Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 1
SECTION 6
6.2
6.3
6.4
6.5
UNIT 2290 - BENZENE
INTRODUCTION AND DESIGN BASIS
6.1.1 Introduction
6.1.2 Design Basis
PROCESS DESCRIPTION
6.2.1 Process Features
6.2.2 Unit Description
6.2.3 Process Controls
6.2.4 Safety Considerations
6.2.5 Material Balance
SPECIFICATIONS OR RAW, AUXILIARY MATERIALS AND UTILITIES
6.3.1 Raw Materials Specifications
6.3.2 Chemicals Specifications
6.3.3 Utilities Specifications
EXPECTED UNIT PERFORMANCES
6.4.1 Production Capacity
6.4.2 Product Characteristics
6.4.3 Expected Consumptions and Recoveries
6.4.4 Chemicals and Auxiliary Material Requirements
6.4.5 Alternative Specification Case
aRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 2
6.6
6.7
6.8
6.9
6.10
OTHER INFORMATION
6.6.1 Data on Releases to Flare System
6.6.2 Recommendations for Products Storage and
Handling
6.6.3 Health Considerations
EQUIPMENT LIST
6.7.1 General
6.7.2 Equipment List
EQUIPMENT CHARACTERISTICS
6.8.1 General
6.8.2 Process Data Sheets
LIST OF CRITICAL ITENSRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 3
6.1
6.1.1
INTRODUCTION AND DESIGN BASIS
Introduction
The FORMEX Process covers the extraction and purification of
aromatics from feedstocks of different origins such as
Reformed Gasoline and Hydrogenated Py-Gasoline in the Cp-Cy
cuts by using an aqueous solution of Foraylmorpholine as a
solvent.
In this specific case, as the only aromatic product to be
produced is Benzene, the Py-Gasoline is fractionated into a
Light cut containing the Benzene and light non aromatic
hydrocarbons and a heavy cut containing Toluene and Xylenes.
The Benzene is separated from the non-aromatics hydrocarbons
in the presence of the solvent in an extractive column.
The rich solvent, containing the benzene, is then sent to a
stripper, where the lean solvent is recovered as bottom
product and recycled back to the extractive column.
The benzene is recovered as extract from the top of the
stripper.
The extract and Raffinate are finally washed to eliminate
possible Formylmorpholine or Morpholine traces -Ras Lanuf Complex - Phase IT
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 4
6.1.2
Design Basis
The Unit has been designed on the basis of 8,000 full
operating hours per year to produce 88,000 t/year of Benzene
having the specifications listed under following para.
6.4.2.1. The feedstock shall be as specified in following
para. 6.3.1.1.
‘The Unit has been designed to allow the operation in the
range from 40 to 110 percent of design flow rate indicated at
para. 6.4.3.1.
The Unit shall be able to accomodate moderate variations on
the composition of the feedstock of the expense of the
production rate but not at the expense of the product
quality.
However, in case the actual feedstock shall be not in
accordance to the feed specification, stated in para,
6.3.1.1, the CONTRACTOR reserve the right to review the
process guarantees Pa(
(
Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 5
6.2 PROCESS DESCRIPTION
6.2.1 Process Features
‘The FORMEX, Aromatics Extraction Process, is based on the use
of a solvent (N-formylmorpholine) which displays excellent
solvent power and selectivity.
This process has proved to be very suitable for the
separation of the aromatics from hydrocarbon mixtures.
One additional feature of the Formylmorpholine is a quite
good thermal stability; furthermore, it is not corrosive,
thus enabling the use of carbon steel as material for the
equipment.
6.2.2 Unit Description
(Reference is made to Process Flow Diagram DWG
GD-12E-04506-0)
‘The Benzene Unit includes the following sections:
6.2.2.1 Splitter Section
The charge, consisting of a C,-Cg hydrogenated fraction,
coming from the Battery Limits, is stored in the feed surge
drum, V-18.
