comments
when needs be
• Time Impact Delay Analysis/EOT Claims preparation with all necessary backup documents
and a proper well- d e f i n e d Mitigation Plan for Baseline recovery
• Good Communication skills with site Engineers, self-motivated, trustworthy and very reliable. Can
work quietly together with client and other contract representatives as part of a group

 Company : MegaTech Electromechanical Company W.L.L


 Client : Ministry Of Education-Qatar University
 Main Contractor : Aldawish Engineering W.L.L
 Project : Design & Build, Mechanical, Electrical & Plumbing Work New College Of Education
 Position Held : Planning / Invoicing Engineer
 Duration : From 2014-2016

 Responsibilities

• Preparation of Execution Program & Budgeting with detailed awareness of


Contract invoicing & Claim’s procedures
• Logical Methodology Sequence of activity for Baseline Program proper monitoring,
Defining project milestones & Constraints,
• Weekly & Monthly progress presentation updates with look-ahead checklist program
• Monthly Invoicing as per monthly performance percentages Progress Cumulative
• Forecast Monthly Invoicing Plan as per Look-Ahead monthly monitoring program
• Recourse & Cost Loading when necessary, generating S-curve and Manpower Histogram for
the Baseline Program and monthly cash Flows

Page 4 of 6
• Under Consultant--Review & integrate Baseline program for contractors
• EOT Claims preparation with all necessary backup documents delay Analysis and a proper
well- d e f i n e d Mitigation Plan
• Monthly Earned Value Management (EVM)
• Baseline Recovery

 Company : Black Arrow Security System Integration & Services


 Position Held : Planning Engineer
 Duration : From 2012 - 2014
 Project-1 : Physical Security System & total Access Control installations-Aljazeera Bin-
Omran
 Client : Al-Jazeera Media Network House Qatar

 Responsibilities

• Execution Program for tender preparation & Budgeting with detailed awareness of
Contract invoicing & Claim’s procedures
• Logical Methodology Sequence of activity for Baseline Program proper Scope of work decomposition,
Defining project milestones & possible Constraints,
• Weekly & Monthly progress report & Dashboard updates with look-ahead checklist program
• Monthly Invoicing as per monthly performance percentages Progress Cumulative
• Forecast Monthly Invoicing Plan / Cash flow as per Look-Ahead monthly monitoring program
• Recourse & Cost Loading when necessary, generating S-curve and Manpower Histogram for
approved Baseline Program
• Time Impact Delay Analysis/EOT Claims preparation with all necessary backup documents
and a proper well- d e f i n e d Mitigation Plan for Baseline recovery
• Under Consultant--Review Baseline program for contractors and make comments when needs
be
• EOT Claims preparation with all necessary backup documents and a proper well- d e f i n e d
Mitigation Plan
• Baseline Recovery

PERSONAL DETAILS

Current Location: - Doha Qatar


Age: – 38 years
Marital Status: - Married
Nationality: -Nigerian

Page 5 of 6
Cell: - +974 55956105
Visa Status: - Resident Permit
Transferable Working Visa
Proven Record referees : On Request

Page 6 of 6