You are on page 1of 17

PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 1 of 16

Project: Expansion of IWTP-8 Stage-4

P.O. # 7200040907

METHOD STATEMENT
FOR INSTALLATION AND JOINING OF
CPVC & PVC/uPVC PIPES

Document No. 7200040907-JWWF-MCMS-06 Rev. 00

OWNER / CLIENT: MARAFIQ

PMC: ILF CONSULTING ENGINEERS

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO. (CJSC)

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 2 of 16

TABLE OF CONTENTS
SECTION DESCRIPTION PAGE
1.0 PROJECT DESCRIPTION 3

1.1 PURPOSE AND SCOPE 3

2.0 REFERENCES AND STANDARDS 3

3.0 ACRONYMS, ABBREVIATIONS & DEFINITIONS 4


4.0 RESOURCES AND MANPOWER 4
5.0 RESPONSIBILITIES OF KEY PERSONNEL 5

6.0 WORK PROCEDURE 7

7.0 HSE REQUIREMENTS 14

8.0 DOCUMENTS AND PLANNING 16

9.0 PLANT & EQUIPMENT 16

10.0 QUALITY CONTROL AND ASSURANCE 16

11.0 TRAINING 16

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 3 of 16

1.0 PROJECT DESCRIPTION


MARAFIQ is a Power & Water Utility Company for Jubail and Yanbu, desires to expand IWTP-8 which will be called
Stage-4 with treatment capacity of 125,000m3/day. The plant will be designed to have layout for future Re-use treatment
plant that will further treat 80,000 m3/day of IWTP-8 Stage-4 effluent to meet Demineralization Feed water quality.

The Expansion project contract is based on a Design, Build and Operate (DBO) concept broken down into an
Engineering, Procurement and Construction (EPC) part and an Operation and Maintenance (O&M) part. The EPC project
duration will be for 36 months from Commencement Date, while the O&M period of the contract will be for 5 years from
Initial Acceptance of the Works from MARAFIQ.

For further details, refer Document No. MSCF-1-PC-057 Attachment D EPC Scope of Work of Contract

The SSEM will provide design and construction drawings, supervision of work, labor, construction plant and equipment,
materials, tools, Quality control and coordination to execute the works in accordance with the relevant design drawings,
Standards and specifications.

1.1 PURPOSE AND SCOPE

The main purpose of this documents is to elaborate the best practices for the installation and joining of CPVC &
PVC/uPVC PIPES underground and above ground piping. This method of statement is applicable to all CPVC and
PVC/uPVC pipe diameters. The purpose of this method statement is to describe the procedure and methodology to be
adopted as a part of UPVC Underground and above ground drainage pipes & fittings installation for the Construction of
Expansion of IWTP-8 Stage-4 DBO. This document should be read in conjunction with the Project Quality Plan and
Contract Specifications

2.0 REFERENCES AND STANDARDS

All work done in the scope of contractor will be executed in accordance, but not limited to the following industry
engineering standards. Where specifications are not clear or covered by these documents the client will be informed and
applicable documents will be provided by the client in order to have clarity on requirements that shall be implemented.

Industry Engineering Codes and Standards:

