Professional Documents
Culture Documents
Transmission Security Standard 2nd Edition
Transmission Security Standard 2nd Edition
Second edition
As Approved by Authority for Electricity Regulation – July 2016
CONTENTS
Page
7 Definitions 33
List of figures
Figure 1.1 – Representation of the OETC licensed transmission system and other GSO systems....... 5
Figure 1.2 – Generation connections, GSO connections and Grid Supply Points ................................. 6
Figure 5.1 – Demand Classes – Demand Group schematics ............................................................... 26
List of tables
Table 2.1 – OETC licensed transmission system – system parameter values ....................................... 8
Table 3.1 – MITS – Intact System requirements at Peak Demand values ........................................... 10
Table 3.2 – MITS – Following a Restricted Period Fault Outage.......................................................... 11
Table 3.3 – MITS – Following a Maintenance Period Fault Outage ..................................................... 12
Table 4.1 – Generation & GSO connections – Intact System requirements at Peak Demand ............ 14
Table 4.2 – Generation & GSO connections – Following a Restricted Period Fault Outage ............... 15
Table 4.3 – Generation & GSO connections – Loss of Power Infeed following a system outage ........ 16
Table 4.4 – Generation & GSO connections – Loss of Power Infeed during Planned Outages .......... 17
Table 4.5 – Generation & GSO connections – Following a Loss of Power Infeed ............................... 18
Table 4.6 – GSO connections – Loss of Power Infeed of following a system outage .......................... 19
Table 5.1 – Demand connections – Intact System requirements at Peak Demand ............................. 21
Table 5.2 – Demand connections – Following a Restricted Period Fault Outage ................................ 22
Table 5.3 – Demand connections – Following a Maintenance Period Fault Outage ............................ 23
Table 5.4 – Demand connections – Following a Restricted Period Unplanned Outage ....................... 24
Table 5.5 – Demand connections – Demand Class specification......................................................... 25
Table 6.1 – Operational outcomes during Prevailing System Conditions ............................................. 28
Table 6.2 – Operational outcomes following a Fault Outage ................................................................ 29
1.1.1 This document sets out the Transmission Security Standard (the “Standard” or “TSS”)
that the Oman Electricity Transmission Company S.A.O.C (“OETC”) will implement for
the planning and operation of its licensed transmission system. The TSS has been
prepared in accordance with Condition 26 of OETC's Transmission and Dispatch
Licence.
1.1.2 The TSS contains technical terms and phrases specific to electricity transmission
systems and the electricity sector that may differ from their common usage. For this
reason ‘Definitions’ have been included in section 7. Throughout this document,
defined terms are shown in italics with capital initial letters. Other terms with an initial
capital letter and in normal font are defined in the Grid Code.
1.1.3 For ease of use, the component elements of the TSS are presented according to the
functional parts of the OETC licensed transmission system to which they primarily
apply, including, but not limited to:
a The Main Interconnected Transmission System (“MITS”) and the Dhofar Power
System
b The generation connections at which a Production Facility feeds into the MITS
and GSO connections both internal to Oman and internationally
c Demand connections, where demand is connected, including:
i Grid Supply Points, and
ii Demand Groups
d The operational security criteria
1.1.4 Taken together, each of elements described in sections 1.1.3a to 1.1.3c inclusive
make up the OETC licensed transmission system, as shown in Figure 1.1.
1.1.5 The criteria for radially connected generation, GSO connections and demand
connections are consistent with the criteria applied to the MITS. However, they are
conditioned by the criteria for the relevant generation connections, GSO connections
and/or demand connections.
1.1.6 The criteria presented in the TSS represent normal requirements for the planning and
operation of the OETC licensed transmission system. Any departure from the TSS
criteria shall be subject to detailed risk and economic studies. These shall include
consideration of the costs associated with the use and/or introduction of out-of-merit
generation as an alternative to network reinforcement. To the extent permitted and
required within the TSS, OETC shall seek derogations from the relevant provisions of
the TSS.
1.1.8 As described above and illustrated in Figure 1.2, there will be many parts of the
OETC licensed transmission system where more than one set of criteria apply. In
such parts, the requirements of all relevant criteria shall be met. Figure 1.1 provides
an overall view of the OETC licensed transmission system. Figure 1.2 shows the
more detailed reach and overlap of the TSS criteria. Thus Figure 1.2 governs in
terms of the application of TSS criteria.