Hence it is pumped by feed pump P-19 A/S, under flow control,
to exchangers X-01/X-04, where it gets preheated exchanging
respectively with T-01 bottom product and the solvent coming
from the stripper vmRas Lanuf Complex - Phase IT
LSTK~1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 6
The T-O1 feed temperature is controlled acting on x-O4
by-pass, solvent side. Feed splitter column T-01 is fed at
tray No. 24 or, alternatively, at tray No. 18 or 30.
‘The separation between the Benzene and heavier aromatics
contained in the charge takes place within column T-01, thus
producing a top stream mainly consisting of Benzene and light
non aromatic hydrocarbons and a bottom stream containing
Toluene, Xylenes and heavy non aromatic hydrocarbons.
The Bottom stream, under level control, is cooled off by
exchanging heat with the feedstock in X-O1 and with cooling
water in X-02 then, it is send to Battery Limits.
The splitter, column is provided with a recirculating
reboiler, X-05.
Medium pressure steam is used as a heating medium, the
quantity of steam is controlled by the reboiler return
temperature which acts in cascade on the flow rate
controller.
‘The T-01 overhead vapours are condensed and subcooled in air
cooler X-03. The condensate is sent to splitter overhead
accumulator V-01.
A pressure controller is installed on V-Ol, acting in split
range, to discharge excess vapour to flare or to request
nitrogen as blanket gas
The hydrocarbons from V-01 are sent, by splitter reflux pumps
P-02 A/S, partly as reflux to column T-01 controlled by the
overhead column temperature gradient which acts in cascade on
the flowrate controller, partly as feedstock to the
extractive distillation section. The flow controller set
point is automatically adjusted by V-01 level controller.
4Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 7
6.2.2.2 Extractive Distillation Section
The feedstock to the extractive distillation section is
preheated by the solvent in X-06. A temperature controller,
acting on the by-pass, solvent side, maintains the stream
near its boiling point.
‘The stream enters extractive distillation colum T-02 at tray
No. 15.
In this column the hydrocarbons get into contact with the
solvent, fed onto tray No. 33, which extracts the Benzene as
bottom product.
‘The temperature of the solvent is controlled by a dedicated
instrument acting on fan pitch of solvent aircooler X-07.
The overhead vapours, consisting of Paraffinic hydrocarbons,
water and traces of solvent, are condensed and subcooled in
air cooler X-08.
‘The condensate is collected in overhead accumulator V-02
where the two phases separate: the aqueous phase is withdrawn
by reflux pumps P-04 A/S, and returns to the tower under
interphase level control to minimize the solvent entrained in
the overhead vapours. The light phase is withdrawn by
raffinate pump P-05 A/S, cooled off in cooler X-09 and then
sent to raffinate washing tower T-O4.
A pressure control is provided on V-02, acting in split
range, requests nitrogen to blanket the tower or discharges
excess vapour to sump tank V-06, where solvent droplets,
possibly entrained, are collected.
Column T-02 is provided with a once-through reboiler, X-10.
4Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 8
6.2.2.3
2
Medium pressure steam, depressurized to 9 kg/cn’g and
desuperheated, is used as a heating medium, the quantity of
steam is controlled by the reboiler return temperature which
acts in cascade on the flow rate controller.
Benzene Stripping Section
‘The extractive distillation bottom product, mainly consisting
of solvent and Benzene, is withdrawn by bottoms pumps P-03
A/S and fed to tray No. 20 of stripper column T-03.
‘The section of the tower above the feeding point has the task
to remove the solvent from the hydrocarbons using an aqueous
flow, whereas in the section below the feeding point the
solvent is stripped.
‘The overhead vapours, consisting of water, Benzene and traces
of solvent, are condensed and subcooled in air cooler X-11.
A pressure control provided on V-03, acting in split range,
requests nitrogen to blanket the tower or discharges excess
vapour to sump tank V-06 where solvent droplets are
collected. The OVHD Condensate is collected in overhead
accumulator V-03, where the two phases separate. The aqueous
phase is refluxed into the tower by pumps P-07 A/S under V-03
interface level control which acts in cascade on a flow
controller.