ASME B31.3 CHEMICAL PLANT & PETROLEUM REFINERY PIPING


AWWA C901-08 POLYETHYLENE (PE) PRESSURE PIPING AND TUBING Y, IN. (13 mm)
AWWA C906-15 PE PRESSURE PIPE AND FITTINGS, 4 In. Through 65 In.
(100 mm THROUGH 1,650 mm) for Waterworks
ASTM 02321 UNERGROUND INSTALLATION OF FLEXIBLE THERMOPLASTIC SEWER PIPE
ASTM 02564 SOLVENT CEMENT FOR PVC PLASTIC PIPE AND FITTINGS
ASTM 02855 SOLVENT CEMENTED JOINTS WITH PVC PIPE AND FITTINGS
ASTM F493 SOLVENT CEMENT FOR CPVC PLASTIC PIPE AND FITTINGS
ASTM F585 INSERTION OF FLEXIBLE POLYETHYLENE PIPE INTO EXISTING SEWERS
ROYAL COMMISSSION GUIDELINES SPECIFICATIONS AS BELOW -
SECTION 02085 GUIDELINE SPECIFICATION FOR UNDERGROUND PIPING MATERIALS
RC SECTION 02530 GUIDELINE SPECIFICATION FOR SANITARY SEWARAGE
RC SECTION 15110 GUIDELINE SPECIFICATION FOR VALVES
RC SECTION 15195 GUIDELINE SPECIFICATION FOR TESTING OF PIPING
3.0 ACRONYMS, ABBREVIATIONS AND DEFINITIONS

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 4 of 16

3.1 ACRONYMS, ABBREVIATIONS

SSEM Saudi Services for Electro Mechanic Works Co. (Closed Joint Stock Company)
PMC Project Management Consultant
ISO International Organization for Standardization
OEM Original Equipment Manufacturer
EPC Engineering, Procurement and Construction
O&M Operation & Maintenance
IFC Issue for Construction
PM Project Manager
CM Construction Manager
QMS Quality Management System
QA Quality Assurance
QC Quality Control
Contractor The main Contractor of Project
Sub-contractor Construction Sub-Contractor
ITP Inspection & Test Plan
RFI Request for Inspection
NCR Non-Conformance Report
HSE Health Safety and Environment
MSDS Material Safety Data Sheets
PPE Personal Protective Equipment
PTW Permit to Work
DN / PN Design Pressure / Nominal Pressure
MEP MECHANICAL, ELECTRICAL & PLUMBING

4.0 RESOURCES AND MANPOWER

The team members in all key positions, which require approval from the client, has been submitted
to the client for pre-approval or in approval stage. Positions not requiring approval from the client
will have the required qualified and experienced needed for their position in order to complete
their responsibilities successfully.

Should there is need to accelerate the progress and catch-up the project schedule SSEM sub-
contractors may be employed any time but would function as part of SSEM’s team. List of SSEM
sub contractors will be made available once their qualification is approved by the client and
mobilized to site.

Organization Chart

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 5 of 16

SSEM PM – Wael
Fathy

CONSTRUCTION MANAGER
AHMED IBRAHEEM
QA/QC MANAGER
MOHAMMED ISMAIL ELDEEB SAFETY MANAGER
NADJME

CIVIL LEAD ENGINEER /


QA / QC
MECHANICAL/ PIPING LEAD SITE ENGINEERS
SUPERVISOR / MUSAAB KHALID / HUSSAM,
ELECTRICAL/ INSTRUMENTATION
INSPECTOR ENGINEER / BENJAMIN, MAGDY, YAZAN, LEAD ENGINEER /
WALEED / AZHAR SITE ENGINEERS MUKHTAR SITE ENGINEERS
CAEMAR / ZAMAN TBA / ARIF MOHAMMAD TBA

MECHANICAL SUPERVISORS CIVIL SUPERVISORS ELECTRICAL SUPERVISORS

PTW COORDINATOR
TBA

SITE EXECUTION LEADMEN / SITE EXECUTION WORKERS


TBD

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 6 of 16

5.0 RESPONSIBILITIES OF KEY PERSONNEL

All actionable responsibilities mentioned in this section for each position will be responsible for
the tasks briefly state against each position.

5.1 CONSTRUCTION MANAGER


Shall be responsible for the site implementation of these procedures and to provide all the
resources from competent and trained manpower, tools, equipment and approved
materials. He shall coordinate with the Quality Control Inspector for inspections and
issuance of Request for Inspections (RFI). He shall be responsible for the safety of all
personnel working on these activities.

5.2 Site Mechanical Engineer


Shall be responsible for overall execution of works, and also responsible for
following all HSE and quality procedure.