1.1.9 While it is a requirement for Transmission Capacity to meet the TSS criteria, it does
not follow that Transmission Capacity should be reduced so that it only meets the
minimum requirement of those criteria.
1.2 Structure and reach of the TSS in the OETC licensed transmission system
1.2.1 Figure 1.1 below shows the relationship between the various elements of the OETC
licensed transmission system.
1.2.2 Figure 1.2 below shows the reach and overlap of the various design criteria specified
in the TSS.
GSO system
GCCIA system
-5-
Demand Demand
connection connection
PDO system
GSO system
Future
Production
Generation connection Dhofar Power System GSO interconnection
Facility
Demand connection
Demand Group
2.1 Introduction
2.1.1 The Grid Code specifies various parameters including frequency, voltage, harmonic
distortion and flicker. These parameters contribute to the quality of supply
experienced by Users.
2.2.1 For purposes of the TSS and in respect of frequency and voltage, four conditions are
identified for determining system parameter values, as follows:
2.2.2 Transient frequency deviations that occur outside the limits of continuous operation
Stretched Conditions and last less than sixty seconds shall only occur at reasonably
infrequent intervals. This governs all relevant TSS criteria.
2.2.3 Table 2.1 sets out the required values for the system parameters.
Unacceptable conditions
Stretched conditions
Disturbed conditions
Parameter
Normal conditions
Low High Low High Low High Low High Low High
Target
˂ ≥ ˂ ≥ ˂ ≥ ≤ > ≤ > ≤ >
3.1 Introduction
3.1.1 As at the approval date, the MITS and Dhofar Power System are connected via a
local GSO system owned and operated by PDO.
3.1.2 For the purposes of this section the MITS design criteria shall apply equally to the
MITS and the Dhofar Power System.
3.2.1 Collectively, sections 3.3, 3.4 and 3.5 set out the design criteria for the MITS (the
“MITS design criteria”).
3.3.1 The minimum Transmission Capacity of the MITS shall be planned and designed to
achieve the outcomes specified in Table 3.1 for the following Background Conditions:
MITS
Intact System design requirements for Peak Demand values
1 GSO connection transfers show power import or export for the OETC licensed transmission system
3.4.1 Using Peak Demand values, the Background Conditions described in section 3.3 and
following a specified Fault Outage, the Transmission Capacity for the MITS shall be
planned and designed to achieve the outcomes specified in Table 3.2.
MITS
Outcomes following a Restricted Period Fault Outage at Peak Demand values
3.5.1 During the Maintenance Period, while using the expected OETC licensed
transmission system demand and the expected generation schedule but excluding
any forecast GSO connection import or export, with a Planned Outage of a single
Transmission Circuit or a single section of Busbar, and following the specified Fault
Outages, the MITS shall be designed to achieve the outcomes specified in Table 3.3.
MITS
Outcomes following a Maintenance Period Fault Outage
3.5.2 Where necessary to satisfy the above MITS design criteria during the Maintenance
Period, and unless operational measures can be applied to ensure adequate
Transmission Capacity, investment analysis shall be applied.
4.1 Introduction
4.1.1 This section presents the criteria to be applied for the direct connection of one or
more Production Facilities or GSO systems to the OETC licensed transmission
system. The criteria in this section will also apply to the connections from a Grid
Supply Point or Demand Group to the OETC licensed transmission system by which
Generation Units embedded within a User’s network (e.g. a distribution network) are
connected to the OETC licensed transmission system.
4.1.2 In those parts of the OETC licensed transmission system where the criteria of any of
section 3 and section 5 also apply, then those criteria shall also be met.
4.2.1 Collectively, sections 4.3, 4.4, 4.5, 4.6 and 4.7 set out the design criteria for
connecting a Production Facility or GSO systems and any other Generation Units to
the OETC licensed transmission system (the “generation connection design criteria”).
4.2.3 The generation connection design criteria apply to all forms of generation, such as but
not limited to:
a Synchronous machines
b Asynchronous machines, such as, for example, solar or wind powered
generators
4.2.4 In designing generation connections or GSO connections to meet the TSS, the
following shall be considered:
a The Loss of Power Infeed resulting from a Fault Outage on the Generation
Circuits or GSO connection circuits themselves; and
b The effects of a Fault Outage on the OETC licensed transmission system
4.2.5 When any new Production Facility, consisting of one or more Generation Units, or a
GSO connection, is proposed to be added to the OETC licensed transmission system,
then any system studies, planning, development and design shall consider the full
simultaneous power of all of the proposed Generation Units or GSO connections
operating together.
