S-CURVE FOR THE PROJECT
Form D1/Tender No: 1TB03-300C04
1TB03-300C04
AMAALA Triple Bay-Wellness Core - Secondary Infra. Construction
600 120%
541
529
550
521
500 100%
446
450
MANPOWER HEAD-COUNT
399
CUMULATIVE MANHOURS
400 80%
350
298
300 60%
250
200 40%
131
150
101
101
101
101
101
97
97
97
97
97
92
100 20%
78
50
0 0%
Months
Months M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-24
OverAll MP Monthly 131 298 446 529 541 521 399 101 101 101 101 101 97 97 97 97 97 92 78
% Cumulative 3% 11% 22% 35% 48% 61% 71% 74% 76% 79% 81% 84% 86% 89% 91% 93% 96% 98% 100%
MH-Monthly 34,060 77,480 115,960 137,540 140,660 135,460 103,740 26,260 26,260 26,260 26,260 26,260 25,220 25,220 25,220 25,220 25,220 23,920 20,280
MH-Cum. 34,060 111,540 227,500 365,040 505,700 641,160 744,900 771,160 797,420 823,680 849,940 876,200 901,420 926,640 951,860 977,080 1,002,300 1,026,220 1,046,500