5.3 QA/QC MANAGER


Managing the development and implementation of the QMS for planning, fabrication,
inspection, documentation, and operations activities including: Planning duties within the
QA/QC staff and related work schedules.

5.4 QA/QC Engineer


The QA/QC engineer will be responsible for the quality aspects of the works. He will ensure
that project QA and QC plan as per ITPs and other QA/QC documents are in accordance
with vendor procedures and other quality documents. The required (RFIs) will be submitted
to the MARAFIQ/ILF. He will proactively coordinate with the material engineer and issue
appropriate internal (Site Instructions) when he sees that performance of works deviate
from the approved method of statement or project and vendor specifications.

5.5 SAFETY MANAGER MANAGER


Shall be responsible for the implementation of all safety requirements and to ensure that
the works are undertaken in a safe and proper manner, all in accordance with
the approved Construction Phase HSE Plan, the approved method statement and the
approved Job Safety Analysis.
Ensure that the procedures and risk assessment are understood, complied and applied in
the worksite. Ensure that all workers are provided with enough/complete information
regarding workplace hazards and planned control measures.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 7 of 16

5.6 COORDINATOR
Responsible for taking all necessary steps to prepare, authorize, and issue the Permit to
Work after assessing the work and work site and/or area hazards and the controls to
address these hazards.

6.0 WORK PROCEDURE

6.1 Delivery, Storage, Handling & Preservation


• On site pipe storage shall meet all manufacturers' requirements.
• Solvent cement and primer for thermoplastic piping shall be stored in an airconditioned building with a
maximum temperature of 26.rC.
• Pipe and fittings shall be properly protected from impact, especially on their ends. They shall not be thrown,
dropped, bumped, hit, or dragged and pushed over abrasive surfaces.
• Adhesive and solvent cement containers shall be tightly closed when not in use, and shall be returned to
the storage facilities to minimize exposure to excessive temperatures.
• Transport individual pipe lengths to the job site on padded bunks with nylon tie-down straps or padded bonding to
protect the pipe.
• Protect the pipe from sharp objects.
• Anchor pipe securely to prevent slippage.
Store individual pipe lengths on earth berms or timber cradles in the numerical order of installation.
• Stack the heaviest series of pipe at the bottom. Do not stack pipe in excess of 20-rows high.
• Protect the pipe from stones and sharp objects.
• Store fittings in their original cartons.
• Lift pipes with handling beams or wide belt slings near the middle of joints as recommended by the pipe
manufacturer.
• Do not use cable slings, chains, or hooks.
• Before installation, check pipe and fittings for cuts, scratches, gouges, buckling, kinking, or splitting.
• Remove any pipe section containing defects by cutting out the damaged section in a complete cylinder.
• All the damaged pipe should be stored in quarantine area with identification mark.

For Preservation below actions shall be taken


• Solvent cement primer and adhesive containers shall be protected from direct sunlight.
• CPVC /PVC/uPVC pipes must be covered with suitable sheet or should be stored under shade in order to avoid
damage the material due to direct sun light.
• Material storage area should be visited and inspected all material on weekly basis.
• For long term storage, pipe racks should provide continues support, but if this is not possible, timber of at least
3in bearing width at spacing not greater than 2ft. centers for pipe sizes 160mm and above should be placed
beneath the pipes and at 1.5m centers at the side, if the stacks are rectangular.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 8 of 16

• For temporary storage in the field, where racks are not provided, the ground should be level and free from
loose stones. Pipes should not exceed three layer high and should be stacked to prevent.
• Stack heights should be reduced if pipe are nested, etc. .. pipes stored inside pipes of larger diameter.
Reduction in height should be proportional to the weight of the nested pipe compared to the weight of the
pipes normally contained in such stowage.
• Any primer, solvent cement, or adhesive that is beyond the stamped expiration date shall be discarded.
Solvent cement that has gelled or thickened shall be discarded. Leaking or opened containers shall also be
discarded.