4.3.1 Using Peak Demand values, the Background Conditions described in section 3.3 and
prior to any Secured Event, the minimum Transmission Capacity for generation
connections and GSO connections shall be planned and designed to achieve the
outcomes specified in Table 4.1.
4.4.1 Using Peak Demand values, the Background Conditions described in section 3.3 and
following the specified Secured Events, the Transmission Capacity for generation
connections and GSO connections shall be planned and designed to achieve the
outcomes specified in Table 4.2.
4.5.1 Starting with an Intact System and including any forecast GSO connection import or
export, generation connections and GSO connections shall be planned, designed,
developed and constructed to achieve the outcomes specified in Table 4.3.
Table 4.3 – Generation & GSO connections – Loss of Power Infeed following a
system outage
Fault Outage of any single Busbar Any Loss of Power Infeed from
coupler circuit-breaker or Busbar Production Facilities shall not exceed
section circuit-breaker on the MITS the Infrequent Infeed Loss Risk
4.6.1 Generation connections and GSO connections shall be planned, designed, developed
and constructed such that, during the specified Planned Outages, any Loss of Power
Infeed shall achieve the outcomes specified in Table 4.4.
Table 4.4 – Generation & GSO connections – Loss of Power Infeed during
Planned Outages
a further single
Transmission Circuit;
or
a single section of
Busbar
A single Transmission
Circuit
a single Busbar coupler
circuit-breaker;
or
a single Busbar section Any Loss of Power
circuit-breaker Infeed from Production
Facilities shall not
a single Transmission exceed the Infrequent
Circuit; Infeed Loss Risk
or
a further single section
of Busbar
A single section of
Busbar on the MITS
a single Busbar coupler
circuit-breaker;
or
a single Busbar section
circuit-breaker
4.7.1 The Transmission Capacity for Generation connections and GSO connections shall
be planned such that, for all OETC licensed transmission system conditions, the Loss
of Power Infeed of the same magnitude as the Normal Infeed Loss Risk or Infrequent
Infeed Loss Risk respectively is secured as specified in Table 4.5.
Table 4.5 – Generation & GSO connections – Following a Loss of Power Infeed
4.8.1 Starting with an Intact System, GSO connections shall be planned, designed,
developed and constructed to achieve the outcomes specified in Table 4.6.
GSO connections
Intact System
Requirements for Loss of Power Infeed following a system outage
4.9.1 OETC may seek derogation for variation to the generation connection design criteria
and/or the requirements of Table 4.6, based on technical and economic analysis of
design options relative to the characteristics of the generation or GSO to be
connected.
5.1 Introduction
5.1.1 This section presents the planning and design criteria for the connection of Demand
Groups to the OETC licensed transmission system.
5.1.2 In those parts of the OETC licensed transmission system where the criteria of
sections 3 and 4 also apply, then those criteria must also be met.
5.2.1 All the criteria listed in this section 5 comprise the demand connection design criteria.
5.3.1 The connection of a particular Demand Group shall meet the criteria set out in
sections 5.4 through to and including 5.7 under the following Background Conditions:
a When there are neither Planned Outages nor Unplanned Outages, the Group
Demand shall be set equal the value at the time of Peak Demand;
b When there is a Planned Outage local to the Demand Group, the Group
Demand shall be set equal to the relevant Maintenance Period Demand;
c Any Transfer Capacity (i.e. the ability to transfer demand from one Demand
Group to another) declared by Distribution Licensees shall be represented
taking account of any restrictions on the timescales in which the Transfer
Capacity applies. Any Transfer Capacity declared by the Distribution
Licensees to be available for use in planning timescales must be available for
use in such planning timescales; and
d Any generation available within a Demand Group shall be taken into account by
considering its forecast generation as provided by the relevant Generation Unit
owner
5.4.1 For Peak Demand values and prior to any Secured Event, the minimum Transmission
Capacity of any demand connection, its relevant Transmission Circuits and Demand
Groups shall be planned and designed to achieve the outcomes specified in
Table 5.1.