The organic phase, consisting of the extracted Benzene, is
sent to air cooler X-12 and subsequently to the washing tower
7-05 by pumps P-08 A/S.
‘The bottom stripper temperature is maintained at the value
necessary to obtain an almost complete Benzene stripping.
3Ras Lanuf Complex - Phase IT
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 9
6.2.2.4
‘The temperature must be carefully controlled, avoiding values
beyond which solvent decomposition would set in, along with
corrosion phenomena. To this purpose, a temperature
controller is provided, which acts in cascade on the vapour
flowrate to reboiler X-13, once-through type.
‘The solvent is withdrawn from the stripper bottom by pumps
P-06 A/S and routed, under level control in cascade on a flow
controller, to exchangers X-O4 and X-06, where it exchanges
heat with the T-01 and T-02 charges respectively, gets
further cooled under temperature control in air cooler X-07
and is finally fed to tray No. 33 of Extractive Distillation
Column T-02.
Extract and Raffinate Washing Section
‘The raffinate is countercurrent water-washed in tower T-Ol in
order to get rid of the residue Morpholine traces and
subsequently is sent to Battery Limits.
Part of the washing water is sent to the solvent circuit to
maintain the current solvent/water ratio; part is drained
into the oily sewer under T-O4 interface level control.
‘The Benzene is washed with water in countercurrent inside
tower 1-05 for residual Morpholine traces removal and
subsequently is sent to clay treatment under V-03 hydrocarbon
level com PRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 10
6.2.2.5 Clay Treatment and Storage
Aim of this section is to clean up the Benzene to meet the
restrictive product specifications.
Benzene coming from T-05 is sent to X-20 A/B, where it is
pre-heated by Clay Treatment effluent and through X-21 where
it is heated by Medium Pressure Steam,
The hot feed passes down through Clay towers T-06 A/B.
Normally only one clay is used, but provision is made to run
both towers in series or parallel operation.
After the Clay tower the effluent is cooled by exchange with
the cold feed and finally in the X-22 water cooler.
The Benzene Product is continuously analyzed by a
chromatograph; if the Benzene stream does not meet the
specifications, it is recycled to the Unit.
From $-01 and S-02 the Benzene is withdrawn by pump P-17 A/S
and conveyed to the Unit Battery Limits. Benzene to storage
pumps are designed to empty the daily tank (24 hours’
production) in 8 hours.
‘The Off-Spec Benzene may be sent, by the same pumps P-17 A/S,
to the following points of the Unit:
- feed surge drum V-18 if it is Off-Spec because of excess
Toluene
- as feedstock to T-02, if it is Off-Spec for excess non
Aromatic Hydrocarbons. -Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 11
6.2.2.6 Solvent Filtration and Regeneration
Provision is made to withdraw from the discharge of the
stripper bottoms pumps P-06 A/S a portion of solvent which is
sent to solvent filter F-Ol A/S after cooling in X-14.
Filters eliminate the possibly entrained solid particles from
the solvent. A high differential pressure alarm indicates
that the filter in operation is plugged.
The cooled solvent is recycled back to the bottom of the T-03
as a quench to minimize thermal degradation of the solvent
itself.
Morpholine and Formic Acid are present in the solvent in
equilibrium with Formylmorpholine. If the quantities present
to the equilibrium decrease either because the Formic Acid
decomposes due to the temperature effect, or for Morpholine
losses with Raffinate and Extract a further Formylmorpholine
decomposition takes place.
‘The quantities of free Morpholine/Formic Acid are, therefore,
to be kept under control by adding Formic Acid/Morpholine
whichever necessary.
To this purpose, from pumps P-06 A/S delivery a slim portion
of solvent is withdrawn which is mixed with a proper dose of
Formic Acid/Morpholine withdrawn from Formic Acid/Morpholine
drum V-05 by pump P-10; this stream is then sent to solvent
correction vessel V-10 dimensioned with the residence time
necessary to reach the equilibrium between Formic
Acid/Morpholine and Formylmorpholine.