6.2 Qualifications of Installers of Plastic Piping.

Each operator performing fusion joining shall be qualified in the use of the manufacturer's recommended fusion
procedure(s) by the following:

Appropriate training or experience in the use of the fusion procedure.

1. Making a sample joint according to the procedure that passes the following inspections and tests:
a) The joint shall be visually examined during and after joining and found to have the same appearance as a photograph
or sample of an acceptable joint that was joined in accordance with the procedure; and

b) The joint shall be tested or examined by 1 of the following methods:


• Pressure and tensile test
• Cut into at least 3 longitudinal straps, each of which is :
• Visually examined and found to be free of voids or unbonded areas on the cut surface of the joint, and
• Deformed bending, torque, or impact and if failure occurs, it must not initiate in the joint area.

2. Each operator shall be re-qualified under the procedure if during any 12month period:
a) Operator has not made any joints under the procedure; or
b) Operator has 3 points or 3% of the joints made, whichever is greater, that are found unacceptable by testing
according to same procedure.

6.3 JOINING METHOD/ ASSEMBLING PROCEDURE OF PVC I uPVC PIPES

6.3.1 TYPES OF JOINTS

There are two major types of joints, namely;

A. SOLVENT WELD JOINTS


B. RUBBER RING SEAL JOINTS

Installation of Thermoplastic Pipes i.e All PVC/uPVC/ CPVC pipe shall be assembled, and installed in accordance with
ASTM code, manufacturer's recommendations, and this procedure. Joints shall be made in accordance with ASTM 02855
for PVC and ASTM F493 for CPVC. Solvent cement shall conform to the following ASTM Designations:
ASTM 02564 for joining PVC to PVC, and ASTM F493 for joining CPVC to CPVC or PVC. Primer and solvent cement shall
be handled in accordance with the safety precautions in ASTM F402 for restrained type joints.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 9 of 16

Solvent cement shall not be used past the manufacturer's expiry date on the label or one year past the date of
manufacture if there is no expiry date specified.

A. Solvent Weld Joints.


- Cutting and Chamfering: Pipes should be cut square with proper marking around the pipe.
- Pipes end should be chamfered at an angle of approximately 15°C to about1/3 of the wall thickness with a coarse file,
chamfering tools.
- Pipes up to 75mm may be jointed easily with solvent adhesive and larger pipes required more special torniquets.
- Mark depth of entry of the size of the pipe into the socket and alignment mark. Roughen the outside of the pipe and
inside of the socket using sandpaper or emery cloth up to entry mark. Clean both surface and remove all dust &
grease using a dry clean cloth and cleaner.
- Apply adhesive without delay after cleaning. using a flat clean and proper brush, where loose fits are found, the pipe
should be given a second coat.
Immediately insert the pipe into the socket up to entry mark. align pipe and socket. Hold in position for a few second.
then wipe off excess cement.
- After the joint has been made. the piping shall not be moved until the drying time listed in Table of this Standard, has
elapsed. To limit movement of a pipe string, the first pipe shall be backfilled with the joint exposed.

Joint Drying Time before Movement Surface Temperature


Hot Weather Above 32 65"C Mild Weather Cold Weather Below 10"C

THROUGH NOMINAL PIPE SIZE


32 12 min 20 min 30 min
63 30 min 45 min 60 min
110 45 min 60 min 90 min
225 60 min 90 min 150 min

Note: These temperatures are pipe surface temperatures and are not air temperature limitations.

B. Rubber Ring Seal Joints


- Ensure that the spigot and socket are free from dust. grit, grease and as dry as possible. In hot climate joining is
recommended in early morning or in the evening to prevent expansion & contraction in excessive amount.

- Insert pipe into the socket without seal ring in place and mark pipe when it is fully inserted.

- Place seal in groove of socket ensuring that seal is correct way round. Rubber seal rings should be fitted with tapered
section facing the outside of the socket

- Apply jointing lubricant to the chamfer and the end of the spigot of the pipe or fitting only. Push the pipe firmly into
the socket up to the insertion mark previously made. If an expansion gap is requiring the pipe is then pulled back by
desired amount according the size.