Demand connections
Demand Group
Intact System design requirements for Peak Demand values
5.5.1 Using Peak Demand values, the Background Conditions described in section 5.3 and
following a specified Fault Outage, the Transmission Capacity for the connection of a
Grid Supply Point to a Demand Group shall be planned and designed to achieve the
outcomes specified in Table 5.2.
Demand connections
Demand Group
Outcomes following a Restricted Period Fault Outage at Peak Demand values
5.6.1 During the Maintenance Period, using Maintenance Period Demand values, with the
Background Conditions described in section 5.3, the Transmission Capacity for the
connection of a Grid Supply Point to a Demand Group shall be planned to achieve the
outcomes specified in Table 5.3.
Demand connections
Demand Group
Outcomes following a Maintenance Period Fault Outage
a) No loss of supply to
Grid Supply Points
such that the
provisions set out in
Table 5.5 are not met
b) System Equipment
A single Transmission shall be within the
Circuit; Fault Outage of a relevant Technical
single Limits
or Transmission c) No Unacceptable
Circuit Frequency Conditions
A single Generation Unit d) OETC licensed
transmission system
voltage levels within
normal conditions
e) No Insufficient
Performance Margins
f) No System Instability
5.6.2 Where necessary to satisfy the above demand connection design criteria during the
Maintenance Period, and unless operational measures can be applied to ensure
adequate Transmission Capacity, investment analysis shall be applied.
5.7.1 Using Peak Demand values, the Background Conditions described in section 5.3 and
following a specified Unplanned Outage, the Transmission Capacity for the
connection of a Grid Supply Point to a Demand Group shall be planned and designed
to achieve the outcomes specified in Table 5.4.
Demand connections
Demand Groups
Outcomes following an Unplanned Outage at Peak Demand values
5.8.1 In addition to the requirements of sections 5.4 through to and including 5.7 and for the
Background Conditions described in section 5.3, the system shall be planned such
that operational switching does not cause Unacceptable Voltage Conditions.
5.9.1 OETC may seek derogation for variation to the demand connection design criteria in
this section 5, based on technical and economic analysis of design options relative to
the characteristics of the demand or embedded Generation Units to be connected.
Demand connections
Demand Class definition and supply restoration times
Demand
Class A Planned Outage
Following a system outage followed by
Demand Class
boundaries
during the Restricted Period a single Fault Outage
during the Maintenance Period
Required Required
Low High level of Time to level of Time to
MW MW served restore served restore
demand served demand served
> ≤ demand demand
MW MW
Repair time
No
A 0 2 of faulted
requirement
circuit
No
B 2 6 3 hours
requirement
Maintenance
Return time
Period
C 6 20 Total Group 15 minutes of Planned
Demand for
Demand Outage
the Demand
Group
Momentary Return time
D 20 115 Interruption of Planned
allowed Outage
Momentary Momentary
E 115 300 Interruption Interruption
allowed allowed
6.1 Introduction
6.1.1 This section sets out the operational requirements, conditions, outcomes and system
states that should be achieved either through automatic control, operator intervention,
or any combination of these, as required by the circumstances.
6.1.2 The overall objective is always to maintain the values of system parameters within the
normal conditions as set out in section 2 and especially Table 2.1.
6.2.1 For the OETC licensed transmission system, sections 6.3 and 6.4 set out the normal
operational security criteria for its operation and maintenance, while section 6.6
provides for further conditional security criteria, together, the “operational security
criteria”.
6.3.1 At all times prior to any Secured Event, the OETC licensed transmission system shall
be operated so as to achieve the outcomes specified in Table 6.1.
6.4.1 At all times during Prevailing System Conditions and following a specified Fault
Outage, the OETC licensed transmission system shall be operated to achieve the
outcomes specified in Table 6.2.
6.5.1 If the any one of the outcomes set out in Table 6.1 and Table 6.2 cannot be achieved,
then the following actions should be taken, preferably in sequence, until the OETC
licensed transmission system has been secured such that the outcomes of Table 6.1
and Table 6.2 are met:
6.5.2 Prior to constraining load and demand as contemplated in section 6.5.1f above, and
to the extent possible, OETC senior management shall be informed of the intended
operator action.