Provision is made for the treated solvent to flow back
upstream of cooler X-07. This discontinuous operation is
fRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 12
carried out every time the content of free Norpholine/Formic
Acid in the solvent shows a tendency to increase.
As an alternative, a slip stream of solvent may be sent to
preheater X-17 and then to regenerator V-07 where is
evaporated under vacuum.
Vapours are condensed in water condenser X-16 and the
regenerated solvent, withdrawn by pump P-13, is sent to
storage tank S-03 under level control of an accumulator boot
of X-16.
This operation, carried out periodically, allows the
elimination of polymers formed due to the temperature effect;
these polymers are drained from the bottom of regenerator
v-o7.
‘The Unit filling and make-up operations are carried out
flowing the solvent from tank S-03 to sump tank V-06; hence
the solvent is sent upstream of cooler X-07 via vertical pump
P-09.
‘The filling of the solvent storage tank is performed by P-09,
which takes suction of the solvent from V-06 through a(
Ras Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 13
6.2.2.7 Drainage Recovery System
Provision has been made for two separate drainage recovery
systems.
One collects the drainage from column T-01 and dedicated
equipment, along with the drainage of storage tanks S-Ol and
S-02.
‘These drainages, consisting of hydrocarbons which have not
yet got into contact with the solvent, are collected and
conveyed to Py-Gasoline sump tank V-11, which receives also
the vents of the same pieces of equipment.
‘The liquid phase separated in V-11 is sent to feed surge drum
V-18 for treatment by vertical pump P-14. Vapours are sent to
flare. The second system collects the drainage of the
remainder Unit equipment (S-03 included) which contains, or
may contain, solvent.
Drainages of this second system are collected and sent to
sump tank V-06, which also receives the vents from the sane
equipment and the blanketing system balancing line header.
The liquid phase separated in V-06 is conveyed upstream of
X-07 for treatment or, alternatively, to tank S-03, by pump
P-09 activated by high level within V-06.
Due to the possible presence for Formylmorpholine which has a
quite high freezing point, provision has been made for a
heating coil in V-06. xRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 14
6.2.2.8 Steam and Condensate Recovery System
Medium pressure stean is used to reboil splitter coluan 7-01.
To minimize solvent corrosion and decomposition phenomena,
columns T-02 and T-03 are reboiled with steam pressured down
tod kg/en?g and desuperheated.
‘The mean pressure steam condensate coming from X-05 and those
from X-10, X-13 and X-16/X-17, when in use, and X-21, are
collected into medium condensate flash drum Y-12, where they
expand to 4.5/5.8 kg/en”. The produced steam is routed to the
ow pressure steam system. The condensate is fed, under level
control, to low condensate flash drum V-13, which also
receives the condensates from the low pressure steam users.
The steam liberated in V-13 is condensed in air condenser
X-18 and the condensate flows back into V-13.
Provision is made for a pressure controller in V-13, which
overflows steam to the atmosphere.
The recovered condensate is withdrawn by pump P-20 and
partially recycled back to the MP Stean desuperheater W-01.
the remainder is cooled in X-19 and sent to B.L.
The recovered condensate is analyzed on a continuous basis
downstream of P-20 and, should it shows hydrocarbon presence,
is drained to the oily sewer after cooling off in water
cooler X-19.
Interception of the condensate line to the steam generation
system and the opening of the valve on the draining line to
oily sewer are rouRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 15
6.2.3
6.2.3.1
Process Controls
‘The Unit has been provided with the normal controls over the
operating variables in order to maintain the unit itself as
close as possible to the design parameters and to check the
main performances of the unit.
‘As On-Line gas-chromatograph has been provided to check the
purity of the Benzene to Storage and its content of toluene
and other non-Aromatics Hydrocarbons
‘The process controls of the unit are shown in detail in the
Process Flow Diagram and in the Piping and Instrument
Diagrams (see following para. 6.10.).
Supervised Variables
For the Splitter Section beside the normal controls, the unit
has been provided with additional instrumentation to realize
a Feed-Forward control.
‘The main facility is the On-Line gas-chromatographic Analysis
of the feedstock.