- Jointing clamps may be used for ease of assembly.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 10 of 16

6.4 INSTALLATION & ASSEMBLING OF PVC/ uPVC / CPVC PIPES

• Field-fabricated, mitered fittings shall not be used.


• Thermoplastic flanges when used, shall be of flat face. Mating flanges of different approved material shall also
be of flat face. They shall be assembled with full-face elastomeric gaskets, 3 mm thick, and 50 to 60 Shore A
Durometer hardness.
• Flat washers shall be used under nuts and bolt heads on nonmetallic flanges.
• Plastic pipes such as PVC, UPVC, CPVC, PP. etc. shall be protected from contact with concrete by tape or
neoprene wrapping.
• At the edges where a thermoplastic pipe or fitting enters or leaves a thrust block, it shall be wrapped with
neoprene wrapping that will protrude slightly from the block.
• All changes of direction must be anchored. Concrete thrust blocks are suitable if require from design, but the
unit should only be hunched and a flexible membrane interposed between the concrete and the unit, to protect it
against damage by abrasion.
• The pipeline should be tested initially after a few joints to ensure that they have been made correctly, and
subsequently at convenient intervals, preferably not exceeding 1000 meters.
• Before testing, the line must be backfilled leaving the joints exposed. If the joints must be covered, it is useful to
mark their position.
• It is very important when laying uPVC pipes for gravity drainage to ensure that the pipe is laid in accordance
with the recommendations of the manufacturer.
6.5 Trench Preparation for underground piping

Following points should be considered during trench excavation


 Take necessary safety precautions to ensure a safe working environment.
 Prevent water penetration into the trench.
 During excavation, make sure that trench walls keep vertical position.
 for a flat bedding, remove all obstacles and sharp edges such as rocks, gravels, concrete, etc. from the
trench
 Remove all organic items such as plants, tree roots, etc. from trench ground.
 Ensure that trench ground is strong and stable.
 If the trench ground is not stable enough. increase trench depth for stabilization works.
 Discharge water (if there is any) from the trench before bedding preparation.
 When the underground water level is high, it might cause pipes to float. To prevent floatation, increase the
trench depth to increase the height of backfilling.
 Ensure that trench width is sufficient enough for bedding and backfilling com paction works.
 Ensure that excavated materials are piled at a distance from the trench to avoid the possibility of rolling back
into the trench

 Trench walls should be supported with sheet piles if the natural ground soil is unstable.
 the minimum trench width from the bottom to 300 mm above the top of the pipe shall be as shown in below
Table.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 11 of 16

TYPE OF PIPES NOMINAL PIPE SIZE (mm) MIN WIDTH OF TRENCH (mm)

THERMOPLASTIC 90 and under 300 mm


THERMOPLASTIC 110 and over OD +300

6.5.1 Preparation of Bedding

Trench bedding should be fattened, levelled and compacted all along the trench. Under unstable soil conditions, trench
depth and bedding thickness can be increased. After trench excavation, bedding should be prepared to provide durable
and stable support for pipe. Pipe bedding should not be less than 15cm in height and should be prepared with
compacted granular material at minimum 90% Standard Proctor Density or any other suitable bedding material at
minimum %95 Standard Proctor Density. Bedding depth should be increased if there are unstable, lose or soft soil
conditions. If bedding material is sandy, bedding material should be moisturized and should be compacted with
vibrating compactors. Bedding should always be flat and levelled with the trench bottom. A non-woven geotextile with a
unit weight of at least 100 g/m2 must be placed between the crushed stone and the sand bedding layer to prevent
filtration of the sand bedding into the crushed stone matrix. The trench bottom shall be continuous, smooth, free of
rocks, and to the line and grade shown on the installation drawings. Bedding material characteristics are very important
for a proper support for the pipes. Generally bedding and backfilling materials are preferred to have the same
characteristics. if the excavated material is preferred to be used as backfilling material, characteristics of the excavated
soil should be analyzed for suitability. Another critical point to be taken into consideration is the possibility of
experiencing different soil characteristics along the pipeline.