6.6.1 During Major Risk Periods, OETC shall implement measures to mitigate the
consequences of this risk. Such measures may include, but are not limited to:
6.6.2 If, following a Fault Outage, any one of the outcomes required in section 6.4 is not
being met, it is acceptable to utilise short-term post-fault actions to avoid
Unacceptable Overloading of System Equipment which may include a requirement for
Group Demand reduction; however, this will not be used as a method of increasing
reserve to cover abnormal post-fault generation reduction. Where possible these
6.7.1 Following the occurrence of a Secured Event, measures shall be taken to re-secure
the system to the above operational security criteria as soon as reasonably
practicable. To achieve this, it is permissible to put operational measures in place
before the occurrence of a Secured Event to facilitate the subsequent restoration of
system security.
6.8.3 The principles of the operational security criteria shall be applied at all times except in
special circumstances where OETC, following consultation with the appropriate User,
may need to give instructions to the contrary to preserve overall OETC licensed
transmission system integrity.
Term Meaning
Background Conditions For system study purposes, this will include, but not be limited to,
any parameters that are relevant to the behaviour and dynamics
of the OETC licensed transmission system, such as:
a) OETC licensed transmission system configuration
b) The electrical location and duration of Planned Outages
and/or Unplanned Outages
c) Voltage levels at Grid Supply Points
d) Forecast demand at Grid Supply Points
e) Transfer Capacity between Demand Groups that may not
make use of circuits within the OETC licensed transmission
system
f) Connected Production Facilities
g) Dispatched Generation Units
h) Available Generation Units which have not been dispatched
i) Energised GSO connection circuits
Specific Background Conditions required for particular Secured
Events are specified throughout the TSS
Demand Class This is designated by a letter “A” through “F” for the relevant
Demand Group and the security of supply that should be
provided for the relevant Demand Group. Refer to Table 5.5 and
Figure 5.1
Demand Group A site or group of sites which collectively take power from the
remainder of the OETC licensed transmission system through a
Grid Supply Point. Refer to Table 5.5 and Figure 5.1
Dhofar Power System For the purpose of the TSS, the Dhofar Power System is that part
of the OETC licensed transmission system that is located in the
Dhofar Governorate, centred on Salalah, but does not include
radially connected Generation Units, GSO connections, and/or
radially connected Grid Supply Points.
Generation Circuit The sole electrical connection between one or more Generation
Units at a Production Facility and the MITS; a radial circuit which,
if removed, would disconnect one or more Generation Units
Grid Supply Point A point of supply from the OETC licensed transmission system to
GSP any of, or any combination of:
a) Distribution Licensees
b) Non-embedded Customers
Infrequent Infeed Loss Risk That level of loss of power infeed risk which is covered over long
IILR periods operationally by frequency response to: (i) avoid a
deviation of system frequency outside the range 49.50 Hz to
50.50 Hz for more than 60 seconds; and (ii) never below
47.50 Hz (Table 2.1).
As at the approval date, it has a value of:
For the MITS:
a) 1,200 MW.
b) The remaining GSO interconnection circuit rating less any
import from the GSO interconnection
For the Dhofar Power System:
c) 40 MW.
d) The remaining GSO interconnection circuit rating less any
import from the GSO interconnection
Insufficient Performance For all time periods, and in particular the during Post-fault
Margins Periods, there are Insufficient Performance Margins when the
voltage on any relevant portion of the OETC licensed
transmission system has values within the range of Unacceptable
Voltage Conditions and occurs under any one of the following
conditions:
a) Based on international best practise, a 5% increase in Group
Demand above the level prevailing prior to the occurrence of
the relevant Secured Event; or
b) The unavailability of any single reactive compensator or other
reactive power provider; or
c) The loss of any one automatic switching system or any
automatic voltage control system for on-load tap changing
Intact System This is the OETC licensed transmission system with no:
a) Planned Outages
b) Unplanned Outages
c) Fault Outages
Loss of Power Infeed Means the output of a Generation Unit or a group of Generation
Units or the import from GSO system(s) disconnected from the
OETC licensed transmission system by a Secured Event, less the
demand disconnected from the OETC licensed transmission
system by the same Secured Event.
For the avoidance of doubt if, following such a Secured Event,
demand associated with the normal operation of the affected
Generation Unit or Generation Units is automatically transferred
to a supply point which is not disconnected from the system, e.g.
the station board, then this shall not be deducted from the total
Loss of Power Infeed to the OETC licensed transmission system.