‘The Combination of the normal controls along with the Feed-
Forward Controls can be considered a low level Advanced
Control System (A.C.S.).
Such a system is to be realized with minimum impact either on
the cost or on the reliability of D.C.S
Scope of the A.C.S. is to maintain the product quality and
benzene recovery targets in the following cases:
- Sudden changes in the Feedstock, either in Composition or
Flow rate.
- Changes in the temperature profile of the cum 2DRas Lanuf Complex - Phase II
LSTK-1 - PETROCHEMICAL PLANT
Part 2 - Technical Proposal Page 6 - 16
6.2.4
6.2.5
Safety Considerations
‘The Unit has been designed with the utmost care as far as
safety is concerned.
Particularly:
- continuous process gaseous discharges are conveyed to the
blow-down system;
- discontinuous drainages and vents (see maintenance, etc.)
are routed to two closed drain systems which are, in turn,
connected to blow-down by a header;
- prevision is made for the installation of 30 gas detectors
to detect release or accumulation of toxic and flammable
gases;
Material Balance
‘The enclosed Table 6.2.5.1 shows the overall material balance
of the Benzene Unit.
As to the number of streams see PFD e-ecues-e.CMRP ASCO- SPLAT | 213/64 | 2250 _
Snamprogetti "ang AUF COMPLEX PHASE TE SPCNo.Tabée 6.2.5.4.
PROJECT/UNIT Rev
Page 6-17 | Ur 2290 -BENZENE — |wA a2. TTT
HEAT AND MATERIAL BALANCE TABLE Ret. PFO No:
STREAM No 4 2 3 4 6 € B
NAME
‘COMPONENT
WATER = ca - = lau = [4uz |
FORTY -MORPHOLINE - = - - 78375| - 78375
BENZENE OFS | W053 | 22 53 |Il008 | 1000| 8
OTHER aRoraTics |¢60ss| 0-6 |eos44| - | O6 | a6 | =
How AROrIATIES HC| 10557 |3937-4|6619-6| 3926 | 11-4 | 1-4 =
Tosa Liquid Mass Fow -ta/h | 2?6Q7| 14991 | 12696 | 397.9 [93512 | 11012 | 82500
[rompers Pe 35| 90 | 40 | 6s |i27 | ¢5 [iss
Pressure “Kgdnig| 5-7 [0-76 | 7-0 | 0-2 | 0-9 | 0-2 |o- 3 |
Standardtig. Density ko/ni = = =
ici Lia DDE, shai? | 834 | 759 | 845 | 67/ | 1005 | 835 |1023
Vapor MW
‘Vapor compressibiliy factor = = = =
4 a |
7 | ae ea [27-07-93]
new Deserpion Prepared | Checked | Approved | ate
Sa
om coge: OAT PT BMT 0001 ShOv/Rev O92 Fie code BLNODEVOAT
‘Tus doruents ne property a! Shamprogetiwho wil slegutra a ng accorang oe ew! and pena provision of hea.738 UTS
Snamprogett 213164 | 2230
Page 6 - 18 SPC No. Tabée 6.2.5.4
242
sr B, ot
HEAT AND MATERIAL BALANCE TABLE — Ret. PFD No
‘STREAM No 8 9
NAME
‘COMPONENT
WATER - [-
FORMyL-HORPHOLINE | = = i |
BENZENE hooo| 53 1
OTHER AROrmTIES | 0-6 | —
now ARormaTics He | 11-4 | 3926
Total Liquid Mass Flow -ka/h
Temperature “Cc
Pressure “Kylatg| 0-0 | 7-0
Siandard.iq, Density -kg/mt | — = a
Actuallig.Densty _—-kg/m™ | BGO _| 680
Vapor Mii = =
‘Vapor compressibility factor SOTTO oor ——a— oa
Fam came OAT TeMTOODT S/R Tin cots UNOOEZOAT cure
‘J Rrloocoment sth propery ol Snamproget. wo wil slaquara ts rght according oe ctl and penal provson of ne tw