6.5.2 Installation of Pipe in the Trench and Lifting

After completion of trench excavation and bedding, installation can start in line with the project. Pipes and fittings
should be stored along the pipeline next to the trench according to the daily installation program for a faster and easier
installation. Stored goods should not block the working path of the construction machines such as crane, excavator,
bulldozer, etc lifting straps should be tied around the pipe from the appropriate lifting points. While lifting fittings,
special lifting and alignment requirements should be taken into consideration. (For instance, the arm angle of the Tee
part). lifting can be performed with a crane or with the excavator arm and pipe should be lowered onto the bedding
slowly. During lifting and lowering inside the trench, field teams instruct directions to the excavator operator to make
sure that pipe will be placed at the right location. Pipe should be lowered closer to the previously installed pipe and
should be carefully aligned.

6.5.3 Multiple Pipe in one Trench

During installation of multiple pipes in a single trench, distance between any of the 2 pipes is determined with the
formula (r1+ r2) /2 whereas r1: radius of the first pipe and r2: radius of the second pipe. Complying with the formula or
Manufacturer recommendation for the distance of pipes in the same trench.

6.6 INSPECTION & TEST PLAN.


- Work execution inspection and test shall be monitored and witnessed as per SSEM ITP and recorded in the
SSEM Inspection checklist and QC forms available in the ITP as applicable.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 12 of 16

- Request for Inspection (RFI)QC inspector shall issue a RFI 24 hour and 48 hours for weekend inspection and
remote area location as per Schedule Q in advance of test I inspection to CLIENT PMT to verify the readiness of
the test I Inspection and to inform MARAFIQ/ILF QC inspection in advance.

6.6.1 TESTING REQUIREMENTS

. Visual inspection.
All installed PVC/uPVC pipe and fittings shall be visually inspected for scratches, damaged ends, cracks,
delamination, crushing, weathering. Each piece of PVC/CPVC/uPVC pipe and fitting shall be examined for cuts,
scratches. gouges, kinks, buckles, and ultra-violet (sun) damage. Damaged lengths of pipe shall be cut out and
discarded. Damaged fittings shall be discarded as well.

GRAVITY TEST FOR DRAINAGE PIPE


• The segment or portion of pipe work to be tested shall be slowly filled from the possible lowest point with clean
domestic water and air is released at all high points in the system until the system is completely full.
• During each phase of installation, carry our interim leakage tests using water head, to ensure and prove the
firmness and leak free of joints.
• All openings of pipes should be closed with suitable plug.
• High level end of the pipe is connected to a 90-degree elbow and is connected to a piece of pipe, in order to get
a minimum head of 3 mtr. of water from the low-level point. The vertical pipe should be supported then start
filling the water into the pipe through water hose.
• Fill water carefully to minimize the air bubbles trapped in the line Then open, small opening in the expansion
test plugs such that all air trapped in the line should washed out. Again, fill water up to the required level of 3
mtr. head and keep this pressure head for 2 hours
• After 2 hours, if there is no decrease in level is observed, then the system will be considered tested
successfully. In case of any decrease in level, find out the leak in joints and re-do the test.