For the purpose of operational criteria, the Loss of Power Infeed
includes the output of a single Generation Unit, CCGT module, or
boiler lost as a result of such an event.
Main Interconnected For the purpose of the TSS, the Main Interconnected
Transmission System Transmission System or MITS is that part of the OETC licensed
MITS transmission system that is interconnected at 400 kV, 220 kV or
132 kV but does not include radially connected Generation Units,
GSO connections, and/or radially connected Grid Supply Points.
For purposes of the TSS, the MITS includes the Dhofar Power
System unless required otherwise by the context
Refer to section 3.1 for the Dhofar Power System
Maintenance Period For MITS: Means the period between 00:00 on 1st October and
24:00 on 31st March of the next following year.
For Dhofar: Means the period between 00:00 on 1st July and
24:00 on 31st March of the next following year.
Maintenance Period This is the highest demand during the Maintenance Period, taking
Demand due account of the Group Demand. If no better forecast is
possible from the data available, Maintenance Period Demand
shall be estimated as the Group Demand multiplied by 67%.
Major Risk Period A Major Risk Period is one during which Secured Events are:
a) judged to be significantly more likely than under the
circumstances addressed by the normal TSS criteria, or
b) judged to have a significantly greater impact than normal, or
c) events not normally secured against which are judged to be
significantly more likely than normal such that measures
should be taken to mitigate their impact
An example would be country-wide extreme weather conditions
Momentary Interruption Means a loss of power that lasts for no more than one (1) minute
from the start of the relevant Fault Initiation Event, with the
restoration of power intended to be performed by automatic
equipment
Normal Infeed Loss Risk Means that value of lost power infeed that would cause the OETC
NILR licensed transmission system frequency to fall to a value equal to
but not below the NILR frequency limit (Table 2.1).
As at the approval date, and it has a value of:
For the MITS:
a) 600 MW
b) The remaining GSO interconnection circuit rating less any
import from the GSO interconnection
For the Dhofar Power System:
c) 25 MW
d) The remaining GSO interconnection circuit rating less any
import from the GSO interconnection
Prevailing System These are conditions on the OETC licensed transmission system
Conditions prevailing at any given time and will therefore normally include
Planned Outages and Unplanned Outages, but excluding any
Fault Outage
Restricted Period For MITS: Means the period other than the Maintenance Period,
occurring between 00:00 on 1st April and 24:00 on 30th
September of any year.
For Dhofar: Means the period other than the Maintenance
Period, occurring between 00:00 on 1st April and 24:00 on 30th
June of any year.
The period is during which:
a) No Planned Outage shall occur
b) Unplanned Outages may only be permitted as prescribed in
the Grid Code
c) The summer Peak Demand will occur
Steady State A condition of a power system in which all automatic and manual
corrective actions, such as, but not limited to, tap changing and
switching of circuits, have taken place and all of the operating
quantities that characterise it can be considered constant for the
purpose of analysis
System Condition Has the meaning shown in Table 2.1 and addresses the following
conditions on the OETC licensed transmission system:
a) Normal conditions
b) Disturbed conditions
c) Stretched Conditions
d) Unacceptable Conditions
Refer to Table 2.1
Transfer Capacity That circuit capacity from adjacent Demand Groups which can be
made available within the times stated in Table 5.5
Transmission Capacity The ability of a network to transmit electricity. It does not include
the use of Operational Intertripping except in respect of
section 5.3.1c
Transmission Circuit Part of the OETC licensed transmission system between two or
more circuit-breakers which includes, for example, transformers,
reactors, cables and overhead lines but excludes Busbars,
Generation Circuits and GSO connection circuits
Unacceptable Frequency These are conditions where the OETC licensed transmission
Conditions system frequency does not meet the criteria for either:
a) High Frequency Limits, or
b) Low Frequency Limits
Refer to:
Section 2.2.1d
Section 2.2.2
Table 2.1
Unacceptable Overloading The overloading of any System Equipment beyond its specified
time-related capability. Due allowance shall be made for specific
conditions (such as ambient or seasonal temperature), pre-fault
loading, agreed time-dependent loading cycles of equipment and
any additional relevant procedures
Refer to Pre-Fault Rating and Technical Limit
-o0o-