6.7 BACKFILLING
When the pipe installation and leak testing is completed and successful, backfilling of the pipe will follow.
However, partial backfilling prior to hydro -testing is permitted provided that the coupling joints or lamination
joints are exposed. During backfilling the following are to be followed:

o Proper selection, placement and compaction of the pipe zone backfill are important for controlling
the vertical deflection and are critical to the pipe performance.
o Attention must be paid so that the backfilling material is not contaminated with debris or other
foreign materials that could damage the pipe or cause loss of side support.
o During backfilling, the granular material should flow completely under the pipe to provide full
support.
o A blunt tool maybe used to push and compact the backfill under the pipe.
o Provide warning tape 300 mm above the top of pipe in burried services. ( Refer RC Section 02085 )
o Proper backfilling should be done in 150 mm to 300mm lifts depending on the backfill material and
compaction material. 300 mm lifts will be adequate for gravel because it is easy to compact.
o Compaction of sandy backfill is most easily accomplished when the material is near to its optimum
moisture content. When backfilling reaches pipe spring line, all compaction shall be done first near the
trench sides and proceeds towards the pipe.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 13 of 16

o It is recommended that placing and compacting of the pipe zone backfill is done in such a way as to
cause the pipe to ovalize slightly in the vertical direction.

The clean sand bedding shall be compacted to 70% Relative Density (ASTM D4253/ASTM D4254). The clean sand
from the bottom of the pipe to 300 mm above the top of the pipe (sand cover) shall be compacted by water
flooding and hand tamping only. No compaction testing is required in this section of the trench. Within 300 mm
of the top of the pipe, backfill shall be hand tamped, or a board shall be used to protect the pipe from damage
from vibratory plate compactors
Backfill above 300 mm sand cover in non-Traffic area shall be on site excavation or borrowed materials that meet
the following conditions:

Type of Pipe Nominal Pipe Size and Minimum


Cover (mm)
Service
Thermoplastic Sewers. gravity flow 900
Thermoplastic Pressure pipe under 100 mm size 600
Thermoplastic Pressure pipe 100 mm and larger 900
sizes
Thermoplastic Irrigation. under 90 mm size 300
Thermoplastic Irrigation. 90 mm and large 600

6.8 TOOLS and MATERIALS

• Hand Saw
• Measuring Tape
• Chalk line & Powder
• Wire Cutter
• Solvent Cement
• Lubricant
• Drilling Machine
• Grinding Machine
• Right Angle
• Ladder or Scaffolding with Platform
• Extension wire for Electrical Power etc.
• PVC/CPVC/uPVC pipe and Fittings

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 14 of 16

7.0 HSE REQUIREMENTS


The Health Safety and Environment Project Management Plan institutes the overall mechanism for the
risk management processes with regard to the Project. Processes are implemented at the earliest
stages within the project cycle, identifying risk and facilitating opportunity for the application of
appropriate mitigation strategies. As an integral part of the planning process, prior to the commencement
of any operational activity a suitable and sufficient specific assessment (RA) of the risks associated with
the works should be undertaken. Below are minimum HSE requirements.
 All works shall be done in accordance with the MARAFIQ Project HSE Manual and all individual activities shall
be set up in an orderly manner to ensure compliance with the requirements.
 Work permit shall be secured by the Site Engineer prior to carrying out any work and work shall proceed in
accordance with the specific measures itemized in the permit
 Relevant information on the permit shall be made available to all operative
 -performing the work by providing a copy to the Bulletin Board nearest or adjacent to the work area.
 The Safety Supervisor I Safety Officer is responsible along with the Site Engineer for ensuring that all
operations are being done with due regard for the safety of personnel property as well as the general public.
 All PPEs shall be worn by personnel performing the work at all times in full compliance to safety rules on PPE
Additional PPEs like respirator. rubber hand gloves and disposable coveralls shall be provided during
lamination and grinding works.
 Barricades shall be provided to isolate the work area but proper access shall be provided to all operatives.
 The work site shall be maintained in a clean and tidy condition

7.1 SAFETY INSTRUCTIONS

. Starting instructions will be given by the supervisors at the start of each activity to explain
the methodology of works and to communicate safe working procedures to the operatives.
These talks are structured in a way to highlight to major risks involved in the activity and
the various control measures required in order to minimize the risk. It is delivered in a
manner such as the key points will be remembered by the operatives receiving it.

. Toolbox talk meetings will be held for each crew, on group or employees, regarding more
general topics of the Project HSE Policy; in example lesson learned, near miss reports,
implementation of the requirements and message from the LBS management or
Employers HSE personnel.

7.2 Personal Protective Equipment’s

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 15 of 16

All workers will be issued and trained in use of the required PPE equipment to comply with contract procedures and
local regulations and will be supplemented with PPE as required by MSDS & Risk Assessments. This will include but will
not be limited to;

 Hard Hats
 Safety Boots with ankle support and steel toe caps
 Safety Goggles
 High Visibility Vests / Overalls with integrated reflective strips
 Hand gloves
 Face Masks
 A variety of mechanisms, such as method statement briefings and toolbox talks will be
 implemented to ensure all relevant personnel are appropriately informed.
 In addition to their safety induction received at their arrival on site, all the workers will have a
 toolbox meeting in order to be briefed about the risks of their specific work task, prior to start of works.

7. 3 ENVIRONMENTAL ISSUES

As part of the development of the Organization’s Environmental Management System(s) the


significant issues that are faced both on site and within offices or other facilities should be
addressed. This approach subsequently allows for a systematic focus upon the important
environmental aspects to be adopted which in turn facilitates prioritization of limited
resources.

7.3.1 MITIGATION MEASURES

 Toolbox talks and care shall be taken to use plenty of water during high humidity weather.
 General housekeeping rules for all operatives shall be observed.
 Stationary equipment e.g. lighting towers, gensets etc. will have containment trays beneath.
 Maintaining good housekeeping minimizes hazardous waste production by increasing the
likelihood that chemicals will be used before they expire and reducing the need to clean up
chemical spills.
 Hazardous substances shall be stored as per manufacturer’s recommendation or as
mentioned in safety data sheet.
 Hazardous waste shall be collected and disposed in hazardous waste skip.
 Spill kits shall be made available on site.
 Dip tray with a capacity of 110% shall be provided to control the chemical spill.

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 16 of 16

 Unauthorized personnel entry shall be restricted.


 Organize the work and setup tools and equipment correctly.
 Check all equipment’s are in good working condition.

8.0 DOCUMENTS AND PLANNING

Work will be performed in accordance with the APPROVED documents; IFC Drawing for Building, Tanks,
Foundation and other structural elements, planning schedule will be updated for delivery and shifting of
material. All lead mechanical engineer site mechanical engineer and material engineer shall have a 3-
weeks look ahead schedule of GRP stock inventory.

9.0 PLANT & EQUIPMENTS

SSEM will provide necessary tools and machinery, manual and torquing tool throughout the project which is depending
upon its requirements. Quantities will be determined by actual site/Store demand. Equipment will be inspected prior
utilizing.

10.0 QUALITY CONTROL AND ASSURANCE RECORDS


All records relevant to the above procedure will be retained by the Quality Control department in the site office, for the
duration of the project, before being handed over to the Contractor in accordance with the requirements of the contract
documents. Copies of all records will be made and transferred to the Contractor Office where they will be retained for
the guarantee period of the contract.

 Approved MRIs / RFIs


 IFC
 Approved Material Receiving RFI

11.0 TRAINING

Training will be providing as per training and project schedule.

 HSE Induction and General Safety Awareness Training


 Heat Stress Awareness Training
 PTW (Permit to Work) Procedure Training
 Lifting and rigging activities at Store / Site.
 Quality Induction Training
 First Aid Training

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907


PROJECT: EXPANSION OF IWTP-8 STAGE-4 DBO

OWNER: MARAFIQ

SSEM: SAUDI SERVICES FOR ELECTRO MECHANIC WORKS CO.


TITLE: METHOD STATEMENT FOR
SPECIAL PROCESS FOR INSTALLATION AND JOINING OF CPVC
& PVC/uPVC PIPES

Revision 00 Prepared By Reviewed By Approved By Page No.


DATE AUG 18, 2022 17 of 16

Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907

You